FY 2003 Middle Snake proposal 199701100
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
199701100 Narrative | Narrative |
199701100 Sponsor Response to the ISRP | Response |
199701100 Powerpoint Presentation | Powerpoint Presentation |
199701100 Powerpoint Presentation: 2003 Update | Powerpoint Presentation |
Middle Snake: Owyhee Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Middle Snake: Owyhee Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Section 1. Administrative
Proposal title | Enhance and Protect Habitat and Riparian Areas on the DVIR |
Proposal ID | 199701100 |
Organization | Shoshone-Paiute Tribes of the Duck Valley Indian Reservation (SPT - DVIR) |
Proposal contact person or principal investigator | |
Name | Guy Dodson Sr. |
Mailing address | Box 219 Owyhee, NV 89832 |
Phone / email | 2087593246 / DVIRFG98@aol.com |
Manager authorizing this project | Guy Dodson Sr |
Review cycle | Middle Snake |
Province / Subbasin | Middle Snake / Owyhee |
Short description | This project increases critical riparian areas of the Owyhee River and its tributaries as well as preserves the numerous natural springs located on the Duck Valley Indian Reservation. Provides a clean pure source of water for the fish and wildlife. |
Target species | Redband trout, Bull trout other wild resident trout species comprising the native community; anadromous salmonids reintroduction/off site mitigation; all wildlife species. |
Project location
Latitude | Longitude | Description |
---|---|---|
NW corner DVIR | ||
SW corner DVIR | ||
NE corner DVIR | ||
SE corner DVIR | ||
41.79 | -115.95 | Owyhee River |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1997 | Began habitat assessments on DVIR |
1997 | Began planting trees around lakes (1000 4-5' trees) |
1997 | Initiated erosion control of lakes |
1997 | Purchase equipment to begin habitat work |
1997 | Quarterly & Annual report |
1998 | Began habitat protection of natural springs (i.e. Exclosure fencing, water troughs for stock) |
1998 | Protected two headwater areas (one fork of the Three Forks, Willis meadows, protecting 2 miles of stream) |
1998 | Initial data on population location, age structure, size, and habitat condition on 6 streams and East Fork Owyhee River |
1998 | Began monitoring tree survival at lakes (Sheep Creek 35% survival, Mt. View 90%) |
1998 | Began monitoring of exclosures |
1998 | Began maintenance of exclosures, and springs |
1998 | Used fishery information to begin work on genetic assessment proposal |
1998 | Protected six springs (see map in narrative), located and prioritized future work |
1999 | Continued spring protection |
1999 | Began stream habitat rehabilitation (planted 50 willow shoots on 3 streams each) |
1999 | Continued maintenance and monitoring (repair exclosure fence, plumbing of troughs, photos of exclosure for future monitoring) |
1999 | Began stream habitat protection |
1999 | Protected 2 headwater areas 1 mile of stream protected (Boyle Creek, Watchabob) |
1999 | Protected 8 springs |
1999 | Collected water quality data and began monitoring biological parameters of streams (D.O, Ph, Temp) |
2000 | Continued Protective measures |
2000 | Protected 2 headwaters (protecting 1.5 miles of stream Boyle Creek, Willis Meadows) |
2000 | Protected 7 springs |
2000 | Continued monitoring of water quality |
2000 | Continued monitoring and maintenance of exclosures and springs |
2000 | Began to work with Tribal Environmental Department in monitoring |
2000 | Began to develop descriptions of streams, length, elevations, etc. |
2001 | Continued protective measures |
2001 | Protected 5 springs |
2001 | Protected 1 headwater area of suspected redband trout stream (Miller Creek, 1.5 miles of stream) |
2001 | Continued stream surveys, habitat and biological monitoring |
2001 | Worked with Project # 2000-079 in sharing data and information on trout streams, habitat conditions, biological information |
2001 | Continued with monitoring maintenance of springs and exclosures |
2001 | Fixed for road crossings (Skull Creek, Jones Creek 2, Little Sheep Creek) putting the stream back in channel and off road. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
8815600 | Implement Fishery Stocking Program Consistent With Native Fish Conservation | Project 97011 provides habitat and clean cold water to the reservoirs to help maintain the fishery |
9501500 | Lake Billy Shaw Fishery O&M | A new BPA- funded reservoir was completed in 1998 on the DVIR -- the development of its fisheries is an integral part of the habitat project. Same benefits as above. |
2000079 | Assess Resident Fish, E. Fork Owyhee Subasin | The habitat project will focus its efforts on where pure native trout populations are located once preliminary results are received. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. NEPA work required under contract - Cultural Resource survey | a. In coordination with Tribal Cultural Resource Dept. Survey areas before any ground disturbing activities | ongoing | $9,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. NEPA work required under contract - Cultural Resource survey | 4 | 7 | $40,000 |
Outyear budgets for Planning and Design phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$10,000 | $10,000 | $10,000 | $10,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. As per list of springs (narative section), begin spring protection | a. Meet with Shoshone-Paiute Livestock Association for prioritization of Springs to be protected/enhanced | ongoing | $10,000 | |
b. Utilizing Tribal, Natural Resources Dept, NRCS, and Tribal Envirinmental Department locate springs | ongoing | $5,000 | ||
c. Implement protective measures of springs (minimum of 6/year) | ongoing | $28,000 | ||
2. In coordination with Project 2000-079 and field observations/fishery work, implement stream protection | a. Locate and prioritize streams/stream reaches in need of protection | ongoing | $12,000 | |
b. Implement protective measures (fencing riparian areas/fixing road crossings) on streams and/or headwaters priority to suspected redband trout streams (appr. 6-10 miles of fence, troughs, culverts, etc) | ongoing | $25,000 | ||
3. Conduct Fishery and habitat surveys | a. Implement PFC assessment | ongoing | $20,000 | |
b. Conduct population estimates, size structure, condition, locations (GPS) in coordination with project 2000-079 | ongoing | $35,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. As per list of springs, begin spring protection | 4 | 7 | $190,000 |
2. In coordination with Project 2000-079 and field observations/fishery work, implement stream protection | 4 | 7 | $165,000 |
3. Conduct Fishery and habitat surveys | 4 | 7 | $235,000 |
Outyear budgets for Construction and Implementation phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$140,000 | $145,000 | $150,000 | $155,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. Maintain exclosures and fences | a. repair fence as needed every spring | ongoing | $30,000 | |
b. repair troughs, braces, or piping as needed | ongoing | $30,000 | ||
2. Equipment & Vehicle maintenance and rental | a. make needed repairs and maintenance on vehicle and ORV | ongoing | $20,000 | |
b. maintain fishery equipment and sampling gear | ongoing | $6,000 | ||
c. Vehicle lease/Rental | $10,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Maintain exclosures and troughs | 4 | 7 | $240,000 |
2. Maintain vehicles and equipment | 4 | 7 | $144,000 |
Outyear budgets for Operations and Maintenance phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$100,000 | $105,000 | $110,000 | $120,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. Collect Water quality data | a. Collect biological parameters (D.O. Temp, Ph, etc) | ongoing | $25,000 | |
b. Once a year to metals testing in Owyhee River w/ assistence of Tribal Environmental Program | ongoing | $10,000 | ||
2. Monitor and Evaluate habitat conditions | a. Monitor habitat conditions in exclosure areas via photo points, species diversity, airial photos (investigate habitat models and other monitoring and assessment protocols) | ongoing | $10,000 | |
b. Monitor and evaluate habitat conditions on streams and River using PFC assessment | ongoing | $25,000 | ||
3. Monitor springs and exclosures for improvement and flow | a. Monitor flows from springs protected for comparisons and evaluation of protection | ongoing | $14,000 | |
b. Monitor plant species composition inside and outside exclosure | ongoing | $11,000 | ||
c. Investigate other monitoring methods (HEP, Suitability Index Models) through USFWS, or other agencies having similar projects | ongoing | $9,696 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Collect Water quality data | 4 | 7 | $140,000 |
2. Monitor and Evaluate habitat conditions | 4 | 7 | $140,000 |
3. Monitor springs and exclosures for improvement and flow | 4 | 7 | $138,784 |
Outyear budgets for Monitoring and Evaluation phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$110,000 | $115,000 | $120,000 | $125,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2003 cost |
---|---|---|
Personnel | FTE: Director, Biologist, Technician 2 laborors | $122,000 |
Fringe | @ 20% of salaries | $24,400 |
Supplies | water troughs, fencing, pipe, fittings, tools,Also supplies for maintenance | $65,000 |
Travel | for local travel and BPA related travel | $5,000 |
Indirect | @24% of budget | $68,016 |
NEPA | For Cultural Resource Surveys NEPA cost | $9,000 |
Other | Equipment lease/rent, vehicle lease, | $51,280 |
$344,696 |
Total estimated budget
Total FY 2003 cost | $344,696 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2003 budget request | $344,696 |
FY 2003 forecast from 2002 | $325,000 |
% change from forecast | 6.1% |
Reason for change in estimated budget
No real change in projection
Reason for change in scope
NA
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
Southwest Idaho Resource Conservation and Development Council | Technical Assistance | $0 | in-kind |
National Riparian Service Team | PFC assessment training | $0 | in-kind |
Shoshone-Paiute Tribes Natural Resources Department | Technical Assistance | $0 | in-kind |
United States Fish and Wildlife Service | Technical Assistance/ Equipment loan, personnel loan | $0 | in-kind |
United States Forest Service | Technical Assistance | $0 | in-kind |
Bureau of Reclamation | Technical Assistance | $0 | in-kind |
Idaho Department of Environmental Quality | Technical Assistance | $0 | in-kind |
Shoshone-Paiute Tribes Cultural Resources Department | Technical Assistance NEPA Documentation | $0 | in-kind |
Shoshone-Paiute Tribes Environmental Protection Program | Technical Assistance Monitoring Assistance | $0 | in-kind |
Southwest Idaho Native Fish Watershed Advisory Group/Basin Advisory Group | Technical Assistance | $0 | in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable only if response is adequate
Mar 1, 2002
Comment:
Response needed. Based on the proposal and presentation, the reviewers saw no evidence the project warrants continued funding and a strong response would be needed to modify that position. The ISRP FY00 comments recommended "fund for one year to allow the project sponsors to better refine their project. Future long-term funding contingent on addressing deficiencies. The authors need to develop quantifiable biologically measurable objectives, without which one cannot evaluate whether the work achieves its goals. More detail is needed on how sites will be evaluated and the standards for success." The current proposal and recent presentation show no indication that these and other items previously identified by the ISRP have been addressed or adopted. Apparently this project did not complete a watershed assessment as proposed in FY00. The tasks completed to date (springhead fencing) do not appear to be providing significant, cost-effective benefits to fish and wildlife.Comment:
A M&E Plan needs to be completed for this project.Comment:
Not fundable. The response provided no new information to suggest the project activities significantly protect or enhance fish and wildlife resources. The ISRP noted in its preliminary review the lack of necessary detail on quantifiable biologically measurable objectives, methods, and M&E; however, the response did not provide any additional substantive detail on these deficiencies. The ISRP remains concerned that the project has too limited a focus. Fencing of the springheads only, without also fencing adjacent stream riparian areas, will not lead to significant habitat protection and fisheries benefits.Earlier ISRP reviews (FY 2000) recommended funding to the DVIR in order to support development of refined sampling protocols, project designs, and project descriptions. Detailed plans for M&E should be developed and reviewed by the ISRP before funding would be recommended. The ISRP believes that it is not appropriate to recommend unconditional funding for projects when one of ISRP's four primary review criteria from the 1996 Power Act amendment directs the ISRP to review and recommend only projects that "have provisions for monitoring and evaluation of results."
Comment:
Do not recommend funding new on ground implementation. To protect past investment, fund on-going O&M and review the need for continuing M&E. May not be an FCRPS responsibility to mitigate above Hells Canyon dam if not affected by the construction or operation of Black Canyon, Anderson Ranch, Boise Diversion, Minidoka, or Palisades reservoirs.Comment:
Project Issue 4: Shoshone Paiute Tribe project 199701100 Enhance and Protect Habitat and Riparian Areas on the DVIR
The ISRP rated as "Not Fundable" because of M&E element concerns. The province group and Council support continuing O&M to maintain past investment. The Council has advised the sponsor that the planning and design and construction and implementation funds requested cannot be provided unless and until needs until an M&E plan is reviewed and found acceptable by the ISRP. Council staff and the project sponsor are discussing a timeline for development and review of a reworked M&E plan for the proposal.
Comment:
Fund as recommended to continue O&M phase and to develop a revised M&E plan for ISRP review. No new construction implementation at this time. The Council recommended a budget of $292,696. Bonneville will review the total budget needs of the project based upon the initial proposal O&M estimate of $96,000 plus a negotiated amount for M&E plan development. The final budget may be less than the Council recommended budget of $292,696.Comment:
On track. Once M&E plan complete, contract will be modified (04). 04 & 05 rec amount ok.Comment:
NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$302,648 | $302,648 | $302,648 |
Sponsor comments: See comment at Council's website