FY 1999 proposal 199005500
Section 1. Administrative
Proposal title | Steelhead Supplementation Studies in Idaho Rivers |
Proposal ID | 199005500 |
Organization | Idaho Department of Fish and Game (IDFG) |
Proposal contact person or principal investigator |
Name | Alan Byrne |
Mailing address | IDFG - Fisheries Research
P.O. Box 25 Boise, ID 83709 |
Phone / email | 2084658404 / abyrne@idfg.state.id.us |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Lower Snake / Salmon, Clearwater |
Short description | Evaluate the feasibility of using artificial production to increase natural steelhead populations and to collect life history, genetic, and disease data from wild steelhead populations in Idaho. |
Target species | |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Section 3. Relationships to other projects
Project ID | Title | Description |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
Personnel |
|
$100,000 |
Fringe |
|
$35,000 |
Supplies |
|
$8,000 |
Operating |
|
$20,000 |
Capital |
|
$15,000 |
Tag |
|
$23,200 |
Travel |
|
$10,000 |
Subcontractor |
|
$10,000 |
Other |
|
$37,000 |
| $258,200 |
Total estimated budget
Total FY 1999 cost | $258,200 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $258,200 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Date:
May 13, 1998
Comment:
Criteria 1: Technical Criteria - Yes
Criteria 2: Objectives Criteria - Yes
Criteria 3: Milestones Criteria - Yes
Criteria 4: Resources Criteria - Yes:
Recommendation:
Fund
Date:
May 13, 1998
Comment:
Recommendation:
Adequate
Date:
Jun 18, 1998
Comment:
This proposal has three objectives. The first objective is to compare wild and hatchery returns, but returns have not been high enough to implement this objective. This should be done only with considerable caution, due to the extremely small numbers of fish remaining. The second objective is to evaluate whether returning hatchery adults spawn naturally. The third objective is to gather baseline background data. The baseline study ought to be done. The experimental design should be described in greater detail, but is adequate to establish that such important factors as replication, control, and power have been taken into account. The paired watershed design is a good approach and the power analysis establishes that an ecologically meaningful project can be conducted with the sample size possible.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$589,086 |
$589,086 |
$589,086 |
Sponsor comments: See comment at Council's website