FY 2002 Mountain Snake proposal 199700100

Section 1. Administrative

Proposal titleCaptive Rearing Project for Salmon River Chinook Salmon
Proposal ID199700100
OrganizationIdaho Department of Fish and Game and Idaho Office of Species Conservation (IDFG/IOSC)
Proposal contact person or principal investigator
NamePaul A. Kline
Mailing address1800 Trout Road Eagle, ID 83616
Phone / email2089394114 / pkline@idfg.state.id.us
Manager authorizing this projectSteve Yundt
Review cycleMountain Snake
Province / SubbasinMountain Snake / Salmon
Short descriptionDevelop captive rearing techniques for chinook salmon and evaluate the success and utility of captive rearing for maintaining stock structure and conservation levels of adult spawners in three drainages.
Target speciesSpring/summer chinook salmon
Project location
LatitudeLongitudeDescription
44.8699 -113.6256 Lemhi River near the mouth of Hayden Creek
44.3514 -114.7266 West Fork Yankee Fork Salmon River near its mouth
44.1075 -114.4235 East Fork Salmon River near hatchery weir and trap
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA
Hatchery RPA Action 170
Hatchery RPA Action 173
Hatchery RPA Action 174
RM&E RPA Action 182
RM&E RPA Action 184
Action 169
Action 175
Action 177
Action 178
Action 179

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription
NMFS Action 176 NMFS BPA shall, in coordination with NMFS, USFWS, and the relevant state and Tribal comanagers, fund the development of HGMPs for the Grande Ronde and Tucannon spring/summer chinook safety-net programs.
NMFS Action 177 NMFS In 2002, BPA shall begin to implement and sustain NMFS-approved, safety-net projects.
NMFS/BPA Action 177 NMFS In 2002, BPA shall begin to implement and sustain NMFS-approved, safety-net projects.

Section 2. Past accomplishments

YearAccomplishment
1995 Collected brood year 1994 spring chinook salmon parr from the Lemhi River, East Fork Salmon River, and West Fork Yankee Fork Salmon River, and captive-reared fish.
1996 Collected brood year 1995 spring chinook salmon juveniles from the Lemhi River and reared. Continued rearing brood year 1994 fish.
Less than 6% overall precocial (age 2) male maturation in brood year 1994 stocks.
Successful transfer of brood year 1994 fish to saltwater (at smoltification).
1997 Less than 30% age-3 male maturation in brood year 1994 stocks.
Successful outplanting of up to four, brood year 1994, three-year-old male chinook salmon to source streams. Movement and behavior documented.
Milt from brood year 1994 East Fork Salmon River and West Fork Yankee Fork Salmon River male chinook salmon cryopreserved.
Less than 6% male maturation in brood year 1995 Lemhi River chinook salmon (age 2).
Collection of brood year 1996 spring chinook salmon parr from the Lemhi River and West Fork Yankee Fork Salmon River.
Successful transfer of brood year 1995 fish to saltwater (at smoltification).
1998 Age 4 maturation in East Fork Salmon River (59%), West Fork Yankee Fork Salmon River (93%), and Lemhi River (74%) brood year 1994 stocks.
Less than 26% male maturation in brood year 1995 Lemhi River stock (age 3).
Outplanted captive reared maturing chinook adults (73 and 44 maturing adults to Lemhi River system and West Fork Yankee Fork Salmon River, respectively).
Conducted intensive evaluations of spawning-related behavior.
Documented 25 and 4 redds (constructed by captive program chinook) in the Lemhi River system and West Fork Yankee Fork Salmon River, respectivly.
Milt from brood year 1994, 1995, and 1996 captive chinook cryopreserved.
Successful hatchery pilot investigations of gamete quality and survival to the eyed-egg stage for spawn products produced by Lehmi River (brood year 1994, 1995), East Fork Salmon River (brood year 1994), and West Fork Yankee Fork Salmon River.
Eyed-eggs from gamete quality investigations outplanted to Lemhi River (9,320), West Fork Yankee Fork Salmon River (3,393), and East Fork Salmon River (17,279).
Collection of brood year 1997 spring chinook salmon parr from the Lemhi River and West Fork Yankee Fork Salmon River.
Successful transfer of brood year 1996 fish to saltwater (at smoltification).
1999 Age 5 maturation of brood year 1994 captive reared stocks and age 4 maturation of brood year 1995 captive reared stocks.
Cryopreserved milt from mature brood year 1996 and brood year 1997 West Fork Yankee Fork Salmon River chinook salmon.
Collected brood year 1998 natural parr from the Lemhi, West Fork Yankee Fork Salmon, and East Fork Salmon rivers.
Developed hydraulic sampling methods for collecting eyed-eggs from chinook redds to source program fish.
Collected brood year 1999 eyed-eggs from natural spawners in the East Fork Salmon and Lemhi rivers using hydraulic methods to establish captive populations.
Produced brood year 1999 West Fork Yankee Fork Salmon River and East Fork Salmon River safety-net brood stocks.
Eyed-eggs produced from safety net spawning distributed as follows: 2,297 outplanted to West Fork Yankee Fork Salmon River, 1,038 outplanted to East Fork Salmon River, and approximately 300 eyed-eggs from each stock retained to develop safety net groups.
Successful hatch and early rearing of fish for captive populations established from eyed-egg collections and safety-net populations.
Outplanted captive reared maturing chinook adults (62 and seven maturing adults to Lemhi River system and East Fork Salmon River, respectively.
Conducted intensive evaluations of spawning-related behavior in Bear Valley Creek - Lemhi River system (cooperatively with NMFS Resource Enhancement & Utilization Technologies Division research staff.
Recorded 433 unique observations of outplanted chinook salmon in Bear Valley Creek - Lemhi River system.
Recorded 30 direct obsevations of chinook salmon spawning in Bear Valley Creek - Lemhi River system (31 redds identified).
Successful transfer of brood year 1997 fish to saltwater (at smoltification).
2000 Age 5 maturation of brood year 1995 and age 4 maturation of brood year 1996 captive reared stocks.
Crypreserved milt from mature brood year 1997 West Fork Yankee Fork Salmon River chinook and brood year 1998 West Fork Yankee Fork Salmon River, East Fork Salmon River, and Lemhi River chinook.
Collected brood year 2000 eyed-eggs from natural chinook spawners in the East Fork Salmon, Yankee Fork Salmon, and West Fork Yankee Fork Salmon rivers.
Successful hatch and early rearing of captive populations established from eyed-egg collections.
Outplanted 72 captive reared maturing chinook adults to Big Springs Creek, a tributary of the Lemhi River.
Eyed-eggs from gamete quality investigations outplanted to West Fork Yankee Fork Salmon River (1,266).
Conducted intensive evaluations of spawning-related behavior in Big Springs Creek - Lemhi River system.
Identified 17 excavation sites and 15 confirmed redds (constructed by captive chinook outplants).
Successful transfer of brood year 1998 fish to saltwater (at smoltification).
Completed draft population viability assessment for Snake River chinook salmon.
2001 Initiation of cooperative research (with NMFS Resource Enhancement & Utilization Technologies Division staff) to quantify maturation timing and gamete development in captive-reared and ocean-returning chinook salmon adults
Initiation of research to evaluate the effects of water temperature on maturation timing in captive-reared chinook salmon.
Successful hatch and early rearing of captive populations established from eyed-egg collections.
Successful transfer of brood year 1999 fish to saltwater (at smoltification).

Section 3. Relationships to other projects

Project IDTitleDescription
199606700 Manchester Spring Chinook Broodstock Project This NMFS project complements IDFG Project 199700100 by sharing fish culture responsibility (seawater) for captive chinook salmon. This project serves to also reduce the risk of catastrophic loss.
199305600 Assessment of Captive Brood Stock Techniques This NMFS project develops information needed to overcome some of the problems that limit the development of viable broodstock adults and progeny.
198909600 Genetic Monitoring and Evaluation of Snake River Salmon and Steelhead This NMFS project provides genetic analysis of brood stock and wild chinook salmon.
199105500 NATURES This NMFS project develops and evaluates fish culture techniques. Topics that have direct bearing on the IDFG captive chinook proposal include exercise training and live food training in captive populations.
199009300 Genetic Analysis of Oncorhynchus Nerka - modified to include chinook salmon This University of Idaho project provides comprehensive genetics support to Project 199700100.
199107200 Redfish Lake Sockeye Salmon Captive Brood Stock Program This IDFG project shares facility resources and personnel with Project 199700100. Project responsibilities overlap and complement eachother.
199705700 Salmon River Production Program This Shoshone-Bannock Tribes project assists the IDFG captive chinook project with the out planting of eggs from hatchery spawning investigations. The SBT provides additional assistance with adult out plants and juvenile production assessments.
200001900 Tucannon River Spring Chinook Captive Broodstock Program This WDFW project develops captive broodstock techniques that are relevant to the IDFG captive chinook program.
199604400 Grande Ronde Basin Spring Chinook Captive Broodstock Program This ODFW program provides complimentary information from captive broodstock efforts inplace to maintain and rebuild three stocks of spring chinook salmon in the Grande Ronde River basin of Oregon.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
3. Complete NPPC four-step process to initiate artificial propagation safety net programs for spring/summer chinook salmon A. Complete population viability assessment (extinction risk analysis, step 1) initiated in FY01. 1 $7,800
B. Develop intervention options (step 2). 1 $11,400
C. Conduct benefit-risk analyses for proposed strategies (step 3). 1 $14,800
D. Develop HGMP's (step 4) to guide implementation of safety net projects. 1 $11,410
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
3. Objective will continue as "construction/implementation" phase. $0
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
1. Produce captive-reared adult chinook salmon with morphological, physiological, and behavioral characteristics similar to naturally produced fish. A. Maintain facilities to produce captive-reared adult chinook salmon and attain objectives. ongoing $81,905
B. Modify facilities (hatchery building well field) to meet water demands, and life support system safety requirements to meet basic program rearing needs to atain objectives. 1 $106,000
C. Develop final costs and modification plans to enclose outside raceways, provide photoperiod control, and provide additional chilled water capability to meet basic program rearing needs to atain objectives. 3 $97,000
D. Collect fish/eggs from three stocks to initiate rearing groups. Rear captive chinook salmon through maturation. Compare captive-reared adults to wild/natural conspecifics. ongoing $122,521
E. Monitor and adaptively manage culture protocols as they relate to fish survival, fish growth, and fish maturation. ongoing $41,030
F. PIT tag and visual implant tag all fish to facilitate poulation isolation and tracking during captive culture. ongoing $13,100
G. Cryopreserve milt from male captive chinook salmon as needed to preserve future options. ongoing $10,170
2. Evaluate spawning behavior and successof out planted (captive-reared) adults. A. Tag adults with externally visible tags prior to out planting and radio-tag a resonable number of fish for field tracking. ongoing $6,750
B. Out plant maturing captive-reared chinook salmon to appropriate stream study sections. ongoing $12,350
C. Monitor and document movement, distribution, behavior, and spawning success of out planted fish. ongoing $80,630
D. Identify and document location of radio-tagged fish daily. ongoing $39,612
E. Map redd locations and note observed spawning pairings. ongoing $35,550
F. Hydraulically sample completed redds and perform snorkel surveys to verify and estimate production. ongoing $5,920
G. Evaluate gamete quality and survival to the eyed-egg stage of development. ongoing $7,305
4. Information/Technology transfer. A. Participate in Technical Oversight Committee process. ongoing $20,876
B. Newtork with technical experts on issues related to fish culture, genetics, pathology, fish maturation phisology, and monitoring and evaluation ongoing $6,472
C. Develop cooperative program management plan. ongoing $2,965
D. Coordinate information dissemination with project cooperators. ongoing $2,516
E. Provide written activity reports to satisfy the needs and requirements of IDFG, the technical oversight committee, NMFS, and BPA. ongoing $12,400
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Produce captive-reared adult chinook salmon with morphological, physiological, and behavioral characteristics similar to naturally produced fish. 2003 2006 $1,717,450
2. Evaluate spawning behavior and success of out planted (captive-reared) adualts. 2003 2006 $851,358
3. Implementation phase of NPPC four-step process to initiate artificial propagation safety net programs for spring/summer chinook salmon 2003 2006 $2,900,000
4. Information/Technology transfer. 2003 2006 $204,690
Outyear budgets for Construction and Implementation phase
FY 2003FY 2004FY 2005FY 2006
$1,800,000$1,500,000$1,300,000$1,200,000

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2002 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2002 cost
Personnel FTE: 2.5 permanent, 3.9 temporary $178,672
Fringe $58,960
Supplies $209,200
Travel Technical meetings, fish transfers, workshops $13,800
Indirect $103,600
Capital Water chilling, pumping, and building acquisitions and improvements $184,000
PIT tags # of tags: 1000 $2,250
$750,482
Total estimated budget
Total FY 2002 cost$750,482
Amount anticipated from previously committed BPA funds$0
Total FY 2002 budget request$750,482
FY 2002 forecast from 2001$515,000
% change from forecast45.7%
Reason for change in estimated budget

The Fiscal Year 2002 budget reflects increased costs associated with hatchery facility maintenance and equipment repair, fixed operational costs, hatchery water system and building modification costs, and chinook out planting costs . Details are presented in Part 2, Section f. of this proposal.

Reason for change in scope

No change

Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Idaho Department of Fish and Game Cost sharing with Project No. 199107200 for Eagle Hatchery water system modification costs $57,000 in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Fundable only if response is adequate
Date:
Sep 28, 2001

Comment:

A response is needed. Reviewers appreciate sponsor's effort to review what has happened in past, and the detailed presentation of results and conclusions to date. The project could benefit significantly, however, by including evaluation of performance (all kinds) of the hatchery-produced fish.

The sponsors need to explain what is to be different about fish now being produced so that there is some reason to do more assessment.

The project seems to have some inconsistent elements. For example, the goal is to develop captive rearing techniques. Hasn't NMFS been doing that with Puget Sound chinook salmon for 20 or more years? An argument for initiating the project was to preclude loss of important sub-populations of chinook salmon. By stocking experimental fish in Bear Valley Creek, not one of the donor streams, isn't the project potentially increasing jeopardy for the sub-population inhabiting Bear Valley Creek? Also, why, in a project to develop rearing techniques was it necessary to use three sub-populations?

The project goal was do develop culture techniques, and to assess the spawning success in nature of the fish produced. Although the growth and survival of the experimental fish has not been comparable to fish produced in nature, hasn't that goal been met? It now seems the goal has changed to one of improving growth, survival, and performance of the fish produced. Why is this new goal necessary? If it is necessary, do growth, survival, and performance of the fish produced have to be comparable to that of wild fish? Please explain your intent here.

You propose to " ...complete NPPC [NMFS] 4-step process to initiate artificial propagation safety net programs for spring/summer chinook salmon. If this is now an implementation project, isn't it premature in the 4-step process?

One identified task is to develop HGMPs. Will this be done in collaboration with other proposals to develop HGMPs (e.g., for hatcheries in the LSRCP)? If not, why not?


Recommendation:
High Priority
Date:
Nov 30, 2001

Comment:

The results from this work will significantly benefit the target populations. This project has had significant peer review and is guided by a technical oversight committee. This project is considered a BASE project by NMFS in regards to the 2000 Biological Opinion. This project should eventually be tied into the Safety Net Artificial Production Program (SNAPP) process.
Recommendation:
Fund
Date:
Dec 21, 2001

Comment:

Fundable, but low priority - Sponsors provided reasonable and detailed answers to reviewers' questions and comments. Questions remain, however, about the need to alter the performance traits of the captive brood to make them similar to fish in nature. These characters are largely dependent on environment so characteristics of fish reared in hatcheries will reflect those conditions, and of fish produced in nature will reflect those conditions. Detailed and careful work to produce fish with similar characteristics from either set of conditions is certain to require a continuing, and long-term effort, and in the view of some reviewers, perhaps a flawed strategy. Sponsors need to reassess what they are doing in his project. It appears from the review that the project will never be "complete."
Recommendation:
Date:
Feb 1, 2002

Comment:

Statement of Potential Biological Benefit to ESU
Intended to restore high-risk chinook populations and test captive-rearing techniques

Comments
This project has tested "captive rearing" of fish from natural parr or eggs, that are subsequently released for natural spawning as adults, as opposed to "captive broodstock" as in some other chinook and sockeye programs. These populations should be evaluated under SNAPP and future actions guided by the review.

Already ESA Req? No

Biop? Yes


Recommendation:
A Conditonal
Date:
Feb 11, 2002

Comment:

Recommend contingent upon reassessment of objectives and full integration with SNAPP for implementation of RPA 175.

BPA RPA RPM:
175

NMFS RPA/USFWS RPM:
base


Recommendation:
Fund
Date:
Apr 19, 2002

Comment:


Recommendation:
Fund
Date:
Jun 13, 2002

Comment:

Fund to implement RPA 177, contingent upon meeting NPPC's requirements for captive brood projects.
Recommendation:
Fund
Date:
Sep 20, 2003

Comment:

Waiting on contract renewal. Increases to offset increases associated with indirect costs/benefits/ facility O&M needs, chiller compressor motor, fleet increases, Captive project, issue 12. Draft submittal received.
Recommendation:
Date:
Sep 20, 2003

Comment:

Increases needed to offset increased costs associated with employee salary and benefit rates, vehicle fleet rental rates, special-use vehicle (e.g., backhoe, tractor, cart) rental rates, fish transportation truck rental rates, computer equipment rental rates, and utility charges (added one new pumping system and additional chiller capacity). Scheduled replacement of chiller compressor motors.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$509,000 $509,000 $509,000

Sponsor comments: See comment at Council's website