Rescheduling Request for FY 2007, Project 200207200

 
Access CBFWA's Status of the Resource (SOTR) website or BPA's Report Center for more information on project 200207200
SOTR Project & Correspondence
Project
Pisces Report
Project Status Work Funded
Section 1: General Administrative Information
BPA Project Number: 200207200
BPA Project Name: Protect and Restore Red River Watershed
BPA Contract Number,
Release and Name
(if applicable):
COTR/BPA Project Manager: Dave Kaplowe
Agency, Institution or Organization Requesting Rescheduling: Bonneville Power Administration
Funding Type: expense
Contact Person
First Name: Dave
Last Name Kaplowe
Address: 905 NE 11th Ave
City, State Zip: Portland, OR 97232
Phone: 503-230-5365
Fax: 503-230-4564
Email: djkaplowe@bpa.gov

Section 2: Financial Information/Budget for Rescheduled Activities
Original Budget for Rescheduled Activities FY 2007: $458,924
Proposed Budget for Rescheduled Activities FY 2008: $458,924
Explanation or Additional Information: Due to delays with appraisal, appraisal review, appraisal revisions and cost share submissions, $458,924 has been requested to be re-scheduled from 08 to O9.

Section 3: Financial Information/Budget for Rescheduled Activities
Activity Description Original Start Date Original End Date New Start Date New End Date Condition/Situation Creating the Need to Reschedule Cost What Will Enable the Work to be Achieved Now?
Completion of conservation easement  12/1/2007  11/30/2008  12/1/2008  11/30/2009  Significant delays in appraisal, appraisal review, appraisal revisions and cost share submissions  $00  The appraisal revisions will be finalized and the cost share contributions will be submitted. 

Please explain why the following alternative funding solutions are not feasible and would jeopardize the project:
Reducing existing scope of project
(i.e., eliminating some activities planned for FY 2008 to accommodate the FY 2007 activities)
This is an internal BPA contract created with funds from the FY 08 project expense allocation. Reducing the 08 scope would forfeit the majority of the easement funds, resulting in a complete loss of the conservation easement.
Shifting entire schedule
(i.e., deferring some FY 2008 activities to FY 2009 to avoid doubling up on activities this year)
A re-schedule of funds from 08 to 09 is the only way the conservation easement can be secured.

Section 4: Documents Pertaining to this Reschedule
No documents are associated with this request