Return to Proposal Finder FY 2001 Ongoing Proposal 199600700

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
Title Type File Size File Date


Section 1. General Administrative Information

Title of Project Proposal Irrigation Diversion Consolidation and Water Consolidation
BPA Project Proposal Number 199600700
Business name of agency, institution,
or organization requesting funding
Lemhi Soil and Water Conservation District
Business acronym (if appropriate) Lemhi SWCD
 

Proposal contact person or principal investigator

Name Patrick Marcuson
Mailing Address P. O. Box 1336
City, State, Zip Salmon, ID 83467
Phone 2087566022
Fax 2087566274
E-mail pmarcuso@idfg.state.id.us
 
Manager of program authorizing this project Patrick Marcuson
 
Review Cycle FY 2001 Ongoing
Province Mountain Snake
Subbasin Salmon
 
Short Description Irrigation consolidation of gravity diversions S-13(10 Acre Canal)with S-14 (Pope Canal)and consolidation of S-11(Edwards Canal) withS-12(Kane-Ramey Canal).Eliminate2 of 4 wingdams,2 of 4 screens,2 of 4 headgates & reduce migrational delay of all fish.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

This information comes from National Marine Fisheries Service (NMFS) and Bonneville Power Administration (BPA) reviews of this project proposal. The following table represents BPA & NMFS determinations as to this proposal's relevance to particular Biological Opinion Reasonable and Prudent Alternatives (RPAs).

Reviewing Agency Action Number BiOp Agency Description
NMFS/BPA Action 149 NMFS BOR shall initiate programs in three priority subbasins (identified in the Basinwide Recovery Strategy) per year over 5 years, in coordination with NMFS, FWS, the states and others, to address all flow, passage, and screening problems in each subbasin over 10 years. The Corps shall implement demonstration projects to improve habitat in subbasins where water-diversion-related problems could cause take of listed species. Under the NWPPC program, BPA addresses passage, screening, and flow problems, where they are not the responsibility of others. BPA expects to expand on these measures in coordination with the NWPPC process to complement BOR actions described in the action above.


Biological Outcomes of this project: Reduced delays of migrating Anadromous fish by eliminating two gravel push-up wing dams to two fish friendly diversions. Fish would be directed into the main Salmon River not back into another irrigation canal as is the present situation. Stream substrate will stabilize without the constant bull dozing of stream gravel to create wing dams across the river. All life stages of all fish will benefit.
Biological Data: By-pass pipes were previously trapped to evaluate condition, timing number of times diverted from river and speed of downstream movement of smolts through consecutive diversions.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1997 Project was designed in concept.
1998 Topographic map of sites were surveyed.
1998 Irrigators were asked if they were willing to consolidate their ditches.
1999 Preliminary designs of the diversion dams, headgates, and canal alignment and size was completed by USBR.
1999 Preliminary designs of fish screens were engineered by IDFG.
1999 More meetings with irrigators defining water saving and fish benefits of the consolidation.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

n/a or no information


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Finalize the consolidation of S-11 with S-12 and S-13 with S-14. a) Collect more water discharge data One Year $ 0  
b) Complete tasks remaining after FY2000 construction One Year $ 80,000 x
c) Build and install splitter boxes to distribute water to proper canals. One Year $140,000  
d) Rehab construction site and plant vegetation. One Year $ 25,000  
e) Educate public and users on benefits to fish. One Year $ 5,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

n/a or no information


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

n/a or no information


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

n/a or no information


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: Note: All planning and design was completed by cost shared funds. $ 0
Personnel FTE: All on site inspection and fabrication in Fish Screen Shop cost shared. $ 0
Capital Metal Fabrication $ 60,000
Subcontractor Civil contract bid winner $190,000
Personnel FTE: Note: All operating and maintenance by cost shared funds. $ 0
Personnel FTE: Note: all monitoring and evaluation by cost shared funds. $ 0
Total Itemized Budget $250,000


Total estimated budget

Total FY 2001 project cost $250,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $250,000
FY 2001 forecast from 2000 $ 0
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

Not applicable  

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed