FY 2000 proposal 198343500
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
198343500 Narrative | Narrative |
198343500 Sponsor Response to the ISRP | Response |
Section 1. Administrative
Proposal title | Operate and Maintain Umatilla Hatchery Satellite Facilities |
Proposal ID | 198343500 |
Organization | Confederated Tribes of the Umatilla Indian Reservation (CTUIR) |
Proposal contact person or principal investigator | |
Name | Gary A. James |
Mailing address | P.O. Box 638 Pendleton, OR 97801 |
Phone / email | 5412764109 / jaburke@ucinet.com |
Manager authorizing this project | |
Review cycle | FY 2000 |
Province / Subbasin | Columbia Plateau / Umatilla |
Short description | Acclimate juvenile salmon and steelhead prior to release in the Umatilla Basin. Collect, hold and spawn broodstock and provide eggs to ODFW and other hatcheries for incubation, rearing and later release into the Umatilla Basin. |
Target species | Summer steelhead, coho, fall and spring chinook |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1998 | Acclimated and released 19.9 million summer steelhead, coho, and fall and spring chinook from project facilities from 1983 to 1998. |
1998 | Held and spawned approximatly 6,100 broodstock in project facilities from 1983 to 1998. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
8802200 | Umatilla Fish Passage Operations | The passage operations project provides adult recovery information and broodstock for spawning, and provide passage for outmigrating hatchery produced juveniles. |
NEOH Hatchery - Walla Walla Component - Design, and Construction | This project provides for design and construction of new artificial production facilities which will be operated under project no. 8343500 when completed. | |
8805302 | Umatilla Hatchery Supplement Facility Design, and Construction | Same as box above |
9000501 | Umatilla Natural Production M & E | The UBNPM&E project provides biological information related to the outcome of the production goals. |
8710001 | Umatilla River Basin Anadromous Fish Habitat Enhancement | The URBAFHE project provides increased habitat for fish utilization. |
9000500 | Umatilla Hatchery M & E | The UHM&E project provides biological information related to the operation of the satellite facilities and evaluates the success of the artificial production program. |
8902401 | Umatilla River WEID/Screens M & E | The URW/SM&E project provides biological information related to the operation of the production program. |
8343600 | Umatilla Passage Facilities O & M | The UPFO&M project assists in preventative and heavy maintenance at all Umatilla hatchery satellite facilities. |
Little White Salmon Hatchery O & M | LWSH provides fall and spring chinook smolts for acclimation and release into the Umatilla River basin. | |
8403300 | Umatilla Hatchery O & M (sub-proposal submitted separately) | |
8343500 | Umatilla Hatchery Satellite Facilities O & M (subject sub-proposal) | |
Umatilla Artificial Production O & M |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2000 cost |
---|---|---|
Personnel | 7.9 FTE | $287,401 |
Fringe | 28% | $80,472 |
Supplies | $30,720 | |
Operating | $88,897 | |
Travel | $25,735 | |
Indirect | 34% | $174,497 |
Other | (fish rearing/marking support serv. to USFWS) | $134,439 |
$822,161 |
Total estimated budget
Total FY 2000 cost | $822,161 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2000 budget request | $822,161 |
FY 2000 forecast from 1999 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Other budget explanation
Schedule Constraints: Availability of broodstock and smolt production levels below targets may constrain or limit satellite facility operations or schedules.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Recommendation: Delay funding until the proposal addresses specific deficiencies noted in the comments. This project should be included in an Independent Programmatic Review of the Umatilla and Walla Walla hatchery programs.Comments: A number of objectives listed here are also covered in other proposals, which raises the question of whether there is duplication of effort or a lack of coordination. The budget is not satisfactorily justified. The number of full time personnel seems high. No explanation is given for increased out-year costs. In fact, the proposal says it expects costs to reach a maximum of $661,000 in FY 1999, but shows $1,486,000 in FY 2000, increasing to $1,675,000 in FY 2004. It is not clear, given the high rate of straying of returning adults, that the acclimation facilities are accomplishing their presumed objective of encouraging return of adults to upstream areas. Is there any evidence that fish held in acclimation ponds are any more likely to return to the area as adults than fish released directly from the trucks?
Comment:
Comment:
Technical Criteria 1: Met? yes -Programmatic Criteria 2: Met? yes - O&M - na for these criteria?
Milestone Criteria 3: Met? yes -
Resource Criteria 4: Met? yes -
Comment:
Reducing staff time.Comment:
Fund existing activities. See programmatic recommendation for Umatilla and Walla Walla under project 8903500. Most concerns were addressed in the review response, except the issue of whether or not smolt-to-adult survival has been increased.Comment:
Comment:
[Decision made in 11-3-99 Council Meeting]; Address ISRP comments in BPA contractNW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$1,018,147 | $1,018,147 | $1,018,147 |
Sponsor comments: See comment at Council's website