Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Restore McComas Meadows/ Meadow Creek Watershed
BPA Project Proposal Number 199607711
Business name of agency, institution,
or organization requesting funding
Nez Perce Fisheries/Watershed Program
Business acronym (if appropriate) NPT
 

Proposal contact person or principal investigator

Name Heidi Mcroberts
Mailing Address P.O. Box 365
City, State, Zip Lapwai, ID 83540
Phone 2088437406
Fax 2088437310
E-mail heidim@nezperce.org
 
Manager of program authorizing this project Ira Jones, Director of Watershed Management
 
Review Cycle FY 2001 Ongoing
Province Mountain Snake
Subbasin Clearwater
 
Short Description Restore, enhance, and protect the diversity of physical and biological habitat characteristics of Meadow Creek and associated wetland areas to provide quality habitat for chinook salmon and steelhead trout through working with an overall watershed approac
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: The expected biological outcomes from this project will be decreased sediment delivery to streams, restore riparian vegetation which will provide shade, in turn reducing stream temperatures, and restore the natural channel morphology to the stream. Sediment abatement from the Fisher Placer mine site will improve spawning habitat within this watershed. Improving aquatic organism habitat is the overall expected biological outcome resulting from this project. The excepted biological outcomes will be measured as part of an overall Monitoring and Evaluation Plan, which is under development by the Nez Perce Tribe Fisheries/Watershed Program. This plan will address in-stream physical and biological characteristics, as well as riparian characteristics.
Biological Data: Stream habitat characteristic data, including but not limited to temperature, cobble embeddedness, percent fines, pool to riffle ratios, width-depth ratios, woody regeneration, channel cross sections, large woody debris, macroinvertebrates, redd counts, and fish densities has been collected . The M & E plan which is under current development will address any data gaps that may be present.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1996 Salmon Corps removes 4 miles of posts, rails, and barbed wire fence
1997 Construct 3.0 miles of riparian/meadow protection fence
1998 Construct 0.5 miles of riparian/meadow protection fence
1998 Installation of water table wells for groundwater monitoring
1999 Installation of automatic temperature recorders, gauging station, and data collection
1999 Re-vegetation planning


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Coordinate with technical advisory work group and the Nez Perce National Forest on associated with BPA projects. a. Attend work group meeting on projects within the Meadow Creek watershed. 1 and on-going and year-to-year $ 1,992  
1. b. Coordinate on logistics of projects with the Meadow Creek Watershed. 1 and on-going and year-to-year $ 2,625  
2. Complete NEPA Analysis to restore hydrological characteristics of the watershed. a. Complete cultural resource consultation. 1 and on-going and year-to-year $ 1,475  
2. b. Complete ESA consultation. 1 and on-going and year-to-year $ 5,646  
2. c. Complete application for permits. 1 and on-going and year-to-year $ 6,633  
3. Complete design for sediment abatement at Fisher Placer Mine Site. a. Hire a sub-contractor to complete the design. 1 and on-going and year-to-year $ 1,469  
3. b. Oversee sub-contractor in the completion of the design. 1 and on-going and year-to-year $ 15,979 x
4. Manage project to effectively accomplish project goals. a. Develop project time schedules. 1 and on-going and year-to-year $ 3,197  
4. b. Update and communicate with all entities involved in the Policy Advisory Group. 1 and on-going and year-to-year $ 1,468  
4. c. Prepare quarterly and annual reports. 1 and on-going and year-to-year $ 4,243  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

FY 2003 FY 2005 FY 2004 FY 2002
$ 54,100 $ 65,500 $ 59,500 $ 49,200


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Restore meadow and riparian plant communities to enhance fish and wildlife habitat. a. Evaluate re-vegetation design. 1 and on-going and year-to-year $ 2,732  
1. b. Purchase/gather vegetation for planting. 1 and on-going and year-to-year $ 6,531  
1. c. Plant vegetation. 1 and on-going and year-to-year $ 12,912  
2. Reduce sediment delivery to the stream, stabilize stream banks, and improve water quality. a. Gather materials for Swede Creek Construction Project. 1 and on-going and year-to-year $ 6,387  
2. b. Complete construction (bioengineering) on Swede Creek (tributary to Meadow Creek). 1 and on-going and year-to-year $ 15,439 x
2. c. Plant riparian vegetation to enhance bank stabilization. 1 and on-going and year-to-year $ 1,767  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2003 FY 2005 FY 2004 FY 2002
$ 55,400 $ 67,000 $ 60,900 $ 50,350


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Maintain cattle exclosure fence. a. Repair any damaged or destroyed sections of fence. 1 and on-going and year-to-year $ 5,635  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2003 FY 2005 FY 2004 FY 2002
$ 6,800 $ 8,250 $ 7,500 $ 6,200


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Monitor and evaluate stream characteristics a. Collect data on stream characteristics, which are limiting factors, as determined by prior research and watershed assessments. 1 and on-going and year-to-year $ 9,589  
1. b. Collect measurements at stream gauging station, and analyze this data. 1 and on-going and year-to-year $ 3,577  
2.Monitor and evaluate regeneration of wetland characteristics a. Collect water table measurements. 1 and on-going and year-to-year $ 3,578  
3. Monitor success of fence in excluding cattle from grazing effects on meadow riparian habitat. a. Evaluate over-winter damage of fence during the spring. 1 and on-going and year-to-year $ 3,577  
3. b. Monitor the regeneration of riparian vegetation. 1 and on-going and year-to-year $ 3,574  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2003 FY 2005 FY 2004 FY 2002
$ 28,900 $ 35,000 $ 31,800 $ 26,300


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: 3 $ 15,330
Fringe 30% $ 4,599
Supplies Office Supplies $ 50
Travel GSA Vehicle & Per Diem $ 3,500
Indirect 26.61% $ 6,248
NEPA In coord. with NPNF $ 5,000
Subcontractor Sediment Abatement Design $ 10,000
Personnel FTE: 3 $ 15,100
Fringe 30% $ 4,530
Supplies Vegetation, fence repair materials, office supplies, erosion control matting $ 7,000
Travel GSA Vehicles & Per Diem $ 3,200
Indirect 26.61% $ 7,938
Subcontractor Heavy Equipment Rental $ 5,000
Other Training $ 3,000
Personnel FTE: 3 $ 3,000
Fringe 30% $ 450
Supplies Fencing tools $ 500
Travel GSA Vehicle & Per Diem $ 500
Indirect 26.61% $ 1,185
Personnel FTE: 3 $ 11,210
Fringe 30% $ 3,363
Supplies Monitoring equipment $ 1,800
Travel GSA Vehicle & Per Diem $ 2,500
Indirect 26.61% $ 5,022
Total Itemized Budget $120,025


Total estimated budget

Total FY 2001 project cost $120,025
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $120,025
FY 2001 forecast from 2000 $120,000
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

The addition of sediment abatement for the Fisher Placer Mine site was not previously planned, but with the development of the Meadow Creek Watershed Assessment, this project has been identified as a priority. This project will help to decrease the sediment delivery to the stream, which will help to improve spawning areas. This objective is still within the overall goals of the project.


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Planning and design $ 49,200 $ 54,100 $ 59,500 $ 65,500
Construction/implementation $ 50,350 $ 55,400 $ 60,900 $ 67,000
Operations and maintenance $ 6,200 $ 6,800 $ 7,500 $ 8,250
Monitoring and evaluation $ 26,300 $ 28,900 $ 31,800 $ 35,000
Total Outyear Budgets $132,050 $145,200 $159,700 $175,750
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

This project has not yet been reviewed