Section 1. General Administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget Summary

Reviews and Recommendations
No documents associated with this request


Section 1. General Administrative Information

Title of Project Proposal Rainwater Wildlife Area Operations & Maintenance
BPA Project Proposal Number 200002600
Business name of agency, institution,
or organization requesting funding
Confederated Tribes of the Umatilla Indian Reservation
Business acronym (if appropriate) CTUIR
 

Proposal contact person or principal investigator

Name Allen Childs
Mailing Address P.O. Box 638
City, State, Zip Pendleton, OR 97801
Phone 5412787626
Fax 5412787673
E-mail AllenChilds@ctuir.com
 
Manager of program authorizing this project Carl Scheeler
 
Review Cycle FY 2001 Ongoing
Province Columbia Plateau
Subbasin Walla Walla
 
Short Description Protect, enhance, and mitigate wildlife habitat impacted by McNary and John Day hydroelectric projects. Project includes O&M to protect existing habitat values, enhancements to increase habitat quantity and quality, and M&E to assess project benefits.
Target Species


Project Location

[No information]


Reasonable and Prudent Alternatives (RPAs)

Sponsor-Reported Relevant RPAs

Sponsor listed no RPAs for this project proposal

Relevant RPAs based upon NMFS & BPA Review

NMFS and BPA did not associate any reasonable and prudent alternatives with this project proposal


Biological Outcomes of this project: The Rainwater Wildlife Area was developed by the CTUIR to offset wildlife habitat losses related to the John Day and McNary hydroelectric projects. The area is located off-site and will provide mitigation primarily in-kind. Key target wildlife mitigation species include: spotted sandpiper, great blue heron, yellow warbler, mink, Western meadowlark, black-capped chickadee, and downy woodpecker, blue grouse, and mule deer. An estimated 7,120 Habitat Units (HU's), quantified using Habitat Evaluation Procedures (USFWS, 1980) , will be generated from the project. In addition, the project will provide dual benefits for both fish and wildlife with over 8 miles of spawning and rearing habitat for summer steelhead, bull trout, and resident rainbow trout in the upper South Fork Touchet River. The project is anticipated to protect and enhance upland, riparian/wetland, and instream habitat and provide significant watershed scale benefits for a wide variety of indigenous fish and wildlife.
Biological Data: A baseline HEP analysis is very near completion for the project. Approx 12 miles of grassland, 4 miles forest, and 7 miles riparian transects survey for baseline habitat evaluations completed in 1999. In conjunction with transects, over 400 micro plots and 40 macro plots inventoried. Aquatic inventories completed to date include over 9 miles of presence/absence fish sampling, fish population surveys, and fish habitat surveys (modified Hankin and Reeves methodology). Data tabulation and input has been completed. Data is currently being summarized and reports being prepared for both terrestrial and aquatic resources.


CBFWA-Generated Information

Database Administrator notes on the history of this proposal form: None
Type of Project (assigned by CBFWA Analysts): wildlife


Section 2. Past Accomplishments

Year Accomplishment
1998 Land Acquisition (8,441 acres) completed 9/98. Milestone: Habitat Protection through fee title acquisition (riparian/wetland, upland native grassland and forested cover types)
1998 Interim Property Management Plan Developed & Implemented (Public Use Regulations, Access & Travel Plan).
1998 Posted signs/maps for public information on property regulations.
1998 Initiated Public Involvement for Management Planning Process. Established stakeholder advisory committee. Conducted stakeholder and public meetings to develop project scoping document for management plan.
1999 Completed HEP field surveys (completed over 23 miles of transect survey, 400+ micro plots (sq. m), and 40+ macro plots (1/10 acre).
1999 Completed aquatic resource and habitat surveys on over 9 miles of fish bearing streams (DNR Fisheries Program funding).
1999 Acquired additional 300 acres of private land within boundary of Rainwater Wildlife Area (interior parcels).
1999 Secured $100K through WA State Gov. Office Salmon Recovery Program for fish habitat and watershed restoration work on wildlife area (road obliteration, instream large woody debris additions, tree and shrub planting). Implement 2000.
1999 Completed Mgmt Plan Scoping Document and conducted public review process to solicit input on property management.
1999 Conducted regular, monthly advisory committee meetings to develop management plan (ongoing).
1999 Conducted meetings with multiple agencies to coordinate property management (WADNR, WDFW, Columbia Co.)
2000 Completed installation of informational kiosks and signage for public information on interim property management.
2000 Ongoing coordination with agencies and advisory committee.
2000 Ongoing interim mgmt, public outreach, and coordination.
2000 Initiated appraisal/timber cruise on additional 250 acres of interior private land for acquisition.


Section 3. Relationships to Other Projects

n/a or no information


Section 4. Budget for Planning and Design Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Plan and design detailed habitat enhancements in forested, grassland, and riparian habitat types identified in management plan to maintain and increase habitat quality and quantity for downy woodpecker, black-capped chickadee, a. Identify and delineate forested stands with overstocked stand conditions. Program for pre-commercial thinning to reduce competition/increase tree growth and cover development. Estimated 1,000 acres. Schedule 100 acres/yr. 1, ongoing $ 4,000  
1. cont--great blue heron, yellow warbler, spotted sandpiper, mink, western meadowlark, mule deer, and blue grouse. Specific objectives include: increasing basal area, snag density, cover quality, forage quality, and habitat security. b. Identify and delineate understocked forest stands. Program for site preparation (prescribed fire/mechanical) and tree planting where natural regeneration has not occurred due to competing vegetation. Est 500 acres. Schedule 50 acres/yr. 1, ongoing $ 3,000  
c. Develop grassland restoration and enhancement strategies. Schedule treatments (prescribed burning and seeding) on an estimated 2,000 acres (200 acres/yr.) 1, ongoing $ 3,000  
d. Develop and program riparian habitat enhancement and restoration strategies on 500 to 800 acres. 1, ongoing $ 4,000  
e. Complete detailed road mgmt plan developed under management plan. Schedule road obliteration and decommissioning. Estimated 20-30 miles of road work planned to restore resource production on 80-120 acres of primarily forested habitats. 1, ongoing $ 3,000  
2. Solicit cost-share funding to implement habitat enhancement and restoration activities from state, federal, and private organizations. 1, ongoing $ 1,868  
3. Conduct necessary environmental compliance review for site-specific project activities. a. Prepare NEPA/SEPA documentation for site-specific project activities. 1, ongoing $ 3,000  
b. Prepare appropriate permit applications for site-specific activities (404 permits, WA Forest Practice Act permit applications, hydrologic permits, etc.) 1, ongoing $ 3,000  
c. Conduct site specific archaeological surveys and TES specific reviews/surveys. 1, ongoing $ 5,300  
d. Prepare Biological Assessments for TES species and consult with appropriate agency for concurrence. 1, ongoing $ 4,000  
4. Identify and pursue additional land acquisitions to consolidate land ownership within and adjacent to wildlife area. a. Contact potential willing sellers and initiated appraisal processes in preparation for acquisitions. (limited primarily to small, <320 acre parcels). 1, ongoing $ 2,000  
5. Secure 2002 O&M Funding a. Prepare and submit NPPC FY2002 O&M project proposal 1, ongoing $ 1,000  
6. Prepare for Project Construction/Implementation. a. Prepare construction contract requests for proposals, conduct project site reviews, develop construction contracts, perform as contract representative/COTR. 1, ongoing $ 1,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Planning and Design Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 46,393 $ 42,080 $ 44,184 $ 40,076


Section 5. Budget for Construction and Implementation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Enhance habitat quality in forested cover types. a. Conduct pre-commercial thinning on approx 100 acres to reduce tree competition, improve tree growth, and facilitate cover development. 1, ongoing $ 20,000 x
b. Conduct tree planting in forested stands to improve tree stocking and facilitate cover development. Estimated 50 acres/yr. (15,000 seedlings consisting of p-pine, western larch, and Douglas-fir). 1, ongoing $ 18,000  
c. Obliterate and decommission roads to restore resource production. Includes winged ripping, tree planting, and seeding. Estimated 6-10 miles/yr. 1, ongoing $ 14,000  
2. Enhance habitat quality in grassland cover types. a. Conduct prescribed burning to assist in noxious weed control and prepare sites for seeding and planting. Estimated 200 acres/yr depending on availability of native seed. 1, ongoing $ 20,000 x
b. Conduct broadcast seeding and range drilling on acreage treated with prescribed burning. Focus on native grassland species (blue bunch wheatgrass, Idaho fescue, and Sandberg's bluegrass) and appropriate non-native seed mix. 1, ongoing $ 15,000  
3. Restore/enhance riparian habitat a. Plant riparian shrubs and trees following instream and floodplain restoration activities including large woody debris additions, channel/meander construction, and road decommissioning efforts. 10,000 trees/shrubs installed. 1, ongoing $ 10,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Construction and Implementation Phase

FY 2005 FY 2003 FY 2004 FY 2002
$117,905 $106,944 $112,291 $101,851


Section 6. Budget for Operations and Maintenance Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Provide Wildlife Area Administration - Protect Existing Resources and Habitat Values a. Administer Mgt. Plan Regulations and Access & Travel Mgt. Plan including conducting road patrols, documenting violations, and coordinating w/ local law enforcement. 1, ongoing $ 15,000  
b. Monitor and address trespass livestock, dumping, illegal uses, etc. and respond appropriately (i.e., contacting livestock owners for removal, garbage clean-up, law enforcement notifications. 1, ongoing $ 10,000  
c. Maintain public information utilizing kiosks/sign boards, infield public outreach 1, ongoing $ 5,000  
2. Maintain/Protect Habitat Values in forested, grassland, and riparian habitat types. a. Implement weed management plan including prevention, manual, chemical, and biological treatments. Activities include removing vectors (vehicles/livestock), spot application of herbicides, hand-pulling, presc fire (spot and landscape treatments) 1, ongoing $ 12,000  
b. Conduct fire mgt activities including wildfire prevention and suppression. Prevention includes monitoring local fire conditions and imposing access & use restriction as necessary. Suppression includes coord w/ WADNR on initial attack/supp. tactics. 1, ongoing $ 15,000  
c. Maintain boundary fences to limit unauthorized livestock use. Approx 8 miles. 1, ongoing $ 16,000  
d. Conduct annual road maintenance to prevent road loss and resource damage. Task includes maintaining drainage, cleaning culverts, limited grading 1, ongoing $ 5,000  
e. Maintain gates and other road closure devices to prevent resource damage from motorized vehicles, limit road maintenance needs, and to maintain wildlife habitat security. 1, ongoing $ 4,000  
f. Maintain Forested Habitats: maintain seedlings installed under implementation effort to improve survival. Task includes managing competing vegetation, protection devices, shade cards. 1, ongoing $ 8,000  
g. Maintain Grassland Habitats: --conduct ongoing noxious weed mgt to maintain treated and existing native plant communities. 1, ongoing $ 9,633  
h. Maintain Riparian Habitats: Conduct ongoing noxious weed control. Maintain seedlings installed under implementation effort to improve survival. Task includes protection devices, shade cards, limited watering. 1, ongoing $ 12,000  
3. Administer Rainwater Wildlife Area Project a. Prepare and manage project contract. Task include preparing scope of work and contrat, administering contract with BPA. 1, ongoing $ 14,000  
b. Prepare annual/semi annual reports per contract agreements. 1, ongoing $ 2,000  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Operations and Maintenance Phase

FY 2005 FY 2003 FY 2004 FY 2002
$155,139 $140,715 $147,751 $134,015


Section 7. Budget for Monitoring and Evaluation Phase

Task-based Budget

Objective Task Duration in FYs Estimated 2001 cost Subcontractor
1. Conduct monitoring and evaluation to assess progress towards meeting project objectives and to identify necessary changes (adaptive management) in management strategies to meet resource needs. a. Take annual photo points at permanent monitoring stations to provide photo image of changes in habitat types. 1, ongoing $ 4,000  
Note: HEP monitoring to be conducted on approx 10 yr interval and is not included in annual M&E. HEP update scheduled to begin in FY2011. b. Conduct regular monitoring of access and travel mgt. plan to determine effectiveness of road mgt plan and whether wildlife habitat security is being maintained. 1, ongoing $ 5,000  
c. Monitor public use including temporal and spatial utilizing variety of methods such as traffic counters, infield surveys, hunter check stations. 1, ongoing $ 3,000  
d. Conduct surveys on permanent vegetation plots (reconnaissance plots) to monitor changes in vegetative composition. Includes structural and composition analysis to determine effectiveness of treatments (seeding, planting, and noxious weed treatments). 1, ongoing $ 8,000  
e. Conduct annual water quality monitoring, redd surveys, and juvenile fish population surveys. 1, ongoing $ 4,576  


Outyear Objective-Based Budget

n/a or no information


Outyear Budgets for Monitoring and Evaluation Phase

FY 2005 FY 2003 FY 2004 FY 2002
$ 29,872 $ 27,095 $ 28,450 $ 25,805


Section 8. Estimated Budget Summary

Itemized Budget

Item Note FY 2001 Cost
Personnel FTE: 0.4 $ 14,165
Fringe @30% $ 4,249
Supplies $ 8,250
Travel $ 1,819
Indirect @34% $ 9,685
NEPA Included in personnel above $ 0
Personnel FTE: .56 $ 19,046
Fringe @30% $ 5,714
Supplies $ 13,400
Travel $ 3,638
Indirect @34% $ 10,811
NEPA included under planning (personnel) $ 0
Subcontractor heavy equipment/operator rental, labor crews, veg collection/propagation $ 44,391
Personnel FTE: 1.06 $ 38,032
Fringe @30% $ 11,409
Supplies $ 28,550
Travel $ 10,914
Indirect @34% $ 30,228
Subcontractor weed control contract, heavy equipment rental contract $ 8,500
Personnel FTE: 0.33 $ 11,401
Fringe @30% $ 3,420
Supplies $ 1,700
Travel $ 1,819
Indirect @34% $ 6,236
Total Itemized Budget $287,377


Total estimated budget

Total FY 2001 project cost $287,377
Amount anticipated from previously committed BPA Funds $ 0
Total FY 2001 budget request $287,377
FY 2001 forecast from 2000 $287,377
% change from forecast 0.0%


Reason for change in estimated budget

No change


Reason for change in scope

n/a


Cost Sharing

Not applicable
 

Outyear Budget Totals

2002 2003 2004 2005
Planning and design $ 40,076 $ 42,080 $ 44,184 $ 46,393
Construction/implementation $101,851 $106,944 $112,291 $117,905
Operations and maintenance $134,015 $140,715 $147,751 $155,139
Monitoring and evaluation $ 25,805 $ 27,095 $ 28,450 $ 29,872
Total Outyear Budgets $301,747 $316,834 $332,676 $349,309
 

Other Budget Explanation

Not applicable


Reviews and Recommendations

This information was not provided on the original proposals, but was generated during the review process.

CBFWA Funding Recommendation Recommendation:
Date:
Jul 14, 2000
2001
$287,377
Comment:

NWPPC Funding Recommendation Recommendation:
Fund
Date:
Sep 13, 2000
2001
$279,744
Comment:
Rationale: Budget increase inappropriate in this review.

NW Power and Conservation Council's FY 2006 Project Funding Review Funding category:
expense
Date:
May 2005
FY05 NPCC Start of Year:
$304,926
FY06 NPCC Staff Preliminary:
$304,926
FY06 NPCC July Draft Start of Year:
$304,926
Sponsor (Confederated Tribes Of The Umatilla Indian Reservation) Comments (Go to Original on NPCC Website):