Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Acquire Oxbow Ranch--Middle Fork John Day River
BPA Project Proposal Number 200001500
Business name of agency, institution,
or organization requesting funding
Confederated Tribes of the Warm Springs Reservation of Oregon
Business acronym (if appropriate) CTWSRO
 

Proposal contact person or principal investigator

Name Shaun W. Robertson
Mailing Address P.O. Box 480
City, State, Zip Canyon City, OR 97820
Phone 5415754212
Fax 5415754212
E-mail ctwsjdbo@highdesertnet.com
 
Manager of program authorizing this project Terry Luther
 
Review Cycle FY 2001 Ongoing
Province Columbia Plateau
Subbasin John Day
 
Short Description Acquire the remaining 540.0 acres of the Oxbow Ranch, protect, enhance, and maintain a total of 1,022 acres of riverine, meadow, and forest habitat on the Middle Fork John Day River.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: Improvements in river corridor and wet meadow habitat types, water quality, and fish and wildlife production.
Biological Data: The John Day Basin Office (JDBO), Nature Conservancy, and Monument High School maintains permanent monitoring stations on the property for the purpose of measuring trends in water quality. The JDBO also cooperates with the ODFW in conducting annual spring chinook and steelhead spawning ground counts and conducting bull trout investigations. The JDBO is also preparing a management plan for the entire property which includes monitoring actions including a modified Hankin & Reeves evaluation and other biological investigations. The JDBO and OSU has conducted a study of corridor water temperatures using forward looking infrared radar.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1999 The Nature Conservancy of Oregon acquires the Middle Fork tract of the Oxbow Ranch.
2000 The CTWSRO acquires approximately 486.45 acres of The Nature Conservancy's Middle Fork holding.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Restoration of approximately 105 acres (2.0 stream miles) of disturbed dredge tailings. a. Complete a hydrologic analysis of possible restoration alternatives 0.25 $ 5,000 x
b. Complete an engineering survey and restoration design. 0.25 $ 10,000 x
c. Complete a cultural resource survey and consultation with the SHPO 0.25 $ 4,000 x
d. Complete an endangered species survey and consultation with USFWS/NMFS 0.25 $ 1,600  
e. Prepare a tailings restoration plan. 0.50 $ 3,200  
f. Complete the NEPA analysis, 401/404 certification 0.25 $ 1,600  
Continue preparation of a management plan including identification of restoration alternatives and monitoring actions. a. Using the information gathered in FY2000, assess alternatives for management including status of water rights, property line adjustments, and other similar. 0.67 $ 5,989  
b. Technical assistance on management/restoration plan. .25 $ 5,000 x
Indirect Costs 41.4% of total excepting subcontracts and capital items. N/A $ 5,369  
Supplies Printing and distribution of contract solicitations, compliance documents, and etc. N/A $ 100  
Travel Associated with above tasks N/A $ 480  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 5,000 $ 5,000 $ 5,000 $ 10,000


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Acquire remaining acres of Oxbow Ranch a. Capital Acquisition 0.25 $1,630,000  
b. Complete closing, negotiate MOA with BPA, other miscellaneous legal 0.25 $ 13,000  
Phase 1 restoration of approximately 105 acres/2.0 stream miles of disturbed dredge tailings. a. Construction 0.08 $ 70,000 x
b. Riparian plantings on remediated area .08 $ 1,000 x
Project Oversight Personnel to oversee above contracts/activities N/A $ 7,792  
Travel Contract administration N/A $ 480  
Supplies Contract solicitations/bid packages, printing and other miscellaneous N/A $ 100  
Indirect Costs 41.4% of total excepting subcontracts and capital items. N/A $ 8,848  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 5,000 $ 40,000 $ 5,000 $100,000


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Upgrade and maintain perimeter fencing a. Upgrade 2.0 miles of boundary fence (North boundary) 0.25 $ 3,800  
b. Upgrade 2.5 miles of boundary fence (West boundary) 0.25 $ 4,750  
c. Perform maintenance on 1.5 miles of boundary fence 0.08 $ 2,250  
Maintain interior fencing a. Perform maintenance on approximately 10.0 miles of interior fence (low priority) 0.25 $ 1,000  
Personnel Implementation of above tasks N/A $ 16,817  
Travel Vehicle for manager N/A $ 2,700  
Indirect Costs 41.4% of total excepting subcontracts and capital items. N/A $ 13,172  
Maintain managers residence Electricity and phone. 1.0 $ 2,100  
Weed mapping and control Supplies & equipment for weed mapping and control N/A $ 500  
Reimbursement to TNC Payment for materials supplied by TNC for reroofing house. N/A $ 11,025 x


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 10,000 $ 15,000 $ 15,000 $ 10,000


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
Monitoring Plan Implement monitoring portion of management plan. 0.50 $ 12,274  
Supplies Monitoring supplies and equipment N/A $ 12,500  
Travel Vehicle for manager N/A $ 2,700  
Indirect Costs $ 11,374  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 20,000 $ 10,000 $ 15,000 $ 15,000


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: 0.29 total $ 10,080
Fringe $ 2,309
Supplies Miscellaneous office supplies, printing, mailing, and etc. $ 100
Travel $ 480
Indirect 41.4% of total excepting subcontracts and capital items. $ 5,369
Subcontractor Hydrologic analysis of restoration alternatives $ 5,000
Subcontractor Engineering survey and restoration design $ 10,000
Subcontractor Cultural resource survey and consultation $ 4,000
Subcontractor Technical assistance from TNC on management plan. $ 5,000
Personnel FTE: 0.25 total $ 6,320
Fringe $ 1,472
Supplies $ 100
Travel $ 480
Indirect 41.4% of total excepting subcontracts and capital items. $ 8,848
Capital Acquire 540.0 acres of Oxbow Ranch from The Nature Conservancy $1,630,000
Subcontractor Equipment and operator rental $ 70,000
Subcontractor Use existing Monument Nursery Contract $ 1,000
Other Closing costs and legal fees $ 13,000
Personnel FTE: 0.60 total $ 13,600
Fringe $ 3,217
Supplies $ 12,300
Travel 0.5 GSA lease vehicle $ 2,700
Indirect 41.4% of total excepting subcontracts and capital items. $ 13,172
Subcontractor TNC: roof materials $ 11,025
Other Phone and electricity $ 2,100
Personnel FTE: 0.50 $ 10,400
Fringe $ 1,874
Supplies $ 12,500
Travel 0.5 GSA lease vehicle $ 2,700
Indirect $ 11,374
Total Itemized Budget $1,870,520


Total estimated budget

Total FY 2001 project cost $1,870,520
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $1,870,520
FY 2001 forecast from 2000 $ 75,000
% change from forecast 2394.0%


Reason for change in estimated budget

The FY2001 budget forecast was based upon receiving the entire capital acquisition cost in FY2000. However, the Northwest Power Planning Council approved one-half of the acquisition cost and designated the entire acquisition as an "ongoing" project under their program, with the remaining funds to be secured in FY2001. Discounting the capital costs in FY2001, the percent change from forecast is only +34%.


Reason for change in scope

Restoration costs had not been identified in FY1999, when this project was submitted. Preliminary restoration opportunities have been identified and anticipated costs have been calculated.


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Planning and design $ 10,000 $ 5,000 $ 5,000 $ 5,000
Construction/implementation $100,000 $ 40,000 $ 5,000 $ 5,000
Operations and maintenance $ 10,000 $ 15,000 $ 15,000 $ 10,000
Monitoring and evaluation $ 15,000 $ 10,000 $ 15,000 $ 20,000
Total Outyear Budgets $135,000 $ 70,000 $ 40,000 $ 40,000
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: yes; New Funding: yes
Date:
Jul 14, 2000
2001
$1,774,120
Comment:
The FY 2001 budget forecast was based upon receiving the entire capital acquisition cost in FY 2000; however, the Northwest Power Planning Council approved one-half of the acquisition cost and designated the entire acquisition as an "ongoing" project under their program, with the remaining funds to be secured in FY2001. Discounting the capital costs in FY 2001, the percent change from forecast is only +34%.

Restoration costs had not been identified in FY1999, when this project was submitted. Preliminary restoration opportunities have been identified and anticipated costs have been calculated. The one change in scope was made to include tailings removal and was not identified in the FY 2000 proposal. Section 3, Objective 1 and Section 4, Objective 2 for a total of $96,400. The CEOR SRT supports this activity.


NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$1,782,546
Comment:

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year: