Rescheduling Request for FY 2007, Project 200739600

 
Access CBFWA's Status of the Resource (SOTR) website or BPA's Report Center for more information on project 200739600
SOTR Project & Correspondence
Project
Pisces Report
Project Status Work Funded
Section 1: General Administrative Information
BPA Project Number: 200739600
BPA Project Name: 2007-396-00 Walla Walla Basinwide Tributary Passage & Flow
BPA Contract Number,
Release and Name
(if applicable):
COTR/BPA Project Manager: Jay Marcotte
Agency, Institution or Organization Requesting Rescheduling: BPA
Funding Type: capital
Contact Person
First Name: Rick
Last Name Jones
Address:
City, State Zip: Walla Walla, WA
Phone: 509-522-6340, x3
Fax:
Email: rick.jones@my180.net

Section 2: Financial Information/Budget for Rescheduled Activities
Original Budget for Rescheduled Activities FY 2007: $1,453,120
Proposed Budget for Rescheduled Activities FY 2008: $1,453,120
Explanation or Additional Information: Reschedule funds from FY07 and FY08 to FY09. This BiOp combined capital project has been delayed due to cultural resources and other factors. Designs for the GFID piping project are now nearly complete and other piping being done by WWBWC is ready to begin.

Reschedule $319,577 from FY07 and $1,133,543 from FY08 to cover construction/ implementation.

Projects are now getting started, with the 2009 spring/summer period a crucial period for getting on-the-ground work done.


Section 3: Financial Information/Budget for Rescheduled Activities
Activity Description Original Start Date Original End Date New Start Date New End Date Condition/Situation Creating the Need to Reschedule Cost What Will Enable the Work to be Achieved Now?
Install Gardena Farms South Lateral Pipeline  8/1/2007  10/31/2008  8/1/2009  10/31/2009  Cultural resources, other factors  $900,000  CR complete, new management, designs are ready 
Pipe 3 ditches; 4 aquifer recharge expansions; 3-4 in-canal reservoirs  9/1/2007  8/31/2009    8/31/2010  Cultural resource issues, economy caused cost-share partners to balk  $553,120  CR issues are cleared up, most cost share partners are back on board or new ones recruited 

Please explain why the following alternative funding solutions are not feasible and would jeopardize the project:
Reducing existing scope of project
(i.e., eliminating some activities planned for FY 2008 to accommodate the FY 2007 activities)
Project 2007-396-00 is a combination of project proposals from the last solicitation. Projects were combined to meet BPA's capital criteria. Reducing the scope of the project would affect the parties' ability to complete their originally proposed work.

Not constructing the pipelines could affect BPA's ability to meet it's obligations under the BiOp.

Shifting entire schedule
(i.e., deferring some FY 2008 activities to FY 2009 to avoid doubling up on activities this year)
Deferring tasks would not help with these discreet capital projects. Funding was requested to cover design and construction and is not necessarily expected to continue into FY2010 and beyond.

Projects are ready to begin this spring/summer, with landowners and partners ready and waiting.