Section 1. Administrative
Proposal title | Monitor and Evaluate the Spawning Distribution of Snake River Fall Chinook |
Proposal ID | 199801003 |
Organization | U.S. Fish and Wildlife Service (USFWS) |
Proposal contact person or principal investigator |
Name | Aaron Garcia |
Mailing address | USFWS-Idaho Fishery Resource Office P.O. Box 18 Ahsahka, ID 83520 |
Phone / email | 2084767242 / aaron_garcia@fws.gov |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Lower Snake / Lower Snake Mainstem |
Short description | Monitor and evaluate the spawning distribution of fall chinook salmon to determine if supplemented yearling hatchery fish spawn where intended, document redd distribution, and collect information on the spawning distribution of subyearling releases and… |
Target species | Snake River fall chinook salmon |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Section 3. Relationships to other projects
Project ID | Title | Description |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
Personnel |
|
$53,440 |
Fringe |
|
$11,920 |
Supplies |
|
$5,200 |
Operating |
|
$9,910 |
Travel |
|
$7,180 |
Indirect |
|
$30,068 |
Subcontractor |
|
$7,800 |
| $125,518 |
Total estimated budget
Total FY 1999 cost | $125,518 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $125,518 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Other budget explanation
Schedule Constraints: Progress may be slowed due to low return rates.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Date:
May 13, 1998
Comment:
Criteria 1: Technical Criteria - Yes
Criteria 2: Objectives Criteria - Yes
Criteria 3: Milestones Criteria - Yes
Criteria 4: Resources Criteria - Yes:
Recommendation:
Fund
Date:
May 13, 1998
Comment:
Recommendation:
Adequate
Date:
Jun 18, 1998
Comment:
ISRP reviewers appreciate this proposal for its clearly expressed procedures and tasks for evaluation of supplementation efforts. The reviewers also suggest that this project along with others dealing with fall chinook should be considered as part of a broader effort with an overall umbrella proposal that explains the relationships of and need for all subcomponents.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$52,000 |
$52,000 |
$52,000 |
Sponsor comments: See comment at Council's website