Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
199800600 Narrative | Narrative |
Section 1. Administrative
Proposal title | PATH Technical Support - James J. Anderson |
Proposal ID | 199800600 |
Organization | James J. Anderson Consulting (Anderson Consulting) |
Proposal contact person or principal investigator | |
Name | James J. Anderson |
Mailing address | 3700 East Union Seattle WA 98122 |
Phone / email | 2065434772 / jim@fish.washington.edu |
Manager authorizing this project | |
Review cycle | FY 2000 |
Province / Subbasin | Mainstem/Systemwide / Systemwide |
Short description | Develop hypotheses underlying key salmon recovery management decisions, develop decision analyses to evaluate alternative management strategies, and assist in designing research monitoring and adaptive management experiments. |
Target species | Chinook and steelhead |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1998 | Developed alternative hypothesis on passage and extra mortality. Reviewed PATH documents |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
9700200 | PATH - UW technical support - Columbia Basin Research | Complimentary analysis will provide new alternatives to 9700200 |
8910800 | Monitoring and Evaluation modeling support - Columbia Basin Research | Complimentary applying analyses and adding results to models |
9600800 | ESSA PATH | Complimentary results will provide new alternatives to 9600800 |
20537 | Bonneville Power Administration Non-Discretionary Projects Umbrella |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2000 cost |
---|---|---|
Personnel | Salary, Fringe benefits and overhead 489 hrs @ $100/hr | $48,900 |
Fringe | $0 | |
Supplies | $0 | |
Travel | 4 trips to Portland @ $275 each | $1,100 |
$50,000 |
Total estimated budget
Total FY 2000 cost | $50,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2000 budget request | $50,000 |
FY 2000 forecast from 1999 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Other budget explanation
Schedule Constraints: None
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Recommendation: Do not fund. PATH, in its present form, with its present mission, should be phased out. A simpler process could be created to meet the continuing need for evaluation of the limited data now available to address management questions relative to the hydro biological opinion. A more ambitious and comprehensive scientific consensus process should be developed, somewhat along the lines of PATH, to address data collection design issues for the basin, to identify data needs that are critical to the actual management questions, and to ensure that data needs are met, to the extent practical, as quickly as possible, in a coordinated and efficient manner.Comments: Similar to project 8910800. Why is this separate from 9800600?
Comment:
Comment:
PATH projects reviewed in detail last year, little has changed. Question amount of hours. Needs to be related through an umbrella. Appears to duplicate work in Project #9700200.Money placed in BPA Tech Support Project Placeholder
Mar 1, 2000
Comment:
[Decision made in 12-7-99 Council Meeting]; Funding subject to independent review: BPA non-discretionary (Technical Support Project Placeholder)