FY 2000 proposal 20524

Additional documents

TitleType
20524 Narrative Narrative

Section 1. Administrative

Proposal titleMulti-Year Walla Walla Anadromous Fish Plan
Proposal ID20524
OrganizationColumbia Basin Fish & Wildlife Authority (CBFWA)
Proposal contact person or principal investigator
NameTom Giese
Mailing address2501 SW First Ave., Suite 200 Portland, OR 97201
Phone / email5032290191 / tom@cbfwf.org
Manager authorizing this project
Review cycleFY 2000
Province / SubbasinColumbia Plateau / Walla Walla
Short description
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
9604600 Habitat coordination, planning and improvements.
20524 Multi-Year Plan Walla Walla Anadromous Fish Plan
9606400 Habitat coordination, planning and improvements.
9601200 Adult Fish Passage Improvement - WW River
9604601 Habitat enhancement, watershed coordination, habitat improvements.
9010 Habitat enhancement, watershed coordination, habitat improvements.
9601100 Juvenile Fish Passage Improvement - WW River

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2000 cost
Personnel $0
Fringe $0
Supplies $0
$0
Total estimated budget
Total FY 2000 cost$0
Amount anticipated from previously committed BPA funds$0
Total FY 2000 budget request$0
FY 2000 forecast from 1999$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
NA - Umbrella Proposal
Date:
Jun 15, 1999

Comment:

Recommendation: NA - Umbrella Proposal

Comments: It seems premature to fund any projects for multiple years until their need and effectiveness have been documented through an umbrella project that evaluates them in a larger context such as a subbasin plan. It would be helpful to have BPA fund 6 or 8 regional evaluators who oversee and report on results of subbasin activities. These individuals should be well trained in science and independent from the entities funded by BPA. Perhaps they could be viewed as extensions of the ISRP. Questions to be addressed would be to what extent is the collection of subbasin activities benefiting fish and wildlife? Is there fiscal accountability? Are the most cost-effective alternatives being implemented? Have limiting factors been identified and addressed? Prior to full implementation of the Walla Walla Anadromous Fish Plan the underlying limiting factors that have been identified, i.e. water quality and quantity, should be dealt with.


Recommendation:
Do Not Fund
Date:
Aug 20, 1999

Comment:


Recommendation:
Date:
Aug 20, 1999

Comment:

Technical Criteria 1: Met? NA -

Programmatic Criteria 2: Met? NA - Inadequate and is too general to fill the need for planning and integration.

Milestone Criteria 3: Met? NA -

Resource Criteria 4: Met? NA -