Return to Proposal Finder FY 2001 Ongoing Proposal 199601900

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Second-Tier Database Support
BPA Project Proposal Number 199601900
Business name of agency, institution,
or organization requesting funding
University of Washington
Business acronym (if appropriate) UW
 

Proposal contact person or principal investigator

Name James J. Anderson
Mailing Address 1325 - 4th Ave., Suite 1820
City, State, Zip Seattle, WA 98101
Phone 2065434772
Fax 2066167452
E-mail jim@fish.washington.edu
 
Manager of program authorizing this project David Askren, BPA
 
Review Cycle FY 2001 Ongoing
Province Systemwide
Subbasin Systemwide
 
Short Description Provide single-point, Internet-based access to a subset of information to guide and support BPA's independent decisions pertaining to its responsibilities under the Power Act and Endangered Species Act.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: The suite of online historical and quasi real time operational, river condition, and fishery observations and presentation tools provides support to adaptive management practices in near term operational decisions and for longer term planning. The interactive and flexible nature of the DART interface permits exploration of cause and effect as well as comparison between past and present. This combination of adaptive management practice with flexible and inclusive data services should produce better decisions and improve species survival and recovery.
Biological Data: Biological outcomes for "system wide" or "adaptive management" projects are perhaps best measured by "global" metrics such as spawner-recruit information, including trends and targets. Such information is presently lacking or severely limited. Task 3 is intended to expand the quantity, scope, and quality of spawner-recruit information and to provide information tools to investigate cause and effect. It is anticipated that such products will improve the ability to assess system-wide biological outcomes.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1995 Initial analysis, design, and implementation of DART
1,358 weekly accesses in December 1995
Designed DART main web page
Inter-organizational contact and coordination
Automated data acquisition
Graphics design (joint effort with Dr. John Skalski's group)
1996 Interacted and coordinated with primary sites (PSMFC, USACE, FPC)
3,736 weekly accesses in April 1996
Added new river and Pit-tag features
Created numerous reports, scripts, and web pages
Created data processing scripts
Added new databases
1997 Interacted and coordinated with primary sites (PSMFC, USACE, FPC)
10,010 weekly accesses in April 1997
Updated processing scripts
Added adult features
Added CWT data, USGS data
Daily maintenance and backups
BPA interface for Technical Management Team requests
Automated reporting to USACE via BPA
1998 Interacted and coordinated with primary sites (PSMFC, USACE, FPC)
10,643 weekly accesses in April 1998
Updated processing scripts
Added PNI Index, recreational fishing page
Updated USGS data
System upgrade and migration to data warehouse status
Built Pit-tag ESU at the request of Technical Management Team
Daily maintenance and backups
Responded to 111,000 web customers via DART web services
1999 Interacted and coordinated with primary sites (PSMFC, USACE, FPC)
10,590 weekly accesses in April 1999
Added hourly water quality at the request of USACE
Upgraded graphics
Upgraded and added new reporting functions for USGS and USACE
Rewrote scripts to process FPC and USACE data files
Upgraded the system
Upgraded ESU at the request of Technical Management Team
Daily maintenance and backups
Y2K conversion for all internal applications
Responded to 238,000 web customers via DART web services
2000 Interacted and coordinated with primary sites (PSMFC, USACE, FPC)
17,481 weekly accesses in April 2000
Added oceanographic and climate data
Upgraded DART to E-450 Solaris
Gave ISRP review of DART and on-site demo at CBR/UW
Tested conversion to Oracle capabilities with recommendations to BPA
Added JavaDart (java graphics for advanced users)
Upgraded coded wire tag database on the web
Preliminary design for a spawner-recruit database for BPA
Responded to 51,784 web customers (number for Jan-Apr) via DART web services
Daily maintenance and backups


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

n/a or no information


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

n/a or no information


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Data services for modeling, monitoring, and evaluation 1a. Electronic data integration $ 30,000  
1b. Monitoring and evaluation $ 30,000  
2. Data access in real-time 2a. Coordination with primary sites $ 20,000  
2b. Historical dataset development $ 20,000  
2c. Daily services $ 30,000  
2d. System support services $ 35,000  
2e. DART graphical analysis development $ 33,000  
3. DART habitat function 3a. Develop database for online data access and analysis of spawner-recruit information $ 30,000  
3b. Obtain historical spawner-recruit data and associated habitat information $ 20,000  
3c. Develop web based maps and system to access habitat and stream data $ 20,000  
3d. Develop online analysis tools for evaluating spawner-recruit information 2001 $ 25,000  
4. Regional information management review 4a. Conduct review meetings and draft initial recommendation proposal 2001 $ 25,000  
4b. Coordinate workshop on development of specifications for a regional web based fisheries information system 2001 $ 27,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2003 FY 2005 FY 2004 FY 2002
$373,152 $403,601 $388,078 $358,800


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

n/a or no information


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: 12 mo. salaries for PI, admin asst., scientist, webpub., webprog, analyst, data mgr & system adm. $184,198
Fringe Standard UW benefit rates $ 47,661
Supplies $ 4,000
Travel Trips to attend regional meetings $ 2,000
Indirect 26% of Modified total direct costs $ 64,236
Other Services & Lease $ 42,905
Total Itemized Budget $345,000


Total estimated budget

Total FY 2001 project cost $345,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $345,000
FY 2001 forecast from 2000 $198,000
% change from forecast 74.2%


Reason for change in estimated budget

The proposed budget is 74% larger than forecast last year due to the inclusion of tasks 3 and 4. Task 4 anticipates ISRP recommendations to improve regional information planning and coordination. Task 3 reflects the need for consistent performance measures for assessing recovery and system wide adaptive management efforts. The remaining work approximates what was previously estimated at $198k.


Reason for change in scope

Objective 3 augments project scope to develop an online, interactive data service focused upon the spawner-recruit metric and related habitat and environmental information. The service is intended to be a decision support tool that integrates spawner-recruit and environmental information in an "all-H" manner similar to that already demonstrated for juvenile migration and its environmental conditions. The emphasis of the first three tasks is to improve access to the broad range of relevant information and its presentation. Analytical tools developed in task 4 will be subject to review by users. Objective 4 augments project scope to anticipate the ISRP's pending review of regional data management review findings. BPA expects the ISRP to recommend improved coordination between regional information managers and services. Objective 4 provides for the coordination of a workshop on specifications for a regional web based fisheries information system.


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Operations and maintenance $358,800 $373,152 $388,078 $403,601
Total Outyear Budgets $358,800 $373,152 $388,078 $403,601
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: no; New Funding: no
Date:
Jul 14, 2000
2001
$ 0
Comment:
This project is proposing new work that has not been technically reviewed. This work also addresses a course of action (reliance on spawner-recruit models) that has not been agreed upon within the basin. It is premature to fund this work until a larger discussion on these issues is completed and the NWPPC Amendment Process is concluded. This would also put an intensive analysis task within a data base project. These tasks would be better addressed as a new proposal for FY 2002.

The proposed budget is 74% larger than forecast last year due to the inclusion of new tasks 3 ($95,000) and 4 ($52,000). Task 4 anticipates ISRP recommendations to improve regional information planning and coordination. Task 3 reflects the need for consistent performance measures for assessing recovery and system wide adaptive management efforts. The remaining work approximates what was previously estimated at $198,000.

This project should not be funded as part of the Fish and Wildlife Program since it is not subject to the same standards of the regional review process. This project also appears to duplicate efforts supported within other data management projects (i.e. Streamnet).


BPA Funding Recommendation Recommendation:
Date:
Sep 8, 2000
[There are no budget numbers associated with this review.]
Comment:
CBFWA comment: This project is proposing new work that has not been technically reviewed. This work also addresses a course of action (reliance on spawner-recruit models) that has not been agreed upon within the basin. It is premature to fund this work until a larger discussion on these issues is completed and the NWPPC Amendment Process is concluded. This would also put an intensive analysis task within a data base project. These tasks would be better addressed as a new proposal for FY 2002. The proposed budget is 74% larger than forecast last year due to the inclusion of new tasks 3 ($95,000) and 4 ($52,000). Task 4 anticipates ISRP recommendations to improve regional information planning and coordination. Task 3 reflects the need for consistent performance measures for assessing recovery and system wide adaptive management efforts. The remaining work approximates what was previously estimated at $198,000. This project should not be funded as part of the Fish and Wildlife Program since it is not subject to the same standards of the regional review process. This project also appears to duplicate efforts supported within other data management projects (i.e. Streamnet).

BPA response: An FY01 budget could be developed that "just" keeps the database going. That amount would be approximately $170,000. This assumes that other existing contracts with Skalski and Anderson, which underwrite common infrastructure and integrate part time employment of critical staff, would be funded. Should either component be reduced or removed, the continuity of service would be threatened. A stand-alone DART contract would cost about $250,000 annually. In the meantime, BPA suggests to the Council that an independent contractor be selected and funded to evaluate each of the regional databases in order to objectively determine where there is and is not overlap or redundancy. The objective of this work would not be to evaluate the merits of the various databases, but simply to compare and contrast. The information provided to the Council should help inform a decision about which database(s) to continue funding from the Direct Program.


NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$170,000
Comment:
Bonneville requires. Budget assumption from BPA comment because of continuation of other related contracts.

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$264,075
FY06 NPCC Staff Preliminary:
$264,075
FY06 NPCC July Draft Start of Year:
$264,075
Sponsor (U of W) Comments (Go to Original on NPCC Website):