FY 2004 Within-year Modification proposal 199205900
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Section 1. Administrative
Proposal title | Amazon Basin/Eugene Wetlands Phase Two |
Proposal ID | 199205900 |
Organization | The Nature Conservancy (TNC) |
Proposal contact person or principal investigator | |
Name | Catherine A. Macdonald |
Mailing address | 821 SE 14th Avenue Portland, Oregon 97214 |
Phone / email | 503-230-1221 / cmacdonald@tnc.org |
Manager authorizing this project | Catherine A. Macdonald |
Review cycle | Within-year Modification |
Province / Subbasin | Lower Columbia / Willamette |
Short description | |
Target species | Beaver, black-capped chickadee, red-tailed hawk, valley quail, western meadowlark, yellow warbler, and western pond turtle. Willamette Basin Wildlife Habitat Protection, Mitigation, and Enhancement Plan, ODFW, 1997. |
Project location
Latitude | Longitude | Description |
---|---|---|
Located in the Willamette Valley ecoregion, situated at the margin of the valley floor on the western edge of Eugene. This site is in the Willow Creek watershed. Willow Creek is a tributary of Amazon Creek and the Long Tom River. |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
9206800 | Implementation of Willamette Basin Mitigation Program - Wildlife | Umbrella project |
9705900 | Securing Wildlife Mitigation sites - Oregon | Umbrella project |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|---|---|---|---|
Acquire 65-acres of highest priority adjacent habitat to expand wildlife credits and improve overall viability of the site for wildlife use. | Complete appraisals, title research, hazardous assessments in order to acquire property and convey permanent mitigation rights. | FY04 | $1,200,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2004 cost |
---|---|---|
$0 |
Total estimated budget
Total FY 2004 cost | $0 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2004 budget request | $0 |
FY 2004 forecast from 2003 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
City of Eugene | Wetlands delineation | $5,000 | cash |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$62,712 | $62,712 | $62,712 |
Sponsor comments: See comment at Council's website