FY 2002 Mountain Columbia proposal 24016

Additional documents

TitleType
24016 Narrative Narrative
24016 Sponsor Response to ISRP Response

Section 1. Administrative

Proposal titleKootenai River Subbasin Stakeholders Symposium
Proposal ID24016
OrganizationKootenai River Network (KRN)
Proposal contact person or principal investigator
NameGretchen Kruse
Mailing address214 E. Hayden Ave. Hayden ID 83835
Phone / email2087629800 / FRAQR@aol.com
Manager authorizing this projectCarolyn Stamy
Review cycleMountain Columbia
Province / SubbasinMountain Columbia / Kootenai
Short descriptionProvide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin (BC Canada, Montana and Idaho).
Target speciesWhite sturgeon, burbot, westslope cutthroat trout, bulltrout, mountain whitefish, redband rainbow trout, kokanee
Project location
LatitudeLongitudeDescription
48.9999 -116.5027 Kootenai River
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1996 Inventory of water quality and habitat restoration and improvement priorities -- EPA Regional Multi-Media Assistance
1997 Development of comprehensive water quality and aquatic habitat monitoring program -- EPA Habitat Improvement Project
1997 Six separate stream restoration projects -- EPA Habitat Improvement Project
1998 Mark Creek Conference
1998 Bull Trout Conference
1999 Strategic Planning workshop
1999 Non-Point Source Project -- Clean Water Act, Section 319 Funding

Section 3. Relationships to other projects

Project IDTitleDescription
8806400 Kootenai River White Strugeon Study and Conservaiton Aquaculture Program Participation of all stakeholders within the Kootenai River subbasin is crucial to the success of the proposed symposium which will be designed to accommodate diverse interests and acitivities-
8806500 (IDFG program) See previous line
Focus Watershed Coordination Project See previous line
9404900 Kootenai River Ecosystems Project See previous line
Kootenai Tribe of Idaho Water Resources Management Plan See previous line
Kootenai National Forest Habitat Enhancement Program See previous line

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin a)Symposium and partnership workshop and agenda development 3 $5,000 Yes
b)Expand the KRN website to accommodate documents that can be downloaded and to include links to related resource web sites 1 $200 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin 2003 2006 $23,534
Outyear budgets for Planning and Design phase
FY 2003FY 2004FY 2005FY 2006
$5,460$5,733$6,020$6,321

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin a)Symposium and partnership workshop outreach and promotion activities 3 $5,500 Yes
b)Convene symposium and all realted activities 3 $20,000 Yes
c)Develop, assemble and publish symposium materials 3 $4,000 Yes
d)Convene partnership workshop 3 $5,000 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin 2003 2006 $156,130
Outyear budgets for Construction and Implementation phase
FY 2003FY 2004FY 2005FY 2006
$36,225$38,036$39,938$41,935

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin a)Coordination of symposium and all related activities 3 $4,500 Yes
b) Coordination of partnership workshop and all related activities 3 $5,000 Yes
c)Maintenance of KRN website as a forum for information exchange through a central clearinghouse 3 $250 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin 2003 2006 $44,126
Outyear budgets for Operations and Maintenance phase
FY 2006FY 2003FY 2004FY 2005
$11,851$10,238$10,750$11,287

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin a)Symposium and partnership workshop evaluation 3 $1,000 Yes
b)Follow-up activities 3 $1,000 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1)Provide a forum to encourage resource information exchange among stakeholders in the Kootenai River subbasin 2003 2006 $9,051
Outyear budgets for Monitoring and Evaluation phase
FY 2003FY 2004FY 2005FY 2006
$2,100$2,205$2,315$2,431

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2002 cost
Personnel FTE: N/A $0
Fringe N/A $0
Supplies Hand outs, conference materials, follow-up/evaluation, stationery, workshop supplies $12,000
Travel Keynote speakers, special guests, facilitators $2,000
Indirect @9% $3,730
Capital N/A $0
NEPA N/A $0
PIT tags # of tags: 0 $0
Subcontractor Technical assistance, facilitators, graphic designer, workshop $25,220
Other Facility and equipment rental and related costs $8,500
$51,450
Total estimated budget
Total FY 2002 cost$51,450
Amount anticipated from previously committed BPA funds$0
Total FY 2002 budget request$51,450
FY 2002 forecast from 2001$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Kootenai River Network Coordination and support $5,000 cash
Kootenai Tribe of Idaho Coordination and support $3,000 in-kind
To be identified Banquet and breaks $2,000 cash
To be identified Coordination and support $5,000 in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Fundable only if response is adequate
Date:
Feb 9, 2001

Comment:

A response is needed that better defines project focus and justifies the budget. The sponsors should consider coordinating with the Lake Roosevelt Forum for the continuing education activities.

The Kootenai River Network proposes to enhance coordination and collaboration among various stakeholders in the Kootenai River Subbasin through an annual symposium and training workshop, and through the enhancement of a website. The symposium would provide a forum for information exchange among researchers, fish and wildlife managers, industry, environmental groups and landowners. The overall goal is to include those stakeholders in the process for their understanding of, and support for, fish and wildlife reclamation. A less pressing role is technical coordination, which also has other avenues.

The proposal is well prepared and reflects a thorough understanding of the technical issues by the authors, who are part of technical teams. The technical background gives an appropriate overview of the basin. It reflects the diversity of uses of basin lands and waters and resulting stakeholders. Significance to regional programs is clearly identified. Major players in the basin are listed, with their principal activities. The proposal reflects and cites the Subbasin Summary and white sturgeon Recovery Plan. It clearly states the importance of stakeholder participation. However, it does not cite the Columbia Basin Fish and Wildlife Program.

The proposal relates the planned symposium to other projects. It cites the analogous symposium in the Lake Roosevelt subbasin, and cites linkages to other projects in the basin, many by project number. The proposal is careful to say it is not intended to replace the information transfer functions of other projects. The objectives are clearly stated, along with appropriate tasks and activities (=methods, in this case). Evaluation of the symposium and workshops is a specified task. Facilities and equipment appear up to the work, and the staff is experienced in basin research activities as past or current participants. Information transfer is the main focus of the proposal. The website function looks like an effective way to maintain coordination and to educate the Province on subbasin planning.

The proposal makes a good case for the benefits of information exchange and coordination of recovery efforts given the size, diversity and remoteness of the subbasin. The project is modeled on the Lake Roosevelt Forum, which focuses on specific resident fish issues in the Inter-Mountain Province. However, the focus of this symposium is less clear. What would be the focus of the stakeholders meetings? Could the KRN evolve into a watershed council?

The project is likely to provide benefits to fish and wildlife through additional research/management, coordination and stakeholder participation and support.


Recommendation:
Recommended Action (Fund for 1 year only)
Date:
Mar 16, 2001

Comment:

Better coordination and information dissemination is needed between northern Idaho and western Montana fisheries agencies and stakeholders on the Kootenai River. Whether a specific symposium is necessary is not certain. Some of the coordination should be the responsibility of the focus watershed coordinator under Project Number 199608720. This project is not needed on an annual basis, only one year of funding should be considered.
Recommendation:
Fund
Date:
Apr 6, 2001

Comment:

Fundable. The response provides adequate detail on the project focus. It does not explain the need for budget items in detail but does indicate that reductions in budget are possible. The response regarding coordination with the Lake Roosevelt Forum is adequate.
Recommendation:
Fundable after Subbasin Planning
Date:
May 30, 2001

Comment:

This project should be reconsidered for funding after subbasin planning is completed as discussed in our cover letter. We have no comments in addition to the ISRP/CBFWA review comments.
Recommendation:
Do Not Fund
Date:
Oct 19, 2001

Comment:


Recommendation:
Do not fund
Date:
Mar 25, 2002

Comment:

Consistent with Council recommendation, BPA does not intend to fund.