FY 1999 proposal 199701000
Section 1. Administrative
Proposal title | PIT Tag System Transition |
Proposal ID | 199701000 |
Organization | Bonneville Power Administration (BPA) |
Proposal contact person or principal investigator |
Name | John H. Rowan - EWI-4 |
Mailing address | P.O. Box 3621 Portland, OR 97208-3621 |
Phone / email | 5032304238 / jhrowan@bpa.gov |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Mainstem / Mainstem |
Short description | Replaces existing 400 kHz PIT tag detection system for juvenile salmonids with 134.2 kHz, ISO-based system for use within the Columbia River Basin; facilitates development and installation of 134.2 kHz adult salmonid detection equipment at mainstem dams. |
Target species | |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Section 3. Relationships to other projects
Project ID | Title | Description |
9008000 |
PTAGIS |
Project operates and maintains the PIT tag interrogation system in the Basin. |
8331900 |
New Marking and Monitoring Techniques for Fish |
Project is investigating PIT tag detection of adult salmonids based on the ISO frequency of 134.2 kHz. |
0 |
XXXXXX |
Many projects use PIT tags and the PIT tag detection system in the Basin for their research. |
9008001 |
PIT Tag Purchase |
Project purchases 400 kHz tags and will purchase 134.2 kHz ISO tags for use by researchers in the Columbia River Basin. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
Capital |
access structures; fiber optics and electrical repair/replace shields; portable readers |
$800,000 |
Subcontractor |
Destron Fearing; PSMFC; U.S. Army Corps of Engineers; NMFS-CZES Division |
$0 |
| $800,000 |
Total estimated budget
Total FY 1999 cost | $800,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $800,000 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Other budget explanation
Schedule Constraints: Adverse weather conditions could delay some of the on-site work at the projects. Inability of manufacturer to produce portable reader would affect schedule; this is not anticipated.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Date:
May 13, 1998
Comment:
Criteria 1: Technical Criteria - Yes
Criteria 2: Objectives Criteria - Yes
Criteria 3: Milestones Criteria - Yes
Criteria 4: Resources Criteria - Yes:
Recommendation:
Fund
Date:
May 13, 1998
Comment:
Recommendation:
Adequate
Date:
Jun 18, 1998
Comment:
ISRP reviewers appreciate the need to change from an interrogation system based on 400 kHz frequency to one based on 134.2 kHz frequency. Nevertheless, they considered that this proposal can benefit from expanded description. The budget only includes capital acquisitions or improvements without detail on the overall cost/benefits. They suggest that the proposal should ensure that the needs of all user groups will be satisfied.