Proposal 199603501: Yakama Reservation Watersheds Project

Download this document in MS Word format
Open this document in PDF format

Table of Contents
Part 1. Administration and Budgeting
Section 1: General Administrative
Section 2: Project Location
Section 3: Project Species
Section 4: Past Accomplishments
Section 5: Relationship to Other Projects
Section 6: Biological Objectives
Section 7: Work Elements
Section 8: Budget
Section 9: Project Future
Section 10: Documents
Part 2. Reviews
Part 1 of 2. Administration and Budgeting
Section 1: General Administrative Information
Process Information:
Date Proposal Submitted & Finalized Status Form Generator
January 10, 2006 Finalized Tim Resseguie

Proposal Type: Ongoing
Proposal Number: 199603501
Proposal Name: Yakama Reservation Watersheds Project
BPA Project Manager: Jay Marcotte
Agency, Institution or Organization: Yakama Confederated Tribes
Short Description: The YRWP works to restore natural function to the Satus, Toppenish and Ahtanum Watersheds. Our restoration and monitoring efforts take a comprehensive approach to the restoration of habitat for fisheries resources including steelhead and bull trout.
Information Transfer: The information we generate guides our project decisions and the management of two of the four Yakima Subbasin steelhead populations. Our monitoring data and input are an integral part of the Yakima Subbasin Plan and the Yakima Subbasin Salmon Recovery Plan. Steelhead tag data are available on the PTAGIS and DART websites and are being used to evaluate survival and passage in the Yakima and Columbia rivers.
 
Project Proposal Contacts
Contact Organization Address Phone/Email Roles Notes
Form Submitter
Tim Resseguie Yakama Nation Fisheries YRWP Box 151
Toppenish, WA, 98948
Ph: (509) 865-2255 x 6358
Fax: [left blank]
Email: timr@yakama.com
Form Submitter
All Assigned Contacts
Tim Resseguie Yakama Nation Fisheries YRWP Box 151
Toppenish, WA, 98948
Ph: (509) 865-2255 x 6358
Fax: [left blank]
Email: timr@yakama.com
Form Submitter
Brandon Rogers YN Fisheries PO Box 151 Fort Rd.
Toppeninsh, WA 98948
Ph: 509 949-4109
Fax: [left blank]
Email: brandonr@yakama.com
Project Lead

Section 2: Project Location
Sponsor Province: Columbia Plateau ARG Province: No Change
Sponsor Subbasin: Yakima ARG Subbasin: No Change
Location(s) at which the action will be implemented
Latitude Longitude Waterbody Location Description County/State Subbasin Primary?
46.5267845 -120.728958 Ahtanum Creek Ahtanum Creek watershed Yakima, Washington Yakima No
46.2106999 -120.470871 Satus Creek Satus Creek Watershed Yakima, Washington Yakima No
46.3759918 -120.612964 Toppenish Creek Toppenish Creek watershed Yakima, Washington Yakima No

Section 3: Focal Species
Focal Species:
Primary Secondary Additional Species
Steelhead Middle Columbia River ESU
All Anadromous Salmonids
Bull Trout
Cutthroat Trout

Section 4: Past Accomplishments
Past Accomplishments for Each Fiscal Year of This Project
Fiscal Year Accomplishments
2005 Monitor precip, temp, flow and fish spawning and migration in 3 watersheds. Lease range units, build and maintain cattle exclusion fences, plant vegetation, drill stock wells. Maintain instream flow, restore fish passage and reconnect fish habitat.
2004 Watershed Monitoring (irrigation, fish, Q, Temp, Precip), Lease Range Unit, fence maintenance, vegetation planting, Improve fish passage, execute instream flow, riparian cattle exclusion fences, built grade structures, install stock wells.
2003 Watershed Monitoring (irrigation, fish, Q, Temp, Precip), Lease Range Unit, fence maintenance, vegetation planting, Improve fish passage, execute instream flow, riparian cattle exclusion fences, built grade structures, install stock wells.
2002 Fish Habitat Monitoring, Watershed Monitoring (Q, Temp, Precip), Lease Range Unit, fence maintenance, plant (grass, hardwoods, willow), Improve fish passage, monitor irrigation diversions, execute instream flow, riparian cattle exclusion fences.
2001 Fish Habitat Monitoring, Watershed Monitoring (Q, Temp, Precip), Lease Range Unit, 18 miles of fence repair, plant (grasses, hardwoods, willow), Improve fish passage, monitor irrigation diversions, and implement instream flow.
2000 Fish Habitat Monitoring, Watershed Monitoring (Q, Temp, Precip), Lease Range Unit, 18 miles of fence repair, plant (grasses, hardwoods, willow), Improve fish passage and monitor irrigation diversions.
1999 Fish Habitat monitoring, Watershed Monitoring (Q, Temp, Precip), Lease Range unit, Road removal, installed ford, Fenced 12 mi, plant (grasses, willow, pine) and grade control structures, consulting resources.
1998 Stream temp/flow measurement/turbidity, collect fish data, lease range units, remove and relocate road, replace 3 culverts, engineer LWD, seeded, rebuilt 18 mi of fence, plant willow/pine, rehabilitate incised channel, install grade control structure
1997 Stream temp/flow measurement, collect fish data, leased range units, removed and relocated 2 road/dikes/culverts, rehabilitating incised channels, rebuilt 8.5 mi of fence, planted willow/pine, engineer LWD, and small grade control structures.
1996 Air photo interpretation, Proper Functioning Condition assessment, stream flow and precip gages, stream temp/flow measurement, collected fish data, leased range units, built 14 mi of fence, 11 cattle guards, seeded 285 ac., removed and relocated roads.

Section 5: Relationships to Other Projects
Other Current Projects Related to this Project (any funding source)
Funding Source Related ID Related Project Title Relationship
Other: BIA [no entry] Fire Rehabilitation BIA has made or passed through in-kind contributions of materials for revegetation and rehabilitation of burned areas, as we assisted them with revegetation and sediment control.
Other: Washington Department of Ecology [no entry] Consolidate Two Simcoe Creek Diversions YRWP staff applied for and received this grant to supplement BPA Project 200106400, allowing a second irrigation ditch to be supplied by the reconstructed Hoptowit Diversion, eliminating a second diversion point.
Other: USDA EQUIP [no entry] Toppenish Ridge Fence YRWP staff applied for and received USDA Environmental Quality Incentives Program (EQIP) funding to construct fencing and drill stock wells along Toppenish Ridge. The objective of this project is to force cattle to pasture on the North side of Toppenish Ridge, a place that previously had no water. Pasturing cattle in this area will lessen the impact the cattel have on the riparian areas found on the south side of the ridge.
Other: USFWS Private Land Stewardship Grant [no entry] LaSalle Riparian Restoration YRWP staff, in partnership with LaSalle High School and the City of Yakima, applied for and received grand funding to restore the riparian area along Ahtanum creek owned by LaSalle High School.
Other: USFWS Partners for Fish and Wildlife [no entry] Ahtanum Sidechannel Reconnection Project YRWP staff applied for and recieved funding from the USFWS PFFW grant. The funding will be used to assist with the reconnectiong of a sidechannel along Ahtanum Creek.
BPA 199206200 Lower Yakima Valley Riparian/W The goal of the Yakama Nation’s Lower Yakima Valley Wetlands and Riparian Area Restoration Project is to purchase, restore and manage riparian lands along the Yakima River, lower Toppenish Creek, and in lower Satus Creek. These efforts are coordinated with and support the goals of the Yakama Reservation Watersheds Project.
BPA 199506325 YKFP - Monitoring And Evaluati As part of Yakama Nation Fisheries, YRWP and YKFP share common goals of increasing anadromous fish production in the Yakima River watershed. Facilities, some equipment, technical expertise, samples and data, are shared between the two projects.
PCSRF - Colville 2000-4-01 Ahtanum Creek Fencing and Ripa YRWP staff applied for and received funding to build 8 miles of riparian fence along Ahtanum Creek. The completed fence protects some of the best riparian areas in the Ahtanum Creek watershed and excludes livestock from several areas deemed prime for steelhead habitat restoration. Project staff have revegetated 6 riparian areas excluded from grazing by these fences.
BPA 200106400 Simcoe Cr Streamflow Enhanceme YRWP applied for and received funding under the 2001 Power System Emergency Action Plan for the project entitled Improve Stream Flow and Passage for Simcoe Creek Steelhead. The funds were used to screen and rehabilitate the most problematic diversion of Simcoe Creek, and to drill a number of solar-powered wells to substitute for creek diversions.
BPA 200202501 Yakima Tributary Access & Habi YRWP staff coordinate restoration efforts with YTAHP as needed, especially in the Ahtanum Creek watershed.
PCSRF - Colville 2003-4-03 LaSalle Coho Hatchery and Educ YRWP staff assisted YKFP staff with the grant applicaton, landowner permission, permitting and biological data on Ahtanum Creek. This project conicides with the YRWP's goals of restoring salmon in the watershed and working with landowners for maximum benifit of the resource.
PCSRF - Colville 2003-4-10 Deployment of Gaging Stations YRWP staff applied for and received funding to implement automated gaging stations along Ahtanum and Toppenish Creeks and their tributaries. This project has allowed the YRWP to more effectively monitor instream flows and temperature in Toppenish, Simcoe, Agency and Ahtanum creeks, and to adjust irrigation intake based on the YN mandated instream flows in those streams. Discharge monitoring stations equiped with cellular telemetry have allowed one person to track flow at several critical locations. This approach to monitoring has begun to free staff from repetitive wading measurements to work on restoration projects, provided a more complete flow record and allowed for more timely irrigation management decisions.
PCSRF - Colville 2004-4-07 Ahtanum Creek Water Pump YRWP staff applied for and received funding for a stock water well on the north side of Ahtanum Ridge. This stock well complements the recently-completed Ahtanum Fencing Project, in which 8.2 miles of riparian fence was constructed along Ahtanum Creek. The stock well provides necessary off-channel watering to allow cattle to continue to be pastured on Ahtanum Ridge in a sustainable manner without impacting Ahtanum Creek and its steelhead resource.
Other: BIA 2138101 Forest Managment & Development Budget The YRWP has taken over the responsibility and funding for fisheries input to timber sale planning and implementation in the three watersheds where we operate. This gives us more influence on the timber management actions of the BIA Branch of Forestry, and on the allocation of forest management funds to forest road abandonment, relocation and repair.
Other: BIA 2208101.512111. YN Emergency Flow Monitoring Project During the 2001 drought, YRWP staff applied for and received BIA funding for stream gage installation to automate flow data collection and provide early warning of low flow below diversions. This complements PCSRF funding described above.

Section 6: Biological Objectives
Biological Objectives of this Proposed Project
Biological Objective Full Description Associated Subbasin Plan Strategy Page Nos
Monitor Watershed Processes, Biological Responses Monitor precipitation, stream discharge and temperature, stream habitat parameters and fish abundance and productivity statistics to determine trends in habitat and fish population responses. Yakima Manage and monitor protection/restoration areas to ensure that ecol. functions and habitat benefits are maintained. note: Subb. Plan objectives emphasize restoration over monitoring. See discussion under this objective in subsec. F of Narrative. 4-16
Restore Channels and Reconnect Floodplains Restore channel and floodplain stability, complexity and function to improve the quantity and quality of spawning and rearing habitats. Yakima Relocate infrastructure to allow natural processes to operate. Compare to 1860s maps, restore physical and riparian characteristics. Raise drains to floodplain level. Redesign crossings to pass LWD. Widen or extend bridges. Relocate roads to uplands 4-45, 51,52,54
Restore Hydrologic Function Restore the water- and sediment-retention capacity of wetlands in headwaters and floodplains to moderate flow, improve water quality, and increase steelhead egg-to-smolt survival rate. Yakima Implement hydrologic restoration measures within the wetlands. Relocate or modify roads negatively impacting publicly owned montane wetlands. Maximize natural retention of flow in basin by restoring hydrologic connectivity and increasing floodplain area 4-8; 27 (suppl)
Restore Passage Eliminate entrainment of smolts and passage barriers to adults at tributary irrigation diversions to increase survival rate of smolts and improve access to spawning habitats. Yakima Design irrigation diversions to function over long time period. Replace/rebuild existing diversions based on prioritization. Relocate or consolidate existing structures. Provide screens. Consolidate diversions. Replace culverts in Ahtanum, Cowiche. 4-52,53
Restore Riparian Communities Restore diverse riparian plant communities that provide shade, habitat structure, bank stability and food, while supporting allied wildlife species such as beaver. Yakima Acquire grazing leases. Controlled burns, veg. mgt for conif. encroachment. Fence livestock from sensitive areas. Plant cottonwood, native riparian veg. Protect/restore Toppenish, Satus, Ahtanum, Naches w’sheds. Relocate roads from riparian zones. 4-7, 15, 51
Restore Stream Flow and Water Quality Restore normative hydrographs, temperature regimes and water quality parameters in stream reaches currently affected by irrigation diversions, spills and return flows. Yakima Maintain trib. flow by means including purchase of land, water rights. Armor channels [in drains], trap sediment, manage spill. Reduce efficiency of Marion Drain. Increase irrig. efficiency. Increase flow to depth threshold. Reduce net water use. 4-14,42,46,5153

Section 7: Work Elements
Work Elements and Associated Biological Objectives
Work Element Name Work Element Title Description Start Date End Date Estimated Budget
Produce Environmental Compliance Documentation Compliance for WEs Assemble, gather, acquire, or prepare documents in support of obtaining environmental compliance from BPA (such as filling out a NEPA Checklist, providing maps, drafting a Biological Assessment, obtaining permits, conducting public involvement activities, completing an archaeological survey, etc.) 10/1/2006 9/30/2009 $50,000
Biological Objectives Metrics
No Metrics for this Work Element

Enhance Floodplain Take Measures to Enhance and Restore Floodplain Install several straw bale structures to provide floodplain roughness. Remove dikes to allow stream better access to the floodplain. Structures range from 100 to 300 yards long and are constructed of standard 4x2.5' straw bales. These 99.9% weed free straw bale structures are used to temporarily direct stream flow, or create temporary "soft" structures on floodplains. The cross floodplain structures in this WE create soft floodplain structures that add roughness to the floodplain where it is lacking. Floodplain roughness slows overland flow, allowing for deposition of sediment on the floodplain and lowering the chances of unwanted floodplain erosion. This technique is typically used in pastures with inadequate grass and shrub growth to withstand high flows without eroding. 10/1/2006 9/30/2009 $220,000
Biological Objectives Metrics
Restore Hydrologic Function
Restore Riparian Communities
* # of acres treated: 400 acers

Increase Instream Habitat Complexity Install stream habitat features Instream Habitat Complexity (root wads) will be added when constructing any instream project to the extent that they don't impact the structural integrity of the project. Work will also include rock vortex weirs, bioengineering to stabilize stream banks and engineerd log jams. 10/1/2006 9/30/2009 $300,000
Biological Objectives Metrics
* # of stream miles treated: 5
* # of structures installed: 30
* Start long of treated reach: -120.50.12.18
* Start lat of treated reach: 46.09.39.53
* End lat of treated reach: 46.15.34.95
* End long of treated reach: -120.06.26.18

Install Fence Install riparian and range fences The following are WE Descriptions from out FY06 SOW. They accurately depict the types of fencing projects we implement. Install .6 mi of fencing to prevent cattle from accessing the watercourse draining Lincoln Meadow. Project includes installing gates and water gaps and 2 cattle guards. Fencing will be constructed to National Resource Conservation Servive specification (4 strand barbed wire with H braces every 1/4 mile). Project will install a livestock pasturing fence to assist in managing the migration of cattle from low elevations in the spring to higher elevations in the early summer. Currently, upon cattle turnout on May 1st, cattle quickly travel approximatly 25 miles to the headwater meadows of Satus and Toppenish creeks. Install fencing to prevent cattle from accessing the creek. Fence will be aproximately 3/4mi long and located along Topenish Creek in T10 R18 Sec 18. Project includes installing gates and water gaps appropriate to assist in grazing management. Fencing will be constructed to National Resource Conservation Servive specification (4 strand barbed wire with H braces every 1/4 mile). 10/1/2006 9/30/2009 $86,021
Biological Objectives Metrics
Restore Channels and Reconnect Floodplains
Restore Riparian Communities
Restore Stream Flow and Water Quality
* # of miles of fence: 15

Plant Vegetation Revegetate riparian areas that have been impacted by grazing or other degredation [Work Element Description Not Entered] 10/1/2006 9/30/2009 $190,000
Biological Objectives Metrics
Restore Channels and Reconnect Floodplains
* # of riparian miles treated: 20
* # of acres of planted: 400

Realign, Connect, and/or Create Channel reconnect side channels, install grade control structures, increase stream/floodplain connection reconnect side channels, install grade control structures, increase stream/floodplain connection 10/1/2006 9/30/2009 $850,000
Biological Objectives Metrics
Restore Hydrologic Function
Restore Riparian Communities
Restore Stream Flow and Water Quality
* # of stream miles treated, including off-channels, after realignment: 20

Lease Land Continue leases for Range Units 7, 8a, 9, 16 Since the inception of the Satus Project we have continuously leased and deferred grazing on 4 grazing permits. These permits encompass nearly the entire Logy Creek Watershed and nearly 20 miles of the Satus Creek corridor. All totaled, the project leases more than 140,000 acres including more than 30 stream miles of high quality steelhead spawning and rearing habitat in Satus and Logy Creeks. Project Staff will also investigate the possibility of leasing other range units and Tribal Allotments as they become available in the next 3 years. 10/1/2006 9/30/2009 $110,000
Biological Objectives Metrics
Restore Channels and Reconnect Floodplains
Restore Hydrologic Function
Restore Riparian Communities
Restore Stream Flow and Water Quality
* # of acres of renewed lease: 279,140

Other Install Fish Monitoring Equipment - Install 5ft Rotary Screwtrap deploy 5ft screwtraps in Satus, Ahtanum and Toppenish Creeks. 10/1/2006 9/30/2009 $6,000
Biological Objectives Metrics
Monitor Watershed Processes, Biological Responses
No Metrics for this Work Element

Coordination Coordinate with landowners and lessees [Work Element Description Not Entered] 10/1/2006 9/30/2009 $60,000
Biological Objectives Metrics
Monitor Watershed Processes, Biological Responses
Restore Channels and Reconnect Floodplains
Restore Hydrologic Function
Restore Passage
Restore Riparian Communities
Restore Stream Flow and Water Quality
No Metrics for this Work Element

Identify and Select Projects ID and select projects [Work Element Description Not Entered] 10/1/2006 9/30/2009 $96,000
Biological Objectives Metrics
No Metrics for this Work Element

Manage and Administer Projects Manage and Administer all restoration projects [Work Element Description Not Entered] 10/1/2006 9/30/2009 $390,000
Biological Objectives Metrics
No Metrics for this Work Element

Outreach and Education Education at local schools and with landowners [Work Element Description Not Entered] 10/1/2006 9/30/2009 $3,450
Biological Objectives Metrics
* # of general public reached: 25
* # of students reached: 200
* # of teachers reached: 20

Produce Inventory or Assessment Timber, Fish and Wildlife (TFW) surveys [Work Element Description Not Entered] 10/1/2006 9/30/2009 $59,868
Biological Objectives Metrics
Monitor Watershed Processes, Biological Responses
No Metrics for this Work Element

Produce Plan Produce plans for restoration of various degraded areas. Plans will be produced only for complex projects. [Work Element Description Not Entered] 10/1/2006 9/30/2009 $140,000
Biological Objectives Metrics
Restore Hydrologic Function
No Metrics for this Work Element

Provide Technical Review contribute to various planning efforts Provide review and data for planning and project proposals. 10/1/2006 9/30/2009 $75,000
Biological Objectives Metrics
No Metrics for this Work Element

Produce Annual Report Submit Annual Report [Work Element Description Not Entered] 10/1/2006 9/30/2009 $21,000
Biological Objectives Metrics
No Metrics for this Work Element

Produce Status Report Submit Quarterly Report [Work Element Description Not Entered] 10/1/2006 9/30/2009 $4,000
Biological Objectives Metrics
No Metrics for this Work Element

Analyze/Interpret Data Analyze field data for use in resource management decisoins [Work Element Description Not Entered] 10/1/2006 9/30/2009 $30,000
Biological Objectives Metrics
Monitor Watershed Processes, Biological Responses
Focal Area: Tributary and Mainstem Streams
Secondary R, M, and E Type: Action Effectiveness Research, Status and Trend Mo

Collect/Generate/Validate Field and Lab Data Collect Data Staff will conduct snorkel surveys in stream reached where restoration efforts may be targeted, as well as several index reaches that are snorkeled yearly to monitor relative population numbers. With good survey conditions, it takes 2 technicians and 1 biologist about 1 day to cover 1/4 miles of stream. Generally project personnel survey about 3 miles of stream per year. As with WE M, the Project's goal is to survey all of the habitat accessable by anadromous salmonids in the Satus, Toppenish and Ahtanum basins. The Project will prioritize reaches slated for restoration or research projects. As an example, in FY05 the Project performed snorkel surveys in the upper reaches of Satus Creek. These surveys increase our knowledge of the upper watershed and served as valuable baseline data for the YKFP steelhead kelt productivity study. Snorkel surveys will often be tied to the TFW habitat surveys in WE F. Collect field data including stream flow, water quality, redd counts, juvenile outmigration, revegetation success, habitat survey data and stream morphology. Perform Timber Fish and Wildlife (TFW) protocol habitat surveys throughout the watersheds. TFW surveys include setting up permanent transect sites, cataloging the size and position of large woody debris, recording stream channel morphology and water quantity during the survey. In addition to those attributes, Staff perform pebble counts and snorkel for species type and abundance (see WEs G&H.) Project staff plan to survey approximately 3.7 miles of stream each year. This amount of surveying take a 5 person team 4 weeks at the minimum. The Project's goal is to survey all of the habitat accessible by anadromous salmonids in the Satus, Toppenish and Ahtanum basins. The Project will prioritize reaches slated for restoration or research projects. As an example, in FY05 the Project performed habitat surveys in the upper reaches of Satus Creek. These surveys increase our knowledge of the upper watershed and served as valuable baseline data for the YKFP steelhead kelt productivity study. Inventory sediment composition and disposition at 25 sites throughout the 3 watersheds. Survey protocols will include the Woman Pebble Count and a more intensive method developed by the United States Forest Service.The Project's goal is to survey all of the habitat accessable by anadromous salmonids in the Satus, Toppenish and Ahtanum basins. A two person team can process 3 to 4 sites a day. The Project will prioritize reaches slated for restoration or research projects. As an example, in FY05 the Project performed sediment inventories in the upper reaches of Satus Creek. These surveys increase our knowledge of the upper watershed and served as valuable baseline data for the YKFP steelhead kelt productivity study. Sediment inventorys are often tied to TFW Habitat surveys. 10/1/2006 9/30/2009 $600,000
Biological Objectives Metrics
Monitor Watershed Processes, Biological Responses
Focal Area: Watershed-wide
Secondary R, M, and E Type: Action Effectiveness Research, Status and Trend Mo
Secondary R, M, and E Type: Project Implementation/ Compliance Monitoring

Create/Manage/Maintain Database Maintain Satus watershed databases Manage and maintain YRWP databases. Databases include: stream discharge, Large Woody Debris, stream temperature, habitat surveys, salmonid redd locations (spatial) fence locations (spatial), snorkel surveys, sediment inventories, photopoints, stock wells (spatial) restoration project location (spatial.) These databases are used on a daily basis to make resource management decisions like instream flow amounts and prioritization of restoration projects. 10/1/2006 9/30/2009 $90,000
Biological Objectives Metrics
Monitor Watershed Processes, Biological Responses
No Metrics for this Work Element

Disseminate Raw/Summary Data and Results Disseminate Project data in raw form Disseminate data in raw or informal form to various agencies. Project staff typically are asked to disseminate information in some form, on average of 2 time per month. Data requests vary from biological data fro Biologic Assessment documents to stream flow data for determining irrigation intake amounts. Data is provided to various agencies including NOAA Fisheries, Washington Dept. of Fish and Wildlife, Yakima Tributary Access and Habitat Project, Yakima Klickitat Fisheries Project, Yakima County. 10/1/2006 9/30/2009 $45,000
Biological Objectives Metrics
No Metrics for this Work Element


Section 8: Budget

Itemized Estimated Budget
Item Note FY 2007 Cost FY 2008 Cost FY 2009 Cost
Personnel Wages $511,936 $558,011 $608,232
Fringe Benefits 18.6% or 22% $99,349 $108,290 $118,037
Supplies Office $1,500 $1,500 $1,500
Supplies Operating $30,000 $30,000 $30,000
Travel Expenses $3,000 $3,000 $3,000
Travel Training $3,000 $3,000 $3,000
Other Insurance $7,000 $7,000 $7,000
Other Contract Labor $1,000 $1,000 $1,000
Other Utilities $2,000 $2,000 $2,000
Other Vehicle Gas/OIl $700 $700 $700
Other Aerial Census $2,000 $2,000 $2,000
Other Repairs/Maintenance $5,000 $5,000 $5,000
Other Rental $68,167 $68,167 $68,167
Supplies Supplies/Equipment $15,000 $15,000 $15,000
Other Small Tools $1,000 $1,000 $1,000
Other Cellular Phones $5,097 $5,097 $5,097
Other Vehicle Repair $7,000 $7,000 $7,000
Other Leases $21,793 $21,793 $21,793
Other Indirect @ 18.89% $148,200 $158,593 $169,920
Other Professiona Services $2,000 $2,000 $2,000
Other Construction $140,000 $140,000 $140,000
Totals $1,074,742 $1,140,151 $1,211,446

Total Estimated FY 2007-2009 Budgets
Total Itemized Budget$3,426,339
Total Work Element budget$3,426,339

Cost sharing
Funding Source or Organization Item or Service Provided FY 2007 Est Value ($) FY 2008 Est Value ($) FY 2009 Est Value ($) Cash or in-kind? Status
NOAA Fisheries Open Rivers Initiataive Cash- Project Engineering and Construction $50,000 $50,000 $50,000 Cash Under Review
NRCS EQUIP Grant Program Cash- Project Construction $15,000 $15,000 $15,000 Cash Under Development
Pacific Coastal Salmon Recovery Funding Board Cash- Project Construction $25,000 $20,000 $20,000 Cash Under Development
USFWS Partners for Fish and Wildlife Project Cash-Project Construction $30,000 $30,000 $30,000 Cash Under Review
Totals $120,000 $115,000 $115,000

Section 9: Project Future
Project Future Costs and/or Termination
FY 2010 Est Budget FY 2011 Est Budget Comments
$1,282,741 $1,354,036 Reflects salary COLAs and merit increases only.
Future Operations & Maintenance Costs
It is difficult to estimate post-restoration O&M costs, but they are likely to be a fraction of the current funding level.
 
Termination Date Comments
None The restoration project will be complete, with only O&M costs required, when the extinction risk for Satus Creek, Toppenish Creek, and Naches River steelhead--of which the Ahtanum aggregation is a part--is deemed to be 5% or less (currently greater than 25% for all three populations).
 
Final Deliverables
This project is ongoing. Deliverables are provided as per our contract with BPA, and include quarterly and annual reports.

Section 10: Narrative
Document Type Size Date

Part 2 of 2. Reviews of Proposal
Administrative Review Group (ARG) Results
Account Type:
Expense
No changes were made to this proposal


NPCC Final Funding Recommendations (October 23, 2006) [Full NPCC Council Recs]

FY 2007 Budget
$ 0
FY 2008 Budget
$ 0
FY 2009 Budget
$ 0
Total NPCC Rec
$ 0
Budget Type:Expense
Budget Category:ProvinceExpense
Recommendation:Fund Pending Available Funds
Comments: Tier 2. Fund at a level consistent with ISRP comments during contracting, when funds become available.


NPCC Draft Funding Recommendations (September 15, 2006) [Full NPCC Council Recs]

FY 2007 Budget
$ 0
FY 2008 Budget
$ 0
FY 2009 Budget
$ 0
Total NPCC Rec
$ 0
FY 2007 MSRT Rec
$ 0
FY 2008 MSRT Rec
$ 0
FY 2009 MSRT Rec
$ 0
Total MSRT Rec
$ 0
Budget Category:ProvinceExpense
Comments:


Independent Scientific Review Panel Final Review (August 31, 2006) [Download full document]

Recommendation: Fundable
NPCC Comments: This ongoing project is very well described in the proposal. The sponsors are to be commended for the organization and presentation of the past and proposed work. A good qualitative summary of past results and actions with some data on fish abundance/trends based on snorkel surveys and redd counts is presented. Staff are to be commended for their insight, and their patient but assertive approach. However, they are dealing with some fairly sophisticated rehabilitation on a large scale, the results of which should be further evaluated, summarized, and reported in peer reviewed literature such as Restoration Ecology.


Independent Scientific Review Panel Preliminary Review (June 2, 2006) [Download full document]

Recommendation: Fundable
NPCC Comments: This ongoing project is very well described in the proposal. The sponsors are to be commended for the organization and presentation of the past and proposed work. A good qualitative summary of past results and actions with some data on fish abundance/trends based on snorkel surveys and redd counts is presented. Staff are to be commended for their insight, and their patient but assertive approach. However, they are dealing with some fairly sophisticated rehabilitation on a large scale, the results of which should be further evaluated, summarized, and reported in peer reviewed literature such as Restoration Ecology.