FY 1999 proposal 199601200
Section 1. Administrative
Proposal title | Adult Fish Passage Improvement - Walla Walla River |
Proposal ID | 199601200 |
Organization | Confederated Tribes of the Umatilla Indian Reservation (CTUIR) |
Proposal contact person or principal investigator |
Name | Gary James |
Mailing address | P.O. Box 638 Pendleton, OR 97801 |
Phone / email | 5412764109 / jaburke@ucinet.com |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Lower Mid-Columbia / Walla Walla |
Short description | Provide for safe adult passage at several irrigation diversion dams in order to enhance summer steelhead and restore spring chinook populations in the Walla Walla River Basin. |
Target species | |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Section 3. Relationships to other projects
Project ID | Title | Description |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
Subcontractor |
|
$400,000 |
| $400,000 |
Total estimated budget
Total FY 1999 cost | $400,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $400,000 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Other budget explanation
Schedule Constraints: This is a cost share project with COE and any changes in their budget schedule would affect this funding request.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Return to Sponsor for Revision
Date:
May 13, 1998
Comment:
Technical Issue: Proposal still incomplete – resubmit in light of addressing those incomplete areas from FY98.Technical Issue: Explain the location and quantity of area that will be accessed from improved migration, quality of that habitat, and the long term benefits in terms of number of fish produced in the future and what it means in terms of a system-wide framework.
Management Issue: 25% of the total is cost shared with COE – is this COE BPA reimbursable?
Recommendation:
Fund
Date:
May 13, 1998
Comment:
Recommendation:
Adequate after revision
Date:
Jun 18, 1998
Comment:
The revised proposal provides sufficient technical justification and better historical context.
Recommendation:
Do Not Fund
Date:
Sep 20, 2003
Comment:
Recommendation:
Date:
Sep 20, 2003
Comment: