FY 2001 Ongoing proposal 199600700
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
Mountain Snake: Salmon Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Mountain Snake: Salmon Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Section 1. Administrative
Proposal title | Irrigation Diversion Consolidation and Water Consolidation |
Proposal ID | 199600700 |
Organization | Lemhi Soil and Water Conservation District (Lemhi SWCD) |
Proposal contact person or principal investigator | |
Name | Patrick Marcuson |
Mailing address | P. O. Box 1336 Salmon, ID 83467 |
Phone / email | 2087566022 / pmarcuso@idfg.state.id.us |
Manager authorizing this project | Patrick Marcuson |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Mountain Snake / Salmon |
Short description | Irrigation consolidation of gravity diversions S-13(10 Acre Canal)with S-14 (Pope Canal)and consolidation of S-11(Edwards Canal) withS-12(Kane-Ramey Canal).Eliminate2 of 4 wingdams,2 of 4 screens,2 of 4 headgates & reduce migrational delay of all fish. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|---|---|---|
NMFS/BPA | Action 149 | NMFS | BOR shall initiate programs in three priority subbasins (identified in the Basinwide Recovery Strategy) per year over 5 years, in coordination with NMFS, FWS, the states and others, to address all flow, passage, and screening problems in each subbasin over 10 years. The Corps shall implement demonstration projects to improve habitat in subbasins where water-diversion-related problems could cause take of listed species. Under the NWPPC program, BPA addresses passage, screening, and flow problems, where they are not the responsibility of others. BPA expects to expand on these measures in coordination with the NWPPC process to complement BOR actions described in the action above. |
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1997 | Project was designed in concept. |
1998 | Topographic map of sites were surveyed. |
1998 | Irrigators were asked if they were willing to consolidate their ditches. |
1999 | Preliminary designs of the diversion dams, headgates, and canal alignment and size was completed by USBR. |
1999 | Preliminary designs of fish screens were engineered by IDFG. |
1999 | More meetings with irrigators defining water saving and fish benefits of the consolidation. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
Finalize the consolidation of S-11 with S-12 and S-13 with S-14. | a) Collect more water discharge data | One Year | $0 | |
b) Complete tasks remaining after FY2000 construction | One Year | $80,000 | Yes | |
c) Build and install splitter boxes to distribute water to proper canals. | One Year | $140,000 | ||
d) Rehab construction site and plant vegetation. | One Year | $25,000 | ||
e) Educate public and users on benefits to fish. | One Year | $5,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Personnel | FTE: Note: All planning and design was completed by cost shared funds. | $0 |
Personnel | FTE: All on site inspection and fabrication in Fish Screen Shop cost shared. | $0 |
Capital | Metal Fabrication | $60,000 |
Subcontractor | Civil contract bid winner | $190,000 |
Personnel | FTE: Note: All operating and maintenance by cost shared funds. | $0 |
Personnel | FTE: Note: all monitoring and evaluation by cost shared funds. | $0 |
$250,000 |
Total estimated budget
Total FY 2001 cost | $250,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $250,000 |
FY 2001 forecast from 2000 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
REVIEW:
CBFWA Funding Recommendation
CBFWA Funding Recommendation
Recommendation:
Ongoing Funding: yes; New Funding: no
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
Jul 14, 2000
Comment:
There is no change in scope or budget.Comment:
As of 9/8 the project has a balance of $293,113.Comment:
Comment: