FY 2000 proposal 198710002
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
198710002 Narrative | Narrative |
Section 1. Administrative
Proposal title | Protect and Enhance Anadromous Fish Habitat in the Umatilla River Subbasin |
Proposal ID | 198710002 |
Organization | Oregon Department of Fish and Wildlife (ODFW) |
Proposal contact person or principal investigator | |
Name | Tim Bailey |
Mailing address | 73471 Mytinger Lane Pendleton, OR 97801 |
Phone / email | 5412762344 / umatfish@oregontrail.net |
Manager authorizing this project | |
Review cycle | FY 2000 |
Province / Subbasin | Columbia Plateau / Umatilla |
Short description | Protect and enhance coldwater fish habitat on private lands in the Umatilla River basin in a manner that achieves self-sustaining salmonid populations and their associated habitat by utilizing natural stream functions to the fullest extent. |
Target species | Summer Steelhead |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1998 | Protected 11 miles of stream by installing 16 miles of fence and retrofitting existing projects with bioengineering treatments. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2000 cost |
---|---|---|
Personnel | full time bio, Tech 2, Tech 1 and 1-2 seasonals, Prgm Ma., Office specialist, ODFW engineers | $128,804 |
Fringe | 38% of personnel | $48,946 |
Supplies | New Implementation | $54,200 |
Operating | This includes only materials, vehicles, mileage, office supplies, tools & equipment | $34,337 |
Capital | Equipment Trailer and Utility Trailer | $15,000 |
Travel | Vehicle Mileage and Training Perdiem | $9,918 |
Indirect | Admin. Overhead @ 35.5%, excluding capital and subcontracts | $98,053 |
Subcontractor | Fence construction, instream construction, weed control | $75,900 |
$465,158 |
Total estimated budget
Total FY 2000 cost | $465,158 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2000 budget request | $465,158 |
FY 2000 forecast from 1999 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
U. S. Army Corps of Engineers (seeking) | instream materials and construction | $150,000 | unknown |
Governor's Watershed Enhancement Board (seeking) | Fencing materials | $27,750 | unknown |
ODFW Restoration & Enhancement Board (seeking) | Fence construction | $18,750 | unknown |
Landowner (secured) | Fence materials fence construction and fence line surveying | $50,000 | unknown |
ODFW - Wildlife (secured) | Fence materials | $3,900 | unknown |
Other budget explanation
Schedule Constraints: Catastrophic events such as flooding, wildfire, etc.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Recommendation: Fund. Review next year for reporting of results.Comments: This proposal is not a stand-alone project. It needs to be evaluated within the Umatilla Subbasin umbrella. The concept is good, but it is noted that only 3 of 13 projects are on schedule. Reviewers wondered how much of the budget goes for lease agreements.
Comment:
Comment:
Reducing implementation. Costs reduced as a result of improved efficiencies. General reduction in the scope of the project.Technically Sound? Yes
Aug 20, 1999
Comment:
Is this program cost effective? How many fish have returned lately? What has been the trend?Long term projects (programs) need to be evaluated for effectiveness to date.
Is it appropriate for BPA to fund conservation easements/ improvements on a NWPPC Member's property?
Proposal exceeds the page limit.
Comment:
[Decision made in 9-22-99 Council Meeting]NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$300,264 | $300,264 | $300,264 |
Sponsor comments: See comment at Council's website