Within-Year Modification Request Form for FY 2007

 
Access CBFWA's Status of the Resource (SOTR) website or BPA's Report Center for more information on
Project 198805301 (Province: Blue Mountain Subbasin: Grande Ronde )
SOTR Province View
Status & Trends Projects Interactive Map Report
SOTR Subbasin View
Status & Trends Projects Interactive Map Report
SOTR Project & Correspondence
Project
Pisces Report
Project Status Work Funded

View Modification

Table of Contents
Part 1. Administration and Budgeting
Section 1: General Administrative Information
Section 2: Description
Section 3: Related Projects
Section 4: Planning and Design
Section 5: Construction/Implementation
Section 6: Operations and Maintenance
Section 7: Monitoring and Evaluation
Section 8: Total Budget
Section 9: Project Documents
Part 2. Current Status of Modification Request
Part 3. Comments on this Modification Request


Part 1 of 3. Administration and Budgeting
Section 1: General Administrative Information
Process Information:
Date Proposal Submitted & Finalized Status BOG Meeting Date
July 9, 2007 Finalized August 8, 2007

Modification Type: FY 2007 Within-Year Ongoing
BPA Project Number: 198805301
BPA Project Name: Grande Ronde/Imnaha Endemic Spring Chinook Supplementation - Northeast Oregon Hatchery
COTR/BPA Project Manager: Kenneth Kirkman
Agency, Institution or Organization Requesting Rescheduling: Nez Perce Tribe
Funding Type: expense
Project Leader: Greg Haller
Province: Blue Mountain
Subbasin: Grande Ronde
 
Contact Person
First Name: Greg
Last Name Haller
Address: P.O. Box 365
City, State Zip: Lapwai, Idaho 83540
Phone: 208-843-7320
Fax: 208-843-2351
Email: gregh@nezperce.org

Administrative Contacts
Primary Administrative Contact Secondary Administrative Contact:
Name Arleen Henry Name Kelly Wasson
Address: P.O. Box 365 Address: P.O. Box 365
City, State Zip: Lapwai, Idaho 83540 City, State Zip: Lapwai, Idaho 83540
Phone: 208-843-7317 Phone: 208-843-7317
Fax: 208-843-7319 Fax: 208-843-7319
Email: arleenh@nezperce.org Email: kellyw@nezperce.org
Note: NPT accountant Note: NPT Finance Department manager

Section 2a: Description (Species Information)
Target Species Oncorhynchus tshawytscha (chinook)

Provide explanations as to why the following alternative funding solutions are not feasible and will jeopardize the project:
Reduction in existing scope of project: Reducing the "existing scope of the project" will not address the problems with the BPA facility.
Deferral of existing work elements to later date: Many of the maintenance issues are of immediate concern and need to be addressed as soon as possible.

Section 2b: Description (Location Information)
Location(s) at which the action will be implemented
Latitude Longitude Location Description
45.42 N 117.44 W The BPA facility is located on Granger Rd. approximately 6 miles upriver from the town of Lostine.

Is this/Are these the same study location(s) that was/were identified in the original proposal? Yes

Condition/situation creating the need for the modification:
Is the situation the result of a catastrophic event that occurred within the existing location? Yes
Has a habitat/population/mechanical/structural dilemma developed in the proposed study location since the contract was signed with BPA? Yes

Section 2c: Description (Work Element Information)
What work elements in the existing proposal does the proposed modification address?
Work Element Work Element Title
#119 Manage and Administer Projects Manage and Administer NEOH Project
#170 Council 3 Step Process Final Design Planning

Proposed action to achieve the objective(s) As part of managing and administering this project (#119), we propose to maintain the BPA property on Granger Road and implement the General Road Maintenance Agreement for Granger Road between BPA and Wallowa County. The buildings and grounds were purchased by BPA as future components of the Lostine River Hatchery facility and are part of the final design planning (#170). However, the vacant buildings have not been maintained in the past and are in need of repair. We seek funding to repair plumbing problems and associated damage in both the main house and guest house. Both the wooden batter board siding and wood deck are in a neglected condition. We request funds to clean, stain and seal these wood structures. The surrounding grounds are overgrown with high grass and weeds. This dry plant material has created a severe fire hazard to the BPA property as well as to other neighborhood homes. We seek funding to maintain a greenbelt lawn around the buildings. The unimproved access road (Granger Rd.)leading to the BPA house is maintained by the Nez Perce Tribe through agreement with BPA and Wallowa County. We request funds to implement the agreement and participate with the neighbors in the maintenance of the road.

Does not implementing this modification jeopardize the ability to achieve existing biological objectives of this project, as well as other projects? Yes

Explain: Not implementing this modification will indirectly jeopardize our ability to achieve the objectives associated with the NEOH project. The BPA house and grounds were purchased as an integral component of the Lostine River Hatchery. Not maintaining the BPA house and grounds now will increase future costs and limit funds available that contribute directly towards achieving biological objectives. Not implementing the road maintenance agreement now will create additional maintenance costs and create bad will with the County and neighbors. The public relations objectives of the project will also be enhanced by implementing this modification.

Section 2d: Description (BiOp Information)
NMFS and/or FWS Biological Opinion that this funding request addresses Strategy
NMFS &/or USFWS
How proposed actions will address the BiOp
(i.e., substrategy / limiting factor / metric to be achieved)
BPA Implementation Plan (NMFS 2004) hatchery BPA provides direction in regards to NEOH in its 2005-2007 Implementation Plan. The plan offers implementation details of the Final Updated Proposed Action (UPAs) for the FCRPS Biological Opinion Remand. The IP states that “BPA will continue to fund RM&E to determine whether safety-net hatchery programs and other UPA hatchery actions contribute to recovery of targeted populations of salmon and steelhead.” Table 19 (pg 37) lists the NEOH project as a 2005– 2007 deliverable objective with the commitment to “continue the planning for future implementation of the NEOH project” (USACE 2005).
NMFS 2000 RPA 176 hatchery Implementation of the Northeast Oregon Hatchery project is specifically identified in the FCRPS Biological Opinion under Reasonable and Prudent Action (RPA) 176, which states: "Based on previous risk assessments, conservation hatchery programs consistent with the safety-net concept already have begun for three populations of spring/summer chinook on the Grande Ronde River and for the single Tucannon River population. Portion of these programs have been accommodated temporarily, but unsatisfactorily, by crowding into existing facilities, with resultant compromises with other ongoing programs. Each conservation hatchery program would benefit from development of an HGMP that identifies the capital and operational needs for these programs and implementation of the HGMP’s findings. The Nez Perce Tribe and Confederated Tribes of the Umatilla Indian Reservation are well along in planning for the North East Oregon Hatchery. Coordination between the existing LSRCP safety-net program and North East Oregon Hatchery planning processes is already occurring to a large degree and should continue among USFWS, NMFS, the states of Oregon and Washington, and the Tribes to provide the best, most efficient and expedient, integration of hatchery programs to meet the resource needs of the region".
NMFS 2000 RPA 8 hatchery This modification will help continue the RPA directive to: "Develop plans for hatchery and harvest measures that provide offsite mitigation".
NMFS 2000 RPA 177 hatchery This modification will help BPA, "begin to implement and SUSTAIN NMFS-approved safety net projects."

Section 2e: Description (Objectives)
Objectives of this proposed project
Objective
(abbreviation)
Full Description
To maintain BPA/NPT property The existing facility was purchased years ago as a future component of the Lostine River Hatchery. It remains vacant, is curently deteriorating and in need of maintenance. Our objective is to simply maintain the property and thereby protect the investment.

Section 3: Is This Funding Request Related to Other Projects in the Basin?

Other projects that are related to this request
Project # Project Title/Description Nature of Relationship

Section 4: Estimated Budget for Planning & Design phase for this request (request amount only)

Work element-based estimated budget
Planning & Design
Objective Work Element Work Element Title Work Element Description Description of Metrics Task Duration
in FYs
Estimated Budget Subcontractor?

Outyear work element-based estimated 2009 - 2012 budget for this proposal
Planning & Design
Work Element Work Element Outyear Description Starting FY
numbers only
Ending FY
numbers only
Estimated cost

Outyear totals
Planning & Design

Section 5: Estimated Budget for Contruction/Implementation phase for this request (request amount only)

Work element-based estimated budget
Contruction/Implementation
Objective Work Element Work Element Title Work Element Description Description of Metrics Task Duration
in FYs
Estimated Budget Subcontractor?

Outyear work element-based estimated 2009 - 2012 budget for this proposal
Contruction/Implementation
Work Element Work Element Outyear Description Starting FY
numbers only
Ending FY
numbers only
Estimated cost

Outyear totals
Contruction/Implementation

Section 6: Estimated Budget for Operations & Maintenance phase for this request (request amount only)

Work element-based estimated budget
Operations & Maintenance
Objective Work Element Work Element Title Work Element Description Description of Metrics Task Duration
in FYs
Estimated Budget Subcontractor?
To maintain BPA/NPT property Maintain Hatchery Mantenance of the BPA/NPT Property on Granger Rd. We seek funding to repair plumbing problems and associated damage in both the main house and guest house. Both the wooden batter board siding and wood deck are in a neglected condition. We request funds to clean, stain and seal these wood structures. The surrounding grounds are overgrown with high grass and weeds. This dry plant material has created a severe fire hazard to the BPA property as well as to other neighborhood homes. We seek funding to maintain a greenbelt lawn around the buildings. The unimproved access road leading to the BPA house is to be maintained per agreement between BPA and Wallowa County. We seek funds to implement that agreement. [Not Entered] 1 $6,981 Yes

Outyear work element-based estimated 2009 - 2012 budget for this proposal
Operations & Maintenance
Work Element Work Element Outyear Description Starting FY
numbers only
Ending FY
numbers only
Estimated cost
Maintain Hatchery Greenbelt maintenance - until the hatchery is build and a normal O&M annual budget is established 2008 2011 $2,272

Outyear totals
Operations & Maintenance
FY 2008 FY 2009 FY 2010 FY 2011
$568 $568 $568 $568

Section 7: Estimated Budget for Monitoring & Evaluation phase for this request (request amount only)

Work element-based estimated budget
Monitoring & Evaluation
Objective Work Element Work Element Title Work Element Description Description of Metrics Task Duration
in FYs
Estimated Budget Subcontractor?

Outyear work element-based estimated 2009 - 2012 budget for this proposal
Monitoring & Evaluation
Work Element Work Element Outyear Description Starting FY
numbers only
Ending FY
numbers only
Estimated cost

Outyear totals
Monitoring & Evaluation

Section 8: Total Budget Modification Request

Itemized Estimated Budget
Item Note FY 2008 Cost
Other Subcontract - Access Road Maintenance $1,330
Other Subcontract - Green Belt Maintenance $705
Capital Equipment Hot Water Heater Replacement $562
Other Subcontract - Guest House Plumbing Repair $801
Other Subcontract - Main House Plumbing Repair $1,697
Other Subcontract - Batter Board Siding Maintenance $1,464
Other Subcontract - Deck Floor Maintenance $348
Supplies Vinyl Rain Gutter Replacement $57
Other Indirect (29.65%) $17

Total Estimated Budget Modification
Total FY 2008 budget modification $6,981
Total FY 2008 budget for this project, including modification request $435,027

Outyear Budget Totals
  2008 2009 2010 2011
Operations & Maintenance $ 568 $ 568 $ 568 $ 568
Total Outyear Budgets $ 568 $ 568 $ 568 $ 568

Cost sharing associated with this modification
Organization Item or Service Provided Amount ($) Cash or in-kind?
NPT Coordination of Maintenance $500 In-Kind

Section 9: Narrative, Maps and Project Documents
No documents are associated with this request

Part 2 of 3. Current Status of Modification Request
Meeting Date Status Record Entry Date Decision Group Adjustment Category Urgency Status Budget Impact Reconsider Date
8/8/2007  7/9/2007  NA      Submitted  $6,981   
Decision Comments Next Steps
   
8/8/2007  8/8/2007  BOG  Budget    Submitted  $6,981  9/5/2007 
Decision Comments Next Steps
Deferred to the September BOG Meeting, because sponsor didn't call in.   
8/8/2007  9/5/2007  BOG  Budget  Not Urgent  Under BOG Review  $6,981   
Decision Comments Next Steps
This request is a category 5 (other).  November decision 
8/8/2007  11/16/2007  BPA  Budget  CAT-5: Other  BPA Approved  $2,000   
Decision Comments Next Steps
Concurrence with Council. $2000 added to Project No. 1998-007-02 for laying gravel on road.   