FY 2000 proposal 20527

Additional documents

TitleType
20527 Narrative Narrative

Section 1. Administrative

Proposal titleMulti-Year Wenatchee River Anadromous Fish Plan
Proposal ID20527
OrganizationColumbia Basin Fish & Wildlife Authority (CBFWA)
Proposal contact person or principal investigator
NameTom Giese
Mailing address2501 SW First Ave., Suite 200 Portland, OR 97201
Phone / email5032290191 / tom@cbfwf.org
Manager authorizing this project
Review cycleFY 2000
Province / SubbasinColumbia Cascade / Wenatchee
Short description
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
20527 MYP Wenatchee River Anadromous Fish Plan
9604000 Re-establish coho in Wenatchee and Methow rivers through supplementation.
9044 Replace the Chumstick Creek culvert, a fish passage impediment.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2000 cost
Personnel $0
Fringe $0
Supplies $0
$0
Total estimated budget
Total FY 2000 cost$0
Amount anticipated from previously committed BPA funds$0
Total FY 2000 budget request$0
FY 2000 forecast from 1999$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
NA - Umbrella Proposal
Date:
Jun 15, 1999

Comment:

Recommendation: NA - Umbrella Proposal

Comments: Very little detail


Recommendation:
Do Not Fund
Date:
Aug 20, 1999

Comment:


Recommendation:
Date:
Aug 20, 1999

Comment:

Technical Criteria 1: Met? NA - While there are descriptions of the facilities, which are adequate for raising fish (they've been doing it for over 50 yrs), the proposal does not indicate who will be responsible or even how many FTEs will be used or what specifically the budget is to coordinate.

Programmatic Criteria 2: Met? NA - Inadequate

Milestone Criteria 3: Met? NA -

Resource Criteria 4: Met? NA -