Section 1. Administrative
Proposal title | Clackamas County 2001 Fish Passage Improvements in the Clackamas, Abernethy and Molalla River Watersheds. |
Proposal ID | 26024 |
Organization | Clackamas County Department of Transportation & Development / Road Maintenance Division (Clackamas Co.) |
Proposal contact person or principal investigator | |
Name | Mark Mouser |
Mailing address | 902 Abernethy Road Oregon City, OR 97045 |
Phone / email | 5036503245 / markmou@co.clackamas.or.us |
Manager authorizing this project | Dave Watson, Road Maintenance Supervisor |
Review cycle | FY 2001 Action Plan |
Province / Subbasin | Lower Columbia / Willamette |
Short description | Restore 26 miles of high quality spawning and rearing habitat in 3 Willamette River subbasins to both ESA-listed anadromous and resident species of fish by remediating 14 existing culvert barriers with fish passable structures. |
Target species | Anadromous Chinook Salmon, Coho Salmon, Steelhead Trout, Pacific Lamprey and Resident Cutthroat Trout and Brook Lamprey |
Project location
Latitude | Longitude | Description |
---|---|---|
45.3237 | -112.5005 | a.Henrici Road at Mile Point 4.13. Clackamas County, OR. SE Quarter of Section 12, Township 3S, Range 2E near Redland. |
45.3783 | -122.4307 | b.Bakers Ferry Road at Mile Point 1.35. Clackamas County, OR. SW Quarter of Section 21, Township 2S, Range 3E, near Carver. |
45.382 | -122.3868 | c. Amisigger Road at Mile Point 0.04. Clackamas County, OR. NE Quarter of Section 23, Township 2S, Range 3E near Boring. |
45.3858 | -122.2822 | d. Colorado Road at Mile Post 0.71. Clackamas County, OR. SW Quarter of Section 14, Township 2S, Range 4E. near Sandy. |
45.173 | -122.6337 | e. Elisha Road at Mile Point 0.61. Clackamas County, OR. NW Quarter of Section 01, Township 5S, Range 1E. near Molalla. |
45.1597 | -122.5385 | f. Macksburg Road at Mile. Point 0.41. Clackamas County, OR. SE Quarter of Section 03, Township 5S, Range 2E near Molalla. |
45.254 | -122.5323 | g. Newkirchner Road at Mile Point 0.17. Clackamas County, OR. SW Quarter of Section 02, Township 4S, Range 2E near Mulino. |
45.2327 | -122.5378 | h. Newkirchner Road at Mile Point 1.66. Clackamas County, OR. SW Quarter of Section 10 Township 4S, Range 2E near Mulino. |
45.4077 | -122.4348 | i. Royer Road at Mile Point 0.71. Clackamas County, OR. NW Quarter of Section9, Township 2S, Range 3E near Damascus. |
45.1728 | -122.5757 | j. Sprague Road at Mile Point 0.11. Clackamas County, OR. SW Quarter of Section 33. Township 4S, Range 2E near Molalla. |
45.2095 | -122.4398 | k. Unger Road at Mile Point 4.12. Clackamas County, OR. SW Quarter of Section 16, Township 4S, Range 3E near Clarkes. |
45.3398 | -122.3287 | l. Van Curen Road at Mile Point 0.51. Clackamas County, OR. SW Quarter of Section 33, Township 2S, Range 4E near Eagle Creek. |
45.2063 | -122.656 | m. Dryland Road at Mile Point 7.80. Clackamas County, OR. NW Quarter of Section 22, Township 4S, Range 1E near Canby. |
45.434 | -122.3028 | n. Brooks Road at Mile Point 0.25. Clackamas County, OR. SW Quarter of Section 34, Township 1S, Range 4E. near Boring. |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Increase anadromous and resident fish populations by replacing 14 culverts that are barriers to fish passage, reestablishing access to quality spawning and rearing habitat. | a. Replace Henrici Road MP 4.13 Crossing | 0.5 months. | $40,916 | |
b. Replace Bakers Ferry Road MP 1.35 Crossing | 3 months | $880,000 | Yes | |
c. Replace Ammisigger Road MP 0.04 Crossing | 0.5 months | $57,638 | ||
d. Colorado Road MP 0.71 Crossing | 0.5 months | $27,832 | ||
e. Elisha Road MP 0.61 Crossing | 0.5 months | $41,223 | ||
f. Macksburg Road MP 0.40 Crossing | 0.5 months | $52,921 | ||
g. Newkirchner Road 0.17 Crossing | 0.5 months | $27,569 | ||
h. Newkirchner Road MP 1.66 Crossing | 0.5 months | $44,823 | ||
i. Royer Road MP 0.70 Crossing | 0.5 months | $56,963 | ||
j. Sprauge Road MP 0.11 Crossing | 0.3 months | $29,174 | ||
k. Unger Road MP 4.12 Crossing | 0.5 months | $46,711 | ||
l. Van Curen Road MP 0.51 Crossing | 0.5 months | $42,436 | ||
m. Dryland Road MP 7.80 Crossing | 0.75 months | $56,062 | ||
n. Brooks Road MP 0.25 Crossing | 0.5 months | $34,596 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
FY 2002 | FY 2003 | FY 2004 | FY 2005 |
---|---|---|---|
$910 | $910 | $910 | $910 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
FY 2002 | FY 2003 | FY 2004 | FY 2005 |
---|---|---|---|
$910 | $910 | $910 | $910 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Personnel | FTE: 6733 hours | $275,990 |
Fringe | $124,354 | |
Supplies | Pipe, structures, rock | $181,666 |
Capital | Right of Way | $50,000 |
PIT tags | # of tags: Bid Opening May 25th, 2001 | $660,000 |
Subcontractor | Equipment costs (Rental, fuel, etc.) | $146,854 |
$1,438,864 |
Total estimated budget
Total FY 2001 cost | $1,438,864 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $1,438,864 |
FY 2001 forecast from 2000 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
Oregon Watershed Enhancement Board | Cash | $939,865 | cash |
U.S. Fish & Wildlife Service | Cash | $45,000 | cash |
Trout Unlimited | Plants and volunteer labor for replanting | $3,250 | in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
REVIEW:
ISRP Review (ISRP 2001-7)
ISRP Review (ISRP 2001-7)
Recommendation:
Not fundable under this solicitation
Not fundable under this solicitation
Date:
Jun 21, 2001
Jun 21, 2001
Comment:
Not fundable under the current solicitation. This proposal does not meet the scope of the solicitation. This proposal is for a project that is below the dams and does not focus benefits on species that are impacted by the power system emergency operations. However, the proposal is well done and is technically sound. One strength of this proposal is the prior identification of nearly 1000 culvert-stream crossings, of which the 14 identified for replacement in this proposal, are recognized passage barriers to anadromous chinook, coho, or steelhead. This is a relatively expensive proposal at $1.4 million, yet it also notes nearly a million dollars of cost share. Permitting appears to be in place for 13 of the 14 proposed sites. The Lower Columbia Province proposal solicitation is scheduled for late fall of 2001, and the proposal might be resubmitted at that time.