Return to Proposal Finder FY 2001 Ongoing Proposal 200001900

Proposal Table of Contents

Additional Documents

Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Tucannon River Spring Chinook Captive Broodstock Program
BPA Project Proposal Number 200001900
Business name of agency, institution,
or organization requesting funding
Washington Department of Fish and Wildlife
Business acronym (if appropriate) WDFW
 

Proposal contact person or principal investigator

Name Joseph D. Bumgarner
Mailing Address 401 South Cottonwood
City, State, Zip Dayton, WA 99328
Phone 5093824755
Fax 5093822427
E-mail bumgajdb@dfw.wa.gov
 
Manager of program authorizing this project Joseph D. Bumgarner
 
Review Cycle FY 2001 Ongoing
Province Columbia Plateau
Subbasin Tucannon
 
Short Description Complete modifications to Lyons Ferry Hatchery to conduct spring chinook captive broodstock program. Rear and spawn broodstock, raise their progeny and release 150,000 smolts into the Tucannon River to rebuild spring chinook run and prevent extinction.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: For FY2001, very few biological outcomes are expected except for the possible collection of gametes (eggs) from 1997 brood year spawners. This will also provide the program with the first data to examine fecundities of mature females (3 year-olds), fertilization success, egg viability, and initial survival rates of their progeny. WDFW will continue to track survival and maturation rates on each brood year in captivity.
Biological Data: The data that will be available to measure biological outcomes are as follows: Survival of captive brood (for each year) will be determined from the starting population of each brood year and subtracting out mortalities and maturing fish. Eggs from each spawned female will be incubated separately to count the number of eggs, and mortality records will be kept for each female's eggs to determine fertilization success and viability. Following swim up of fry, all progeny will be mixed. Their survival will be compared each month to the supplementation (production) fish in the hatchery to determine if there are any obvious differences between survival of fish from captive brood or standard supplementation.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): anadromous


Section 2. Past Accomplishments

Year Accomplishment
1997 Collect 1997 brood year eggs (from supplementation program) to initiate captive broodstock.
1998 Collect 1998 brood year eggs (from supplementation program) to continue captive broodstock.
Rear 1997 brood year juveniles at Lyons Ferry Hatchery.
Planning, site modification designs, and budget proposal for captive broodstock program.
Submit FY2000 proposal to CBFWA under the NPPC Fish and Wildlife Program for review and funding by BPA.
1999 Collect 1999 brood year eggs to continue captive broodstock program.
Use LSRCP funds ($120,000) to begin site modifications at Lyons Ferry Hatchery.
Rear and mark by "family" the 1997 and 1998 brood year juveniles.
Write and submit Tucannon Master Plan for 3-Step Review process.
Partially complete site modifications at LFH (ponds to rear captive year fish, but no security, alarms, or overhead covers).
Work with BPA in Drafting the Environmental Assessment for NEPA compliance.
Monitor and document mortality of captive brood fish (1997 and 1998 broods).
2000 Work with BPA to complete Environmental Assessment for NEPA compliance.
Reply to questions from the ISRP on the Tucannon Master Plan of the captive broodstock program: Master Plan Accepted by ISRP and NPPC.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

n/a or no information


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

n/a or no information


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Provide safekeeping of captive broodstock a. Solicit bids, and select contractor to install security fencing around the perimeter of the captive brood rearing ponds. 1 $ 14,000  
2. Provide cover for rearing ponds (reduce sun damage to ponds and provide additional cover to fish). a. Solicit bids, and select contractor to construct an open pole building (roof only) over the captive brood rearing ponds. 1 $ 11,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

n/a or no information


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Raise captive brood fish a. Conduct daily rearing and raising of captive brood fish (daily feeding, pond cleaning, medical treatments to control mortalities, basic hatchery record keeping for feed fed, mortalities, water inflow, etc…) 6 $ 20,900  
2. Spawn mature captive brood fish a. Sort mature fish from immature fish, and separate mature fish to spawning tank. Conduct weekly checks for ripeness during spawning season, and spawn all ripe fish and incubate fertilized eggs 7 $ 6,850  
3. Rear captive brood progeny a. Pick and record all dead eggs after shocking and determine fecundity and mortality of eggs from each spawned female. Incubate fry until ponding, and then place all captive brood progeny in standard raceways for rearing. 6 $ 8,300  
4. Disseminating or collating information a. Attend captive broodstock meetings, workshops, etc.. to learn or pass on information from/to others regarding captive broodstock program 8 $ 1,800  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 55,000 $ 55,500 $ 60,000 $ 47,500


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Monitor and document survival, mortality, and maturity rates of captive brood fish. a. Assist hatchery staff in monthly record keeping of mortalities and maturation (by family groups) for each brood year. 8 $ 11,400  
2. Monitor and document mortality, survival, and viability of captive brood progeny. a. Assist hatchery staff in egg picking to determine mortality, survival, fecundity, and egg viability of collected captive brood eggs that were fertilized. 8 $ 2,300  
3. Permanently identify all 15 families from the 1999 brood year for captive broodstock rearing. a. Assist hatchery and tagging staff with marking (CWT and VI) of 1999 brood year fish for captive broodstock rearing. 3 $ 1,200  
4. Spawn mature captive brood adults a. Assist hatchery staff in sorting and spawning of mature captive broodstock (Obj 2, Task a, O&M phase) 7 $ 8,870  
5. Conduct Genetic Monitoring a. Collect, send, and analyze DNA samples from captive broodstock spawners and from parents to captive broodstock program (2000 BY) 8 $ 10,000  
6. Disseminating or collating information a. Attend captive broodstock meetings, workshops, etc.. to learn or pass on information from/to others regarding captive broodstock program 8 $ 1,800  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 71,500 $ 66,000 $ 66,000 $ 47,000


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Capital Security Fencing, Overhead Pond Cover Building $ 25,000
Personnel FTE: Hat Spec 2 (0.25 FTE), CM (0.08 FTE), Fish Health (0.08 FTE) $ 15,950
Fringe Calculated at 28.5% $ 4,550
Supplies Misc Equip (brushes, nets, screens, buckets, crowders, etc…), chemical supplies (formalin) $ 5,500
Travel $ 1,000
Indirect Agency Overhead at 23.5% $ 6,350
Other Fish Food, Utilities, Water Pumping Costs $ 4,500
Personnel FTE: Fish Biologist (0.17 FTE), Fish Tech (0.08 FTE) $ 11,050
Fringe Calculated at 28.5% $ 3,150
Supplies Genetic sampling and analysis, Fish marking (BWT/No ad), broodstock marking $ 13,600
Travel $ 1,000
Indirect Agency Overhead at 23.5% $ 6,770
Total Itemized Budget $ 98,420


Total estimated budget

Total FY 2001 project cost $ 98,420
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $ 98,420
FY 2001 forecast from 2000 $ 75,000
% change from forecast 31.2%


Reason for change in estimated budget

The FY20001 Budget increased because of a shortfall in completing the capital construction for the project with FY2000 funds. Some of the necessary plumbing parts to complete the facility modifications were more costly than originally expected. Also, labor and transportation costs were higher than expected. The amount requested by WDFW in FY2001 for capital construction is $25,000. By subtracting that amount from the FY2001 proposal, the O&M and M&E portion of the project is $73,675, about 1,400 off the initial projected cost identified in the FY2000 project proposal.


Reason for change in scope

The scope of the project has not changed.


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Operations and maintenance $ 47,500 $ 55,500 $ 60,000 $ 55,000
Monitoring and evaluation $ 47,000 $ 66,000 $ 66,000 $ 71,500
Total Outyear Budgets $ 94,500 $121,500 $126,000 $126,500
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
2001
$ 98,420
Comment:
The FY 2001 budget increased because of a shortfall in completing the capital construction for the project with FY 2000 funds. Some of the necessary plumbing parts to complete the facility modifications were more costly than originally expected. Also, labor and transportation costs were higher than expected. The amount requested by WDFW in FY 2001 for capital construction is $25,000. By subtracting that amount from the FY 2001 proposal, the O&M and M&E portion of the project is $73,675, about $1,400 off the initial projected cost identified in the FY 2000 project proposal.

NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$ 98,420
Comment:

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year: