Proposal title | PIT Tag Purchase and Distribution |
Proposal ID | 199808001 |
Organization | Pacific States Marine Fisheries Commission (PSMFC) |
Proposal contact person or principal investigator |
Name | Carter Stein |
Mailing address | 45 SE 82nd Dr., Suite 100 Gladstone, OR 97027-2522 |
Phone / email | 5036505400 / carters@psmfc.org |
Manager authorizing this project | |
Review cycle | FY 2000 |
Province / Subbasin | Mainstem/Systemwide / Systemwide |
Short description | Purchase and distribute PIT tags needed for BPA funded projects and track number of tags purchased and dollars spent on a per project basis. |
Target species | Chinook, Steelhead, Sockeye, Coho Salmon; |
Project ID | Title | Description |
9011 |
Characterize & Quantify Residual Steelhead in Clearwater River, Idaho |
PIT Tagging Project |
9104 |
Conduct Baseline Habitat and Pop. Dynamics Studies on Lampreys in Cedar Cr. |
PIT Tagging Project |
9105 |
Determine if Salmon are Successfully Spawning Below Lower Columbia MS Dams |
PIT Tagging Project |
9144 |
Monitor Natural Escapement & Productivity of John Day Basin Spring Chinook |
PIT Tagging Project |
8331900 |
Monitor Natural Escapement & Productivity of John Day Basin Spring Chinook |
PIT Tagging Project |
8332300 |
Monitor Smolts at the Head of Lower Granite Reservoir and Lower Granite Dam |
PIT Tagging Project |
8335000 |
Nez Perce Tribal Hatchery |
PIT Tagging Project |
8605000 |
White Sturgeon Mitigation and Restoration in the Columbia and Snake Rivers |
PIT Tagging Project |
8712700 |
Smolt Monitoring By Non-Federal Agencies |
PIT tagging project |
8712702 |
Comparative Survival Rate Study (CSS) of Hatchery Pit Tagged Chinook |
PIT tagging project |
8712703 |
Imnaha River Smolt Monitoring Program Project |
PIT tagging project |
8806400 |
Kootenai River White Sturgeon Studies and Conservation Aquaculture |
PIT tagging project |
8902401 |
Evaluate Juvenile Salmonid Outmigration and Survival in the Lower Umatilla |
PIT tagging project |
8906500 |
Annual Fish Marking - Missing Hatchery Production Groups |
PIT tagging project |
8909800 |
Salmon Supplementation Studies in Idaho Rivers |
PIT tagging project |
8909801 |
Salmon Supplementation Studies in Idaho Rivers |
PIT tagging project |
8909802 |
Salmon Supplementation Studies in Idaho Rivers |
PIT tagging project |
8909803 |
Salmon Supplementation Studies in Idaho Rivers |
PIT tagging project |
9000500 |
Umatilla Hatchery Monitoring and Evaluation |
PIT tagging project |
9000501 |
Umatilla and Walla Walla Basin Natural Production M&E Project |
PIT tagging project |
9005500 |
Steelhead Supplementation Studies in Idaho Rivers |
PIT tagging project |
9008000 |
Columbia Basin PIT Tag Information System |
PIT tagging project |
9102800 |
Monitoring Smolt Migration of Wild Snake River Spring/Summer Chinook |
PIT tagging project |
9102900 |
Life History and Survival of Fall Chinook Salmon in Columbia River Basin |
PIT tagging project |
9105500 |
Supplementation Fish Quality (Yakima) |
PIT tagging project |
9105500 |
Supplementation Fish Quality (Yakima) |
PIT tagging project |
9107100 |
Snake River Sockeye Salmon Habitat and Limnological Research |
PIT tagging project |
9107200 |
Redfish Lake Sockeye Salmon Captive Broodstock Program |
PIT tagging project |
9107300 |
Idaho Natural Production Monitoring and Evaluation Program (INPMEP) |
PIT tagging project |
9202604 |
Spring Chinook Salmon Early Life History |
PIT tagging project |
9302900 |
Survival Estimates for Passage of Juvenile Salmonids Through Dams & Res. |
PIT tagging project |
9401001 |
Mitigation for Excessive Drawdowns at Hungry Horse & Libby Reservoirs - Lib |
PIT tagging project |
9403400 |
9403400 |
PIT tagging project |
9506300 |
Yakima/Klickitat Monitoring and Evaluation Program |
PIT tagging project |
9603201 |
Begin Implementation of Year 1 of the K Pool Master Plan Program |
PIT tagging project |
9604000 |
Evaluate the Feasibility and Risks of Coho Reintroduction in Mid-Columbia |
PIT tagging project |
9700100 |
PIT Tag System Transition |
PIT tagging project |
9800702 |
Grande Ronde Supplementation - O&M/M&E - Nez Perce Tribe Lostine |
PIT tagging project |
9800703 |
Conduct Satellite Facility O&M and Program M&E for Grand Ronde Spring Chino |
PIT tagging project |
9801001 |
Grande Ronde Basin Spring Chinook Captive Broodstock Program |
PIT tagging project |
9801002 |
Captive Rearing Initiative for Salmon River Chinook Salmon |
PIT tagging project |
9801004 |
Monitor and Evaluate Yearling Snake R Fall Chinook Upstream of Lwr Granite |
PIT tagging project |
9801006 |
9801006 |
PIT tagging project |
9808001 |
PIT Tag Purchase and Distribution |
PIT tagging project |
|
USACE - Evaluation of Juvenile Salmonid Transportation |
PIT tagging project |
|
USACE - Estuarine Recovery of PIT-Tagged Juvenile Salmonids |
PIT tagging project |
|
LSRCP - Lower Snake River Compensation Program |
PIT tagging project |
|
USACE - Caspian Tern Predation on Juvenile Salmonids in the Columbia River |
PIT tagging project |
|
USACE - Evaluation of the Effects of Multiple Dam Passage on the Physiologi |
PIT tagging project |
|
USACE - Relative Survival of Juvenile Salmon Passing Through the Spillway o |
PIT tagging project |
|
USACE - Evaluation oo the Effects of Homing in Adult Chinook |
PIT tagging project |
|
USACE - Snake River Drawdown Modeling in CRISP |
PIT tagging project |
Schedule Constraints: 16-26 week lead time for tag manufacture.
This information was not provided on the original proposals, but was generated during the review process.
Comments:
The project may result in cost reductions for PIT tags needed for BPA funded projects and may also provide better accountability for tag use. However, no monitoring plans or assessment of unwanted side effects are explained. A system for tracking cost savings and improvements in data integrity of the PTAGIS data set should be implemented.