Return to Proposal Finder FY 2001 Ongoing Proposal 199705600

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Lower Klickitat Riparian and In-Channel Habitat Enhancement Project
BPA Project Proposal Number 199705600
Business name of agency, institution,
or organization requesting funding
Yakama Nation
Business acronym (if appropriate) YN
 

Proposal contact person or principal investigator

Name Melvin R. Sampson
Mailing Address PO. Box 151
City, State, Zip Toppenish, WA. 98948
Phone 5098656262
Fax 5098656293
E-mail mel@yakama.com
 
Manager of program authorizing this project Melvin R. Sampson
 
Review Cycle FY 2001 Ongoing
Province Columbia Gorge
Subbasin Klickitat
 
Short Description Lower Klickitat (RM 1-43) watershed/instream habitat restoration. Use completed steelhead/chinook EDT to prioritize restoration by effected life stage and location to guide action (i.e. fencing, acquisitions, pool formation, augment baseflows, add LWD).
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: Through restoration efforts within the stream channel and adjacent uplands, available habitat is anticipated to double for spawning, juvenile rearing, velocity refugia, and adult holding. The project work is also expected to improve water quality by reducing erosion, filtrating and storing fine sediments, augmenting canopy cover for temperature moderation, and reducing livestock waste from entering waters. Juvenile survival rates will be improved by reducing stream temperatures through increasing riparian vigor. EDT analysis of restoration activities will be used to gauge success of moving from Patient (Current) to Template (Historic) habitat conditions. Investigations in BC, WA. and OR., clearly shown the critical importance of in-channel habitat and adjacent riparian stands for salmonid production (Binns 1994, House 1996, Beschta 1991). Recent habitat enhancement/riparian revegetation work by the YN has created additional rearing area and demonstrated use by juvenile salmonids.
Biological Data: Five years of steelhead spawner data exists for estimating escapement into Project tributaries. Population estimates (fish/m2) derived from screw trapping, electrofishing and snorkeling surveys on all Project tributaries. Timber Fish and Wildlife (TFW) Ambient Monitoring data (pool, riffle, run area m2 and volume m3, channel confinement, gradient, substrate composition, LWD counts, canopy cover) and stream temperature data exists for all Project tributaries. Under YKFP guidelines, baseline data collection was initiated to populate both spring chinook and steelhead EDT model. The EDT steelhead model encapsulates information outlined above into a predicative model used to estimate increases in productivity as habitat conditions move towards template (historic) conditions by way of habitat restoration. EDT analysis will drive restoration by identifying the critical life stages affected and the specific habitat attribute that limits production on a reach-by-reach basis.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1997 Initial TFW habitat inventory of entire Swale Creek stream corridor.
1997 Project initiation, landowner involvement, and town meetings.
1998 Completion of Project Supplemental Analysis and finding of consistency with Watershed Management Program EIS (DOE/EIS-0265)
1998 Constructed 2 base flow augmentation ponds with a total watershed of 617 acres of agricultural lands.
1999 Constructed 5 base flow augmentation ponds with a total watershed of 1505 acres of agricultural lands.
1998 Fenced and revegetate 2 base flow augmentation ponds.
1999 Fenced and revegetate 5 base flow augmentation ponds.
1998 Constructed 6 miles of cattle exclosure fencing, protecting 6 miles of riparian habitat.
1999 Constructed 8 miles of cattle exclosure fencing, protecting 16 miles of riparian habitat.
1998 Revegetate 4 miles of riparian corridor.
1999 Revegetate 3 miles of riparian corridor.
1998 Completed engineering design plans for 1/2 mile of in-channel work for lower Swale Creek.
1999 Completed engineering design plans for milldam passage enhancement as cost-share project.
1998 Installed off-channel watering system on 1,200 acre Swale Creek sheep ranch.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Manage Project Funds to Implement Project Goals and Biological Outcomes a. Foster and develop additional community based support. 4 $ 2,500  
b. Participate in watershed groups and councils. Develop focus and direction for Klickitat basin aquatic resources. 4 $ 7,500  
c. Meet with perspective landowners for project participation. 4 $ 10,000  
d. Solicit additional project funds through various sources for cost-share opportunities. 4 $ 2,000  
e. Query recently completed Klickitat basin spring chinook and steelhead EDT model and other databases to identify and prioritize restoration actions with benefits. 4 $ 15,000  
f. Using available information, generate conceptualized plans for in-channel structures, riparian restoration actions, and grazing management plans. 4 $ 10,000  
g. Develop sub-contracts with labor force, engineering contractors, and construction contractors to implement planned actions 4 $ 2,000  
h. File all necessary permits, and NEPA related documentation. 4 $ 2,000  
i. Write periodic progress reports and annual report. 4 $ 2,344  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 66,700 $ 59,500 $ 63,000 $ 56,200


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Restore aquatic habitat through construction of in-Channel (bio-engineered) structures. Creation of habitat currently limiting production by life stage as outlined in EDT model. a. Construct in-channel habitat structures, using existing bioengineering guidelines with proven contractors. 4 $ 90,000 x
b. Construct streambank stabilization structures, using existing bioengineering protocol with proven contractors 4 $ 53,000 x
2. Restore aquatic habitat and reduce water temperatures through construction of riparian exclosures (fencing/plantings). Recreate habitat currently limiting production by life stage as outlined in EDT model. a. Plant native vegetation in identified locations to restore streambank stabilization, and canopy shading. 4 $ 20,000 x
b. Construct riparian fencing to exclude livestock from riparian zone. 4 $ 40,000 x
c. Construct water gaps or off-channel watering facilities in association with riparian fencing projects. 4 $ 8,000 x
3. Restore upland health and function that directly affects aquatic habitat. Recreate habitat currently limiting production by life stage as outlined in EDT model. a. Collaborate with NRCS officials and landowners to implement Grazing Management Plan. 4 $ 1,000  
b. Implement Grazing Management Plan, through use of fencing, alternative lease site cost-share or purchase 4 $ 10,368  
c. Cost-share with non-till farming demonstration plots in Klickitat County. 4 $ 6,000  
4 . Protect Refugia Habitat, identified within the EDT model. Protect high quality habitat, which enhances overall production as identified in EDT model. a. Investigate land acquisition opportunities and potential. Develop appraisal protocol with BPA. 4 $ 1,000  
b. Develop cost-share protocol with Columbia Land Trust 4 $ 1,000  
c. Develop Habitat Conservation Easements with NRCS officials and landowners. 4 $ 1,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2005 FY 2003 FY 2004 FY 2002
$250,000 $250,000 $250,000 $237,700


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Maintain existing structures in working condition. a. Conduct fence line surveys. Note: 75% of Task 1.a, born by SRFB grant to maintain all Klickitat Basin restoration projects. 4 $ 2,000 x
b. Conduct periodic inspections to assure 80% survival of riparian planting, and restock as needed. 4 $ 1,000 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 10,000 $ 6,000 $ 8,000 $ 4,000


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Continue monitoring and evaluation of existing structures and restored areas using standardized protocols to determine Project effectiveness. a. Continue and implement additional standardized vegetation transects within Project locations 4 $ 6,000  
b. Continue and implement additional photo documentation points at Project sites. 4 $ 5,000  
c. Continue and implement additional TFW habitat inventory transects at Project sites. 4 YKFP in-kind $ 0  
d. Continue and implement additional standardized fisheries inventories (electrofishing or snorkeling) at Project sites. 4 YKFP in-kind $ 0  
2. Assess Monitoring Information a. Conduct semi-annual M&E reviews 4 $ 288  
b. Based on semi-annual M&E review, implement new habitat restoration action to meet project goals 4 $ 1,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 15,000 $ 13,000 $ 14,000 $ 12,000


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: 0.6 $ 21,600
Fringe 20 % fringe rate $ 4,320
Supplies Miscellaneous supplies and materials, computer, GIS supplies, telephone $ 8,000
Travel Training and/or project presentation $ 1,500
Indirect 23.5 % $ 8,324
Subcontractor No subcontractors needed for Project Management $ 0
Other GSA vehicle rental. insurance, and mileage $ 9,600
Personnel FTE: 0.2 $ 7,200
Fringe 0 $ 1,440
Supplies Fencing, vegetation stock and tools, off-channel water supply materials (pumps, screens) $ 11,197
Indirect 23.5 % $ 4,661
Capital Grazing Management Plan implementation, cost-share alternative lease sites, cost-share no-till plots $ 15,870
Subcontractor In-Channel (1.a) and Bank Stabilization (1.b) subcontractors. $143,000
Subcontractor Labor Force to conduct Tasks (2.a - 2.c). Existing contact w/ Northwest Service Academy (NWSA). $ 48,000
Personnel FTE: 0 $ 0
Supplies Maintenance materials identified in supplies line item under Construction/Implementation Phase $ 0
Subcontractor NWSA labor force, in conjunction with Klickitat County SRFB maintenance crew (in-kind) $ 3,000
Personnel FTE: 0.2 $ 7,200
Fringe $ 1,440
Supplies Materials to conduct monitoring: film, photo-point stations, and measuring tapes. $ 1,500
Indirect 23.5 % $ 2,148
Total Itemized Budget $300,000


Total estimated budget

Total FY 2001 project cost $300,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $300,000
FY 2001 forecast from 2000 $300,000
% change from forecast 0.0%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Planning and design $ 56,200 $ 59,500 $ 63,000 $ 66,700
Construction/implementation $237,700 $250,000 $250,000 $250,000
Operations and maintenance $ 4,000 $ 6,000 $ 8,000 $ 10,000
Monitoring and evaluation $ 12,000 $ 13,000 $ 14,000 $ 15,000
Total Outyear Budgets $309,900 $328,500 $335,000 $341,700
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
2001
$300,000
Comment:
There is no change in scope or budget forecast.

NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$268,632
Comment:
Rationale: Budget increase inappropriate in this review. Budget increases should be determined in provincial review.

NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 20, 2003
2004 2005 2006
$397,414 $397,414 $397,414

Funding Category: Expense

Comment:
Name change. Project has September 1 start. Obligation and accrual estimates are changed because of that. Many cost shares and several subcontracts that are coming on line. 6% COLA in 05.

Project Sponsor Request for FY04-05 Recommendation:
Date:
Sep 20, 2003
2004 2005
$397,414 $414,259

Funding Category: Expense

Comment:

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$397,414
FY06 NPCC Staff Preliminary:
$397,414
FY06 NPCC July Draft Start of Year:
$397,414
Sponsor (Confederated Tribes And Bands Of The Yakama Indian Nation) Comments (Go to Original on NPCC Website):