Rescheduling Request for FY 2006, Project 199304000

 
Access CBFWA's Status of the Resource (SOTR) website or BPA's Report Center for more information on project 199304000
SOTR Project & Correspondence
Project
Pisces Report
Project Status Work Funded
Section 1: General Administrative Information
BPA Project Number: 199304000
BPA Project Name: Fifteen Mile Habitat Improvement
BPA Contract Number,
Release and Name
(if applicable):
COTR/BPA Project Manager: John Baugher
Agency, Institution or Organization Requesting Rescheduling: ODFW
Funding Type: expense
Contact Person
First Name: Brian
Last Name Benjamin
Address: 3561 Klindt Dr.
City, State Zip: The Dalles, OR. 97058
Phone: 541 296-8026
Fax: 541 296-7889
Email: brian.d.benjamin@state.or.us

Section 2: Financial Information/Budget for Rescheduled Activities
Original Budget for Rescheduled Activities FY 2006: $46,000
Proposed Budget for Rescheduled Activities FY 2007: $46,000
Explanation or Additional Information: Additional requirements and long delays by BPA NEPA staff reviews did not allow the on the ground implementation to be completed within the performance period.

Section 3: Financial Information/Budget for Rescheduled Activities
Activity Description Original Start Date Original End Date New Start Date New End Date Condition/Situation Creating the Need to Reschedule Cost What Will Enable the Work to be Achieved Now?
To implement 1 mile of fence construction and 2 off site water developments  4/1/2006  9/30/2007  10/1/2007  12/31/2007  See above  $00  Having Environmental Clearance 

Please explain why the following alternative funding solutions are not feasible and would jeopardize the project:
Reducing existing scope of project
(i.e., eliminating some activities planned for FY 2007 to accommodate the FY 2006 activities)
This would prevent completing much of the similar new work planned in FY08.
Shifting entire schedule
(i.e., deferring some FY 2007 activities to FY 2008 to avoid doubling up on activities this year)
This would prevent completing as much work on the ground in as timely a manner. There is no problem with the ability to implement both the rescheduled and the new contract work within the same period of time since this is not a lot of work relative to our abilty to implement it.

Section 4: Documents Pertaining to this Reschedule