Project Proposal Request for FY 2007 - FY 2009 Funding (Revised Summer 2006)

Proposal 198805315: Hood River Adult Salmonid Trapping Facilities/Parkdale Fish Facility Expansion

Download this document in MS Word format
Open this document in PDF format

Table of Contents
Part 1. Administration and Budgeting
Section 1: General Administrative
Section 2: Project Location
Section 3: Project Species
Section 4: Past Accomplishments
Section 5: Relationship to Other Projects
Section 6: Biological Objectives
Section 7: Work Elements
Section 8: Budget
Section 9: Project Future
Section 10: Documents
Part 2. Reviews
Part 1 of 2. Administration and Budgeting
Section 1: General Administrative Information
Process Information:
Date Proposal Submitted & Finalized Status Form Generator
Finalized Rod French

Proposal Type: Ongoing
Proposal Number: 198805315
Proposal Name: Hood River Adult Salmonid Trapping Facilities/Parkdale Fish Facility Expansion
BPA Project Manager: Sarah Branum
Agency, Institution or Organization: Oregon Department of Fish & Wildlife (ODFW)
Short Description: Conduct environmental compliance and initiate construction on proposed adult salmonid trapping facilities in the Hood River Subbasin, and expansion of the Parkdale Fish Facilty to accomodate spring Chinook rearing.
Information Transfer: Through BPA's reporting requirements.
 
Project Proposal Contacts
Contact Organization Address Phone/Email Roles Notes
Form Submitter
Rod French Oregon Department of Fish and Wildlife 3701 W. 13th St.
The Dalles, OR, 97058
Ph: 541-296-4628
Fax: 541-298-4993
Email: rod.a.french@state.or.us
Form Submitter
All Assigned Contacts
Rod French Oregon Department of Fish and Wildlife 3701 W. 13th St.
The Dalles, OR, 97058
Ph: 541-296-4628
Fax: 541-298-4993
Email: rod.a.french@state.or.us
Form Submitter

Section 2: Project Location
Sponsor Province: Columbia Gorge ARG Province: No Change
Sponsor Subbasin: Hood ARG Subbasin: No Change
Location(s) at which the action will be implemented
Latitude Longitude Waterbody Location Description County/State Subbasin Primary?
Newly identified adult trapping sites will be identified by RFP000000537 in the Hood River Subbasin on the East, Middle, and West Fork of the Hood River. , Oregon Hood No
Rogers Spring Creek Parkdale Fish Facility is located near Parkdale, Oregon. , Oregon Hood No

Section 3: Focal Species
Focal Species:
Primary Secondary Additional Species
Chinook Lower Columbia River ESU
Steelhead Lower Columbia River ESU
All Anadromous Salmonids

Section 4: Past Accomplishments
Past Accomplishments for Each Fiscal Year of This Project
Fiscal Year Accomplishments
2005 Continued operation of PDFT to collect life history characteristics, monitor escapements, and collect broodstocks. Ongoing HRPP hatchery production continues.
2004 Hood River Subbasin Plan completed, relies heavily upon HRPP data. Genotyping of steelhead broodstock. Continued operation of PDFT to collect life history characteristics, monitor escapements, and collect broodstocks. Ongoing HRPP hatchery production.
2003 HRPP Programatic Review completed. Settlement agreement with PacifiCorps reached. Continued operation of PDFT to collect life history characteristics, monitor escapements, and collect broodstocks. Ongoing HRPP hatchery production continues.
2002 Continued operation of PDFT to collect life history characteristics, monitor escapements, and collect broodstocks. Ongoing HRPP hatchery production continues.
2001 Genetic studies to determine reproductive success of Hood River steelhead initiated. Continued operation of PDFT to collect life history characteristics, monitor escapements, and collect broodstocks. Ongoing HRPP hatchery production continues.
2000 Continued operation of PDFT to collect life history characteristics, monitor escapements, and collect broodstocks. Ongoing HRPP hatchery production continues.
1999 Continued operation of PDFT to collect life history characteristics, monitor escapements, and collect broodstocks. Ongoing HRPP hatchery production continues.
1998 Out of basin Skamania stock summer steelhead prevented from escaping above Powerdale Dam. Continued operation of the Powerdale Dam Fish Trap and release of winter steelhead and Chinook. First take of Hood River origin wild summer steelhead broodstock.
1997 New Powerdale Dam Fish Trapping facility completed and operational. Continued operation of the Powerdale Dam Fish Trap along with locally adapted Hood River stock hatchery winter steelhead and Deschutes stock spring Chinook successfully released.
1996 Hood River EIS completed. Hood River stock hatchery winter steelhead successfully released. Oak Springs Hatchery's new incubation facility and rearing ponds become operational.
1995 New rearing cells completed at Pelton Ladder. Hood River stock hatchery winter steelhead successfully released.
1994 Out of basin Big Creek stock hatchery winter steelhead prevented from escaping above Powerdale Dam. Continued operation of the Powerdale Dam Fish Trap. Hood River stock hatchery winter steelhead successfully released. Initiated radio tracking studies.
1993 Continued operation of the Powerdale Dam Fish Trap. First release of Hood River stock hatchery winter steelhead into the Hood River basin.
1992 Continued operation of the Powerdale Dam Fish Trap. First take of Hood River origin wild winter broodstock.
1991 Initiated continuous operation of the Powerdale Dam Fish Trap located in the upper pool of the existing fish ladder at Powerdale Dam.

Section 5: Relationships to Other Projects
Other Current Projects Related to this Project (any funding source)
Funding Source Related ID Related Project Title Relationship
BPA 198805303 Hood River Production M&E - Ws This contract implemented by the CTWS consists of acclimation of spring Chinook and summer and winter steelhead; spring Chinook natural spawning distribution studies; spring Chinook run predictions; tribal harvest and creel; water quality monitoring; and PIT tagging hatchery production.
BPA 198805304 Hood River Production M&E-ODFW This contract allows for data collection and management of Hood River juvenille screw traps; adult trap and return summaries; distribution; streamflow data collection; steelhead run predictions; and PIT tagging natural production.
BPA 198805306 Hood R Prod O&M - PGE This project provides funding for Portland Gas and Electric (PGE) for a portion of the use of Round Butte Fish Hatchery to assist with rearing of spring Chinook for HRPP use.
BPA 198805307 Hood R Prod O&M - WS/ODFW This project is implemented by the CTWS to operate and maintain the Parkdale Fish Facility, which includes adult broodstock holding, spawning, and a portion of the acclimation activities. The PFF recieves adult summer and winter steelhead and spring Chinook from the Powerdale Fish Trap (ODFW). All broodstock are held and spawned at the PFF. The fertilized steelhead eggs are shipped out green to Oak Springs Hatchery. Spring Chinook eggs are incubated until they reach the swim-up fry stage and are then shipped to Round Butte Hatchery. A portion of the winter steelhead and spring Chinook smolts are held at PFF for acclimation prior to volitional release into the Middle Fork Hood River.
BPA 199802100 Hood River Fish Habitat This project works with local and regional partners to conduct habitat restoration work and monitor it with implementation type parameters and long-term biological parameters. Most of the actions within this contract receive cost sharing funding from a variety of sources. This work aids in developing prioritites for habitat restoration that uses a watershed approach to ecosystem recovery.
BPA 199902400 Bull Trout Assessment Col Gorg This project will recieve extensive biological and PIT tag data collected from bull trout in the Hood River subbasin, at the Powerdale Fish Trap and multiple juvenille screw traps. This information will be used to assist with research on bull trout life history patterns.
BPA 200305400 Repro of Steelhead In Hood Riv Oregon State University implements this contract, which consists of genetic analysis and pedigree study of anandromous and resident fish in the Hood River subbasin. Data from this project provides critial infromation to insure the supplementation program does not adversely affect the genetic integrity of the naturally producing steelhead.

Section 6: Biological Objectives
Biological Objectives of this Proposed Project
Biological Objective Full Description Associated Subbasin Plan Strategy Page Nos
Objective 2. Conduct environmental compliance investigation, planning, and engineering required for proposed expansion of the Parkdale Fish Facility to rear spring Chinook. Hood Research monitoring and evaluation. 201
Ojbective 1. Conduct environmental compliance investigation, planning, and engineering required for proposed adult trapping facilities in the Hood River Subbasin Hood Harvest and hatchery supplementation strategies. 195

Section 7: Work Elements
Work Elements and Associated Biological Objectives
Work Element Name Work Element Title Description Start Date End Date Estimated Budget
Produce Environmental Compliance Documentation [Work Element Title Not Entered] BPA will likely hire a contractor to produce an EIS for the proposed new facilities. Covers work by ODFW and CTWSRO to support BPA in obtaining compliance. 10/1/2006 9/30/2009 $500,000
Biological Objectives Metrics
Objective 2.
Ojbective 1.
No Metrics for this Work Element

Coordination [Work Element Title Not Entered] Coordination efforts between ODFW, CTWSRO, and other agencies to ensure a smooth sailing project. 10/1/2006 9/30/2009 $25,000
Biological Objectives Metrics
Objective 2.
Ojbective 1.
No Metrics for this Work Element

Manage and Administer Projects [Work Element Title Not Entered] Work to manage on the ground efforts and subcontractors associated with the project (e.g., construction management) . Also covers administration work in support of on the ground efforts and BPA's contracting requirements. 10/1/2006 9/30/2009 $25,000
Biological Objectives Metrics
Objective 2.
Ojbective 1.
No Metrics for this Work Element

Produce Design and/or Specifications [Work Element Title Not Entered] After the HRPP Expansion plan is completed, design work sufficient to describe the proposed project for an EIS will be needed. Detailed specifications will be needed after the EIS is completed. 10/1/2006 9/30/2009 $500,000
Biological Objectives Metrics
Objective 2.
Ojbective 1.
No Metrics for this Work Element

Provide Technical Review [Work Element Title Not Entered] Covers work by ODFW and CTWSRO to review design and specifications for any proposed construction and improvements. 10/1/2006 9/30/2009 $50,000
Biological Objectives Metrics
Objective 2.
Ojbective 1.
No Metrics for this Work Element

Produce/Submit Scientific Findings Report Produce Annual Report All contractors under this project proposal will be required to complete annual summary reports of activities. 10/1/2006 9/30/2009 $25,000
Biological Objectives Metrics
Objective 2.
Ojbective 1.
No Metrics for this Work Element

Produce/Submit Scientific Findings Report Produce Pisces Status Report Produce Pisces status report each quarter. 10/1/2006 9/30/2009 $25,000
Biological Objectives Metrics
Objective 2.
Ojbective 1.
No Metrics for this Work Element


Section 8: Budget

Itemized Estimated Budget
Item Note FY 2007 Cost FY 2008 Cost FY 2009 Cost
Other Budget supplied is estimated, detailed budget information will not be available until after completion of RFP 00000537. $750,000 $250,000 $150,000
Totals $750,000 $250,000 $150,000

Total Estimated FY 2007-2009 Budgets
Total Itemized Budget$1,150,000
Total Work Element budget$1,150,000

Cost sharing
Funding Source or Organization Item or Service Provided FY 2007 Est Value ($) FY 2008 Est Value ($) FY 2009 Est Value ($) Cash or in-kind? Status

Section 9: Project Future
Project Future Costs and/or Termination
FY 2010 Est Budget FY 2011 Est Budget Comments
$ 0 $ 0 [Outyear comment field left blank]
Future Operations & Maintenance Costs
Outyear budgetting will not be possible until results of RFP 00000537 are available late in FY2006.
 
Termination Date Comments
Unforseen Basin co-managers have yet developed a termination date for the HRPP.
 
Final Deliverables

Section 10: Narrative
Document Type Size Date
No revised documents are associated with this request
Documents Originally Submitted with this Proposal

Part 2 of 2. Reviews of Proposal
Administrative Review Group (ARG) Results
Account Type:
Expense
Location:
Province: No Change
Subbasin: No Change
Primary Focal Species
No Change
ARG Comments: [none]


NPCC Final Funding Recommendations (October 23, 2006) [Full NPCC Council Recs]

FY 2007 NPCC Rec
$ 0
FY 2008 NPCC Rec
$ 0
FY 2009 NPCC Rec
$ 0
Total NPCC Rec
$ 0
Budget Type:Expense
Budget Category:ProvinceExpense
Recommendation:Do Not Fund
NPCC Comments:


NPCC Draft Funding Recommendations (September 15, 2006) [Full NPCC Council Recs]

FY 2007 NPCC Rec
$ 0
FY 2008 NPCC Rec
$ 0
FY 2009 NPCC Rec
$ 0
Total NPCC Rec
$ 0
FY 2007 MSRT Rec
$ 0
FY 2008 MSRT Rec
$ 0
FY 2009 MSRT Rec
$ 0
Total MSRT Rec
$ 0
Budget Category:ProvinceExpense
NPCC Comments:

Local or MSRT Comments: OSPIT concurs with ISRP that this project should go into the Three Step process and so we have removed money for implementation. However, given that Powerdale Dam is slated for removal in 2010, it is imperative that the proposal for reconfiguring the tra


Independent Scientific Review Panel Final Review (August 31, 2006) [Download full document]

Recommendation: Not fundable
Comments: Despite its numeric designation as an ongoing project, this seems to be new work and appropriate for the Three-Step Review process. As written, the proposal suffered greatly from a lack of clarity and definition in every aspect. The ISRP cannot recommend this project for funding at this time.


Independent Scientific Review Panel Preliminary Review (June 2, 2006) [Download full document]

Recommendation: Not fundable
Comments: Despite its numeric designation as an ongoing project, this seems to be new work and appropriate for the Three-Step Review process. As written, the proposal suffered greatly from a lack of clarity and definition in every aspect. The ISRP cannot recommend this project for funding at this time.