Rescheduling Request for FY 2007, Project 200200200

 
Access CBFWA's Status of the Resource (SOTR) website or BPA's Report Center for more information on project 200200200
SOTR Project & Correspondence
Project
Pisces Report
Project Status Work Funded
Section 1: General Administrative Information
BPA Project Number: 200200200
BPA Project Name: Restore Natural Recruitment of Kootenai River White Sturgeon
BPA Contract Number,
Release and Name
(if applicable):
COTR/BPA Project Manager: Virgil Watts
Agency, Institution or Organization Requesting Rescheduling: BPA
Funding Type: expense
Contact Person
First Name: Sue
Last Name Ireland
Address: County Rd. 38A
City, State Zip: Bonners Ferry Idaho 83805
Phone: (208) 267-3620
Fax:
Email: ireland@kootenai.org

Section 2: Financial Information/Budget for Rescheduled Activities
Original Budget for Rescheduled Activities FY 2007: $1,735,000
Proposed Budget for Rescheduled Activities FY 2008: $1,735,000
Explanation or Additional Information: The rescheduling of unspent project funds from the 2007 project budget to the 2008 project budget; the amount of reschedule is approximately $1,735,000.

Section 3: Financial Information/Budget for Rescheduled Activities
Activity Description Original Start Date Original End Date New Start Date New End Date Condition/Situation Creating the Need to Reschedule Cost What Will Enable the Work to be Achieved Now?

Please explain why the following alternative funding solutions are not feasible and would jeopardize the project:
Reducing existing scope of project
(i.e., eliminating some activities planned for FY 2008 to accommodate the FY 2007 activities)
Shifting entire schedule
(i.e., deferring some FY 2008 activities to FY 2009 to avoid doubling up on activities this year)

Section 4: Documents Pertaining to this Reschedule
No documents are associated with this request