Section 1. Administrative

Proposal titleRestore long-term bull trout migration corridor in Pipe Creek at the Kootenai River
Proposal ID26023
OrganizationMontana Department of Fish, Wildlife and Parks (MFWP)
Proposal contact person or principal investigator
NameGreg Hoffman
Mailing address475 Fish Hatchery Road Libby, MT 59923
Phone / email4062934161 / ghoffman@libby.org
Manager authorizing this projectBrian Marotz, MFWP Kalispell
Review cycleFY 2001 Action Plan
Province / SubbasinMountain Columbia / Kootenai
Short descriptionRestore proper channel dimension, pattern and profile to approximately 2 miles of stream upstream from the confluence of Pipe Creek at the Kootenai River to ensure long-term fish passage to spawning areas in the headwaters.
Target speciesBull trout
Project location
LatitudeLongitudeDescription
48.086 -116.1 Pipe Creek is a major tributary to the middle section of the Kootenai River downstream of Libby, Montana. The project area is the lower mile of stream.
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Complete "Total Station" survey of floodplain below Kootenai River Road This objective has been completed by USFS (May 2001) 1 $0
Complete stream channel design a. FWP previously committed up to $15K for a USFS stream hydrologist to prepare a site plan. 3 $0
b. Work with landowners to ensure that the design is acceptable for all parties on lower Pipe Creek (funded by the Libby Mitigation Program) 3 $0
Contract the construction of the proposed plan a. Compile a qualified vendors list and solicit bids for the project based on the conceptual design. 3 $10,000 Yes
Implement the proposed design a. Fund cunstruction, supervise and manage implementation of the project. 2 $200,000 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
PIT tags # of tags: To be selected from qualified vendors list based on state bid process $210,000
$210,000
Total estimated budget
Total FY 2001 cost$210,000
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$210,000
FY 2001 forecast from 2000$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
USFS "Total Station" survey $0 in-kind
USFS Conceptual Design $15,000 cash

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Not fundable under this solicitation
Date:
Jun 21, 2001

Comment:

Not fundable under this solicitation. This proposal does not relate clearly to the current power emergency, is planned to happen anyway in the future, and does not appear that it can be accomplished quickly. Thus, immediate benefits are not apparent. No compelling argument is presented to expedite funding under this solicitation. This is a proposal to improve what is perceived to be needed improvement in passage of bull trout in Pipe Creek, Kootenai River. The proposal shows bull trout numbers steadily increasing in recent years making it difficult to follow the sponsor's reasoning for the poor passage conditions. The proposal does not make a convincing argument that conditions altered in the Kootenai River by the emergency action exacerbated problems for bull trout destined for Pole Creek. The proposal contains appropriate detail on planning and methods of stream reconstruction.