Proposal titleIDL Maggie Cr. Area Fish Passage Proposal
Proposal ID200734200
OrganizationIdaho Department of Lands
Short descriptionThis proposal seeks to replace fish passage blocking culverts with fish passage structures. This will increase the quantity of available suitable fish habitat.
Information transferThis information will be transfered on-line.
Proposal contact person or principal investigator
Contacts
ContactOrganizationEmail
Form submitter
Pete Van Sickle Idaho Department of Lands pvansickle@idl.state.id.us
All assigned contacts

Section 2. Locations

Province / subbasin: Mountain Snake / Clearwater

LatitudeLongitudeWaterbodyDescription
46.13.2 -115.50.18 Cabin Creek T33N, R5E, Sec.9
46.12.22 -115.49.34 Lohrey Cr. T33N, R5E, Sec. 27
46.11.27 -115.48.45 Lolo Cr. T34N, R5E, Sec.23
46.11.8 -115.48.7 Maggie Cr. T33n, R5E, Sec. 23
46.11.9 -115.47.57 N. Fork Maggie Cr. T3N, R5E, Sec. 15
46.10.54 -115.48.45 Pete and Charlie Cr. T34N, R5E, Sec. 15
46.10.37 -115.48.29 Suttler Cr. T33N, R5E, Sec. 23
46.17.36 -115.48.57 Suttler Cr. T33N, R5E, Sec. 23
46.17.29 -115.47.11 Suttler Cr. T33N, R5E, Sec. 22
46.17.14 -115.46.52 Trout Cr. T34N, R5E, Sec. 14
46.17.2 -115.46.44 Trout Cr. T34N, R5E, Sec. 13
46.16.11 -115.48.4 Trout Cr. T34N, R5E, Sec. 13
46.11.30 -115.48.16 Maggie Cr. T33N, R5E, Sec.22

Section 3. Focal species

primary: Chinook Snake River Spring/Summer ESU
primary: Steelhead Snake River ESU
secondary: All Resident Fish
secondary: Cutthroat Trout
secondary: Brook Trout
secondary: Bull Trout
secondary: Rainbow Trout

Section 4. Past accomplishments

YearAccomplishments

Section 5. Relationships to other projects

Funding sourceRelated IDRelated titleRelationship
[Funding Source left blank] [no entry] This project is not related to anyother projects by IDL.
[Funding Source left blank] [no entry] There are no on-going projects within the general local related to this proposal.

Section 6. Biological objectives

Biological objectivesFull descriptionAssociated subbasin planStrategy
F. Resident fish species Prioritize activities to improve cutthroat and bull trout habitat Clearwater Strategy 2. Improve gabitat conditions for native populations by increasing the existing habitat available.
P. Reduce number of artifically blocked streams Prioritize barriers to fish passage for treatment Clearwater 2. Prioritize barriers for removal or modification 3. Remove or midify human-caused problems
S. Reduce stream sedimentation Prioritize projects to reduce sedimentation. Clearwater 4. Reduce sediment by implementing practicies that address problems

Section 7. Work elements (coming back to this)

Work element nameWork element titleDescriptionStart dateEnd dateEst budget
Install Fish Passage Structure Increase quantity of available habitat by improving fish passage structures This project will replace culverts blocking fish passage with structures that allow for fish passage during all seasons of fish use. 7/1/2007 10/31/2009 $630,000
Biological objectives
Metrics
* # of miles of habitat accessed: 18.35 miles
* Does the structure remove or replace a fish passage barrier?: Yes
* Was barrier Full or Partial?: Full

Section 8. Budgets

Itemized estimated budget
ItemNoteFY07FY08FY09
Supplies Includes all costs associated with removal of existing structure and replacement with new structure where applicable $210,000 $220,000 $200,000
Totals $210,000 $220,000 $200,000
Total estimated FY 2007-2009 budgets
Total itemized budget: $630,000
Total work element budget: $630,000
Cost sharing
Funding source/orgItem or service providedFY 07 est value ($)FY 08 est value ($)FY 09 est value ($)Cash or in-kind?Status
Idaho Department of Lands Planning, Design, Project Administration $13,000 $13,000 $13,000 In-Kind Confirmed
Totals $13,000 $13,000 $13,000

Section 9. Project future

FY 2010 estimated budget: $0
FY 2011 estimated budget: $0
Comments:

Future O&M costs:

Termination date: 12/31/2009
Comments: Termination of project occurs when stream crossing structures are completed to project specifications and all contractual payments are completed.

Final deliverables: Final deliverables include existing structures removed and disposed and replacement structures installed and site prepared to specifications.

Section 10. Narrative and other documents


Reviews and recommendations

FY07 budget FY08 budget FY09 budget Total budget Type Category Recommendation
NPCC FINAL FUNDING RECOMMENDATIONS (Oct 23, 2006) [full Council recs]
$0 $0 $0 $0 Expense ProvinceExpense Do Not Fund
NPCC DRAFT FUNDING RECOMMENDATIONS (Sep 15, 2006) [full Council recs]
$0 $0 $0 $0 ProvinceExpense

ISRP PRELIMINARY REVIEW (Jun 2, 2006)

Recommendation: Response requested

NPCC comments: This is one of three Idaho Department of Lands projects (200729600, 200734200, and 200736100) to remove culverts in streams of the Clearwater Basin. It is proposed here to replace eight culverts perceived to be blocking access to productive habitat for migratory fish in Lolo and Maggie creeks. The ISRP requests a joint response for the three projects (200729600, 200734200, and 200736100) to items listed under Project 200729600.


ISRP FINAL REVIEW (Aug 31, 2006)

Recommendation: Response requested

NPCC comments: This is one of three Idaho Department of Lands projects (200729600, 200734200, and 200736100) to remove culverts in streams of the Clearwater Basin. It is proposed here to replace eight culverts perceived to be blocking access to productive habitat for migratory fish in Lolo and Maggie creeks. The ISRP requests a joint response for the three projects (200729600, 200734200, and 200736100) to items listed under Project 200729600.