FY 2001 Action Plan proposal 26003
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
26003 Narrative | Narrative |
Design Drawings | Narrative Attachment |
Section 1. Administrative
Proposal title | Fox Creek Daylighting, Rainier, Oregon |
Proposal ID | 26003 |
Organization | City of Rainier (Rainier, WA) |
Proposal contact person or principal investigator | |
Name | Chad Olsen |
Mailing address | P.O. Box 100 Rainier, OR 97048 |
Phone / email | 5035567301 / chad@cityofrainier.com |
Manager authorizing this project | Taunja Berquam, U.S. Army Corps of Engineers |
Review cycle | FY 2001 Action Plan |
Province / Subbasin | Lower Columbia / Lower Columbia |
Short description | The proposed modification would entail restoration of the Fox Creek stream channel for an approximate distance of 735 feet inland from its confluence with the Columbia River. Request $30,000 to match Corps of Engineers Section 1135 funding. |
Target species | coho salmon and steelhead |
Project location
Latitude | Longitude | Description |
---|---|---|
46.0845 | -122.9325 | City of Rainier, 45 miles NW of Portland, Oregon on the Columbia River |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
Improve habitat, fish passage | a.complete planning and design b.construct restored channel | 12 | $412,000 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
FY 2002 | FY 2003 | FY 2004 | FY 2005 |
---|---|---|---|
$500 | $500 | $500 | $500 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Capital | 412,000 | $412,000 |
$412,000 |
Total estimated budget
Total FY 2001 cost | $412,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $412,000 |
FY 2001 forecast from 2000 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
U.S. Army Corps of Engineers | Design & Construction | $300,000 | cash |
Friends of Fox Creek | property appraisal | $2,000 | in-kind |
City of Rainier | Lands easements and rights of way | $80,000 | in-kind |
BPA | Cost share | $30,000 | cash |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
REVIEW:
ISRP Review (ISRP 2001-7)
ISRP Review (ISRP 2001-7)
Recommendation:
Not fundable under this solicitation
Not fundable under this solicitation
Date:
Jun 21, 2001
Jun 21, 2001
Comment:
Not fundable under this solicitation. This does not fit the scope of the solicitation. This proposal is for passage improvements on a tributary below the dams and does not focus benefits on species that are impacted by the power system emergency operations.