FY 2003 Middle Snake proposal 32002
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
32002 Narrative | Narrative |
32002 Sponsor Response to the ISRP | Response |
32002 Powerpoint Presentation | Powerpoint Presentation |
Section 1. Administrative
Proposal title | Implement Best Management Practices to improve riparian habitat and upland conditions within the Billingsley Creek watershed. |
Proposal ID | 32002 |
Organization | Gooding Soil Conservation District (Gooding SCD) |
Proposal contact person or principal investigator | |
Name | David F. Ferguson |
Mailing address | P. O. Box 790 Boise, ID 83701 |
Phone / email | 2083328654 / dferguso@agri.state.id.us |
Manager authorizing this project | Bob Bolte, Chairmen, GSCD |
Review cycle | Middle Snake |
Province / Subbasin | Middle Snake / Snake Upper Middle |
Short description | Enhance riparian habitat and reduce nonpoint source pollution within the Billingsley Creek watershed through the development and implementation of conservation plans on private lands, coordinated with state owned and managed lands within the watershed. |
Target species | Redband Trout, Brown Trout |
Project location
Latitude | Longitude | Description |
---|---|---|
T7S, R13E, Section 32 (headwaters) down to section 11 (mouth) | ||
42.8323 | -114.9038 | Billingsley Creek |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
9.6.2.1 Habitat actions |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
2001 | Draft TMDL subbasin assessment provided by IDEQ |
1998 | Middle Snake nutrient managementplan/TMDL completed by IDEQ |
1984 | Watershed water quality assessment completed by IDEQ |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
98002 | Snake River Native Salmonid Assessment | Data share & coordination of monitoring activities |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. Evaluate and assess waterswhed conditions to update the 1990 "Recommendation for Water Quality Improvement to the Billingsley Creek Agricultural LandUsers" and state land managers | a. Identify land management units/tracts, land owners/operators/managers, solicite participation for landuse inventory (includes upland and riparian) | 0.5 | $5,000 | Yes |
b. General inventory of cropland areas, grazing land areas, riparian areas, and other watershed nonpoint source land areas susceptable to erosion and overutilization | 1.0 | $12,500 | Yes | |
c. Develop watershed treatment alternatives with input from local, state, federal agencies, tribal, public and other watershed interests to address upland and riparian resource problems. | 0.3 | $5,000 | Yes | |
d. Prepare, print, display, and dispurse "Recommendation" report.. | 0.1 | $6,000 | ||
2. Develop conservation plans with landowners to address and correct the riparian and upland resource problems (NEPA addressed here through NRCS policy) | a. Prepare cooperator agreements with watershed participants, prepare 6-part cooperator folders, determine landowner and site-specific project objectives, inventory land resource, identify resource problems. | 5.0 | $5,000 | Yes |
b. Develop site-specific resource treatment alternatives, determine environmental effects of each, estimate installation and annual maintainence costs. | 5.0 | $5,000 | Yes | |
c. Prepare BMP specific designs and BMP management plans for each conservation plan, obtain site-specific engineering, geomorphology, soils, and plant materials assistence where necessary. | 5.0 | $5,000 | Yes | |
d. Develop a plan and implement appropriate measures to restore 3/4 miles of stream health to established levels within Billingsley Creek State Park. | 2.0 | $0 | ||
e. Develop a plan and implement steps to stablize 20 acres of slope along Billingsley Creek within Billingsley Creek State Park to prevent erosion and stream damage. | 2.0 | $0 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Evaluate and assess waterswhed conditions to update the 1990 "Recommendation for Water Quality Improvement to the Billingsley Creek Agricultural LandUsers" and state land managers | $0 | ||
2. Develop conservation plans with landowners to address and correct the riparian and upland resource problems (NEPA addressed here through NRCS policy). | 2004 | 2007 | $60,000 |
Outyear budgets for Planning and Design phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$15,000 | $15,000 | $15,000 | $15,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
3. Implement landowner conservation plans and watershed treatment measures | a. Install riparian fencing (total average cost $1.5/linear ft., 30,000 ft total) | 5.0 | $6,750 | Yes |
b. Install livestock/wildlife water facilities (total average cost is $5000 ea., 10 total) | 5.0 | $7,500 | Yes | |
c. Install in-stream barbs, etc. (total average cost is $1,000/ea., 30 total) | 5.0 | $7,500 | Yes | |
d. Install riparian/channel vegetation/revetments (average total cost is $5/ft.., 20,000 feet total) | 5.0 | $15,000 | Yes | |
e. Remove or replace old culverts (average total cost is $2,500 ea., 5 total) | 5.0 | $1,875 | Yes | |
f. Install upland sediment basins (average total cost is $1,500 ea, 7 total) | 5.0 | $1,575 | Yes | |
g. Install riparian buffers (average total cost is $80/ac. 80 acres total) | 5.0 | $960 | Yes | |
h. Install livestock, wildlife crossings (average total cost is $1,800 ea., 5 total) | 5.0 | $1,350 | Yes | |
i. Install watergaps (average total cost is $2,500 ea, 5 total) | 5.0 | $1,875 | Yes | |
j. Stabilize critical, erosive areas impacting riparian conditions (average total cost $700/ac. 50 acres total) | 3.0 | $5,250 | Yes | |
k. Inspect each BMP installation or application to ensure standards and specifications are met. | 5.0 | $5,000 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
3. Implement landowner conservation plans and watershed treatment measures | 2004 | 2007 | $134,550 |
Outyear budgets for Construction and Implementation phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$54,635 | $54,635 | $54,635 | $54,635 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
4. Evaluate previously installed and applied BMPs to ensure watershed objectives are being met. | a. Annually re-inspect BMPs to ensure operation and maintainence is occuring according to applicable specifications. Evaulate post-treatment effectiveness of BMPs through stream transects, riparian vegetation surveys, up-to-date photo points. | Ongoing | $5,000 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
4. Evaluate previously installed and applied BMPs to ensure watershed objectives are being met. | 2004 | 2007 | $20,000 |
Outyear budgets for Operations and Maintenance phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$5,000 | $5,000 | $5,000 | $5,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
5. Evaluate conservation plan BMP and watershed conservation treatment effectiveness on fish, wildlife and other environmental factors. | a. IDEQ will conduct water quality analysis on an ongoing basis, macroinvertebrate analysis included. | Ongoing | $0 | |
b. IDFG will evaluate fish populations, spawning success, and various in-stream habitat conditions (substrate, etc.) on an ongoing basis. | Ongoing | $3,000 | Yes | |
c. Watershed photo points, representative stream morphology transects, riparian greeenline reaches, and other established long-term monitoring stations will be evaluated on an ongoing basis, usually on a 3-5 year cycle. | Ongoing | $5,000 | Yes | |
d. Prepare annual report for dispursment to public, BPA, agencies, etc. | Ongoing | $500 | ||
6. Enhance the public's awareness of the watershed approach in meeting the holistic, ecologocally based objectives | a. Hold annual field tours, show-casing site-specific BMP installation and cooperation of private and state land owners/managers. | Ongoing | $1,500 | |
b. Prepare annual reports and quarterly newsletters and other media for public, local, state, federal agencies, tribal, and other interests in the ongoing activities and cooperation in the watershed. | Ongoing | $1,500 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
5. Evaluate conservation plan BMP and watershed conservation treatment effectiveness on fish, wildlife and other environmental factors. | 2004 | 2007 | $25,000 |
6. Enhance the public's awareness of the watershed approach in meeting the holistic, ecologocally based objectives | 2004 | 2007 | $15,000 |
Outyear budgets for Monitoring and Evaluation phase
FY 2004 | FY 2005 | FY 2006 | FY 2007 |
---|---|---|---|
$11,500 | $11,500 | $11,500 | $11,500 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2003 cost |
---|---|---|
Personnel | FTE: 0.15 of GCSD permanent staff | $3,000 |
Supplies | For annual reports, field tours, newsletters, etc. | $6,500 |
NEPA | Addressed through NRCS planning policy | $0 |
PIT tags | # of tags: NA | $0 |
Subcontractor | 1.0 staff for P/D, I/C, O&M, & M&E stages | $55,500 |
Other | BMP installation (75% of total cost) | $49,635 |
$114,635 |
Total estimated budget
Total FY 2003 cost | $114,635 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2003 budget request | $114,635 |
FY 2003 forecast from 2002 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
NRCS | Technical, engineering, supervision | $10,000 | in-kind |
ISCC | Administrative, technical | $2,000 | in-kind |
IDFG | Technical, monitoring | $10,000 | in-kind |
IDEQ | Technical, monitoring | $10,000 | in-kind |
GSCD | Administrative, awareness | $5,000 | in-kind |
Landowners | Installation & operation costs | $16,545 | cash |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable only if response is adequate
Mar 1, 2002
Comment:
A response is needed. Ties to fisheries biologists such as at IDFG need to be more strongly specified. More detail needs to be provided on monitoring or links to other monitoring efforts that would provide information on fish response. See the programmatic section at the beginning of this report. Details need to be given on prioritization of sites for restoration. Is there a watershed assessment that specifies needed actions? Are there potential benefits of using additional CRP enrollment in this project area?Comment:
Concerns expressed relative to Proposals 32012 and 33007 also apply to this project. In addition, CBFWA found that some of the work would be performed in a State Park and question whether it should be a BPA responsibility. CBFWA also found that there is a lack of coordination with the Tribes.Comment:
Fundable. Billingsley Creek is one of the largest spring creeks in the southern Idaho-Hagerman area and because of its natural high productivity offers one of the most promising opportunities for restoration of fisheries habitat and benefits, albeit for non-native rainbow and brown trout. Billingsley Creek has suffered from long-term habitat degradation from development of agriculture and aquaculture practices, such that restoration of the primary stream corridor will be expensive and may be intractable with current approaches and smaller-scale restoration projects. Previous small-scale restoration activities have largely failed.The response provided good indication of coordination with, and active support from, the Idaho Department of Fish & Game. Also encouraging are the signs of nascent activities to reverse a long and gradual history of man-caused change to Billingsley Creek. However, until those activities are better proven and private landowners are more involved, it remains risky to invest BPA funds here.
Comment: