Return to Proposal Finder FY 2001 Ongoing Proposal 199801005

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Pittsburg Landing, Capt. John Rapids, Big Canyon Fall Chinook Acclimation Facilities
BPA Project Proposal Number 199801005
Business name of agency, institution,
or organization requesting funding
Nez Perce Tribe
Business acronym (if appropriate) NPT
 

Proposal contact person or principal investigator

Name Bruce M. Mcleod
Mailing Address P.O. Box 365
City, State, Zip Lapwai, ID 83540
Phone 2088437320 x4
Fax 2088432351
E-mail Brucem@NezPerce.org
 
Manager of program authorizing this project Silas Whitman
 
Review Cycle FY 2001 Ongoing
Province Blue Mountain
Subbasin Mainstem Snake
 
Short Description Supplement natural production of Snake River fall chinook above Lower Granite Dam through acclimation, final rearing and release of Lyons Ferry yearling and subyearling fish at two sites on the Snake River and one site on the Clearwater River.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: The smolt to adult return rate is expected to be equal to the Lyons Ferry Hatchery return rate of 0.269%. Each year 1345 adults may return above Lower Granite Dam as a result of these annual releases. Additional adults will return from subyearling releases above Lower Granite Dam. In 1999, a total of 1279 adults returned to Lower Granite Dam as a result of previous releases from the acclimation sites. The immediate goal of the project is to ensure that naturally spawning Snake River fall chinook salmon do not go extinct. Long term goals of the project are: 1. Increase the natural population of Snake River fall chinook spawning above Lower Granite Dam. 2. Sustain long-term preservation and genetic integrity of this population. 3. Keep the ecological and genetic impacts of non-target fish populations within acceptable limits. 4. Assist with the recovery of Snake River fall chinook to remove from ESA listing. 5. Provide harvest opportunities for tribal and non-tribal anglers.
Biological Data: All yearling releases are coded wire tagged and externally marked with a unique colored elastomer tag to identify their release site. Returning adult fall chinook salmon are tallied each year as they are passed above Lower Granite Dam. Fish that are identified as being released from the acclimation sites are passed upstream to spawn naturally. At the end of each return year, a stock composition report is prepared to account for the origin of all fall chinook trapped at or passed above Lower Granite Dam. Redd counts are conducted in spawning areas above Lower Granite Dam and carcasses recovered and identified by their release site. The monitoring and evaluation of yearling Snake River fall chinook released upstream of Lower Granite Dam is covered under BPA project 9801004. BPA projects 9403400 and 9801003 work closely with the fall chinook acclimation project in assessing restoration and spawning distribution of Snake River fall chinook.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1996 Pittsburg Landing assembled and operated, 114K yearlings released. Adult returns not complete until 2000.
1997 Pittsburg Landing operated, 147K yearlings released; Big Canyon assembled and operated, 198K yearlings and 253K subyearlings acclimated and released. Adult returns data not complete until 200l.
1998 Pittsburg Landing operated, 124K yearlings released; Big Canyon operated, 61K yearlings released; Capt. John Rapids constructed and operated, 133K yearlings released. Adult return data not complete until 2002.
1998 A total of 464 adult fall chinook returned above Lower Granite Dam from previous acclimation site releases. A total of 263 fall chinook redds counted in the Snake and Clearwater Rivers
1999 Pittsburg Landing operated, 147K yearlings released; Big Canyon operated, 229K yearlings and 347K subyearlings released; Capt. John Rapids operated, 157K yearlings and 323K subyearlings released.
1999 A total of 1279 adult fall chinook returned to Lower Granite Dam from previous upstream releases at the three acclimation sites. A total of 552 fall chinook salmon redds were counted in the Snake and Clearwater Rivers.
2000 U.S. v Oregon, PAC estimates 2,461 fall chinook adults from acclimation releases above Lower Granite Dam will return to the Snake and Clearwater Rivers in 2000.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

n/a or no information


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

n/a or no information


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Supplement natural production of Snake River fall chinook above Lower Granite Dam through acclimation and final rearing of fish from Lyons Ferry Hatchery. a. Coordination/planning/report writing 1 $ 73,000  
b. Assembly and disassembly of facilities l $145,000  
c. Fish transport, acclimation and release l $396,000  
d. Maintenance of equipment and facilities 1 $103,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2005 FY 2003 FY 2004 FY 2002
$860,000 $784,000 $825,000 $756,000


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

n/a or no information


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: 7.18 $232,700
Fringe $ 47,000
Supplies $137,500
Travel 80% for field crew per diem and mileage $ 23,650
Indirect $117,750
Capital $ 57,000
Subcontractor Fish health pathology; Water pump rent; Equipment rent for assembly and disassembly of facililties $101,400
Total Itemized Budget $717,000


Total estimated budget

Total FY 2001 project cost $717,000
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $717,000
FY 2001 forecast from 2000 $720,000
% change from forecast - 0.4%


Reason for change in estimated budget

Not applicable


Reason for change in scope

Not applicable


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Operations and maintenance $756,000 $784,000 $825,000 $860,000
Total Outyear Budgets $756,000 $784,000 $825,000 $860,000
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
2001
$694,033
Comment:
The budget has been adjusted due to a change in the indirect cost rate.

There is no change in the scope of work.


NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$660,000
Comment:

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$729,635
FY06 NPCC Staff Preliminary:
$729,635
FY06 NPCC July Draft Start of Year:
$729,635