Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Walla Walla River Juvenile and Adult Passage Improvements
BPA Project Proposal Number 199601100
Business name of agency, institution,
or organization requesting funding
Confederated Tribes of the Umatilla Indian Reservation
Business acronym (if appropriate) CTUIR
 

Proposal contact person or principal investigator

Name Gary A. James
Mailing Address P.O. Box 638
City, State, Zip Pendleton, OR 97801
Phone 5412764109
Fax 5412764348
E-mail garyjames@ctuir.com
 
Manager of program authorizing this project Gary A. James
 
Review Cycle FY 2001 Ongoing
Province Columbia Plateau
Subbasin Walla Walla
 
Short Description Provide safe passage for adult and juvenile salmonids in the Walla Walla Basin by constructing and maintaining fish passage facilities at irrigation diversion dams and canals.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: Increased survival of migrating juvenile and adult summer steelhead, bull trout, and spring chinook.
Biological Data: Since the project primarily involves construction and operation, rather than research, specific data relative to the expected biological outcome may be limited. Other data relative to the expected biological outcome is collected peripherally during other projects' objectives and tasks. Most notably, juvenile and adult distribution and survival information is collected under projects 20127 (CTUIR - WW Basin Natural Production M&E) and 9901100 (WDFW - WW Watershed Habitat and Salmonid Assessment). Project 20127 is also proposing a radio tracking study in FY2001 to evaluate adult summer steelhead passage in the basin. In addition, there are monitoring and evaluation tasks under this project to ensure that passage facilities meet design criteria.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1997 Removed Marie Dorian Dam on Walla Walla River
1998 Removed Maiden Dam on Touchet River
1998 Constructed Burlingame Dam fish ladder on Walla Walla River
1999 Constructed Burlingame fish screens and bypass on Walla Walla River
1999 Designed Garden City/Lowden II screens and ditch consolidation - to be constructed in 2000/2001
1999 Preliminary design for Hofer Dam screens and adult fishway
2000 Constructed Little Walla Walla River fish screens, trap, and fishway
2000 Constructed Nursery Bridge Dam fish ladder on Walla Walla River
2000 Constructed Smith-Nelson screens on Walla Walla River
2000 Designed Milton Ditch consolidation - to be constructed in 2000/2001
2000 Completed feasibility study on additional passage needs in Walla Walla Basin
2000 Contracted for Operation and Maintenance of BPA funded passage facilities


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Provide safe passage at diversion structures for migrating juvenile and adult salmonids in the Walla Walla Basin a. Complete final design for juvenile screens and adult fishway at Hofer Dam diversion 1 $252,000 x
b. Do final planning and design for Bergevin-Williams diversion screens 1 $141,000 x
c. Do final planning and design for Old Lowden diversion screens 1 $115,000 x
d. Do final design and planning for Titus Creek screens 1 $ 60,000 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

n/a or no information


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
2. Provide safe passage at diversion structures for migrating juvenile and adult salmonids in the Walla Walla Basin a. Construct new juvenile screens and adult fishway at Hofer Dam diversion 1 $1,008,000 x
b. Establish small project cost share fund such as conversions to pumps, jump pools, weirs, etc. ongoing $100,000 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2003 FY 2005 FY 2004 FY 2002
$100,000 $100,000 $100,000 $1,430,000


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
3. Provide safe passage at diversion structures for migrating juvenile and adult salmonids in the Walla Walla Basin a. Provide O&M at BPA funded fish passage facilities in Walla Walla Basin ongoing $150,000 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2003 FY 2005 FY 2004 FY 2002
$210,000 $230,000 $220,000 $200,000


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
4. Provide safe passage at diversion structures for migrating juvenile and adult salmonids in the Walla Walla Basin a. Evaluate seals and velocities at Little Walla Walla screen facility to ensure that they meet design criteria 1 $ 12,500 x
b. Evaluate seals and velocities at Burlingame screen facility to ensure that they meet design criteria 1 $ 12,500 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2003 FY 2002
$ 30,000 $ 27,500


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Subcontractor $568,000
Subcontractor $1,108,000
Subcontractor $150,000
Subcontractor $ 25,000
Total Itemized Budget $1,851,000


Total estimated budget

Total FY 2001 project cost $1,851,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $1,851,000
FY 2001 forecast from 2000 $250,000
% change from forecast 640.4%


Reason for change in estimated budget

The two primary reasons for the large increase over the FY2000 budget forecast are; 1) cost inflation for construction of currently implemented projects have resulted in budget shortages for previously identified projects and 2) additional projects identified for passage improvement since the original list was developed prior to ESA listings in the basin. Since ESA listings of summer steelhead and bull trout, additional projects have been identified by the Walla Walla Technical Work Group as critical for passage of these species. Many smaller projects are also being developed to improve passage conditions as a result of ESA which the requested "small project fund" would provide cost share funds of up to 50% for implementation/construction. Types of projects which would fall under this program would include conversions from gravity to pump diversions and elimination of pushup dams through use of rock weirs. The FY2000 forecast had identified only O&M costs for the outyears.


Reason for change in scope

As efforts in the basin have intensified due to the ESA listings and additional information has become available, the relative importance of various passage improvement projects has been reprioritized and new projects have been identified for implementation.


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Construction/implementation $1,430,000 $100,000 $100,000 $100,000
Operations and maintenance $200,000 $210,000 $220,000 $230,000
Monitoring and evaluation $ 27,500 $ 30,000 $ 0 $ 0
Total Outyear Budgets $1,657,500 $340,000 $320,000 $330,000
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
2001
$1,851,000
Comment:
The two primary reasons for the large increase over the FY2000 budget forecast are; 1) cost inflation for construction of currently implemented projects have resulted in budget shortages for previously identified projects and 2) additional projects identified for passage improvement since the original list was developed prior to ESA listings in the basin. Since ESA listings of summer steelhead and bull trout, additional projects have been identified by the Walla Walla Technical Work Group as critical for passage of these species. Many smaller projects are also being developed to improve passage conditions as a result of ESA which the requested "small project fund" would provide cost share funds of up to 50% for implementation/construction. Types of projects which would fall under this program would include conversions from gravity to pump diversions and elimination of pushup dams through use of rock weirs. The FY2000 forecast had identified only O&M costs for the outyears. As efforts in the basin have intensified due to the ESA listings and additional information has become available, the relative importance of various passage improvement projects has been reprioritized and new projects have been identified for implementation.

Although there has been no change in scope for this project, additional activities appear to have been added. It is not clear if these activities have been technically reviewed by an oversight committee, but they should probably be technically reviewed by the Anadromous Fish Committee prior to funding.


NWPPC Funding Recommendation Recommendation:
Do Not Fund
Date:
Sep 13, 2000
2001
$ 0
Comment:
Rationale: Previous commitments remain available for scope of work; Project has 2.4 million already committed but not contracted - carried $1million from 1999.

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$317,000
FY06 NPCC Staff Preliminary:
$317,000
FY06 NPCC July Draft Start of Year:
$317,000
Sponsor (Confederated Tribes Of The Umatilla Indian Reservation) Comments (Go to Original on NPCC Website):