Section 1. Administrative
Proposal title | Northeast Oregon Hatchery Master Plan |
Proposal ID | 198805301 |
Organization | Nez Perce Tribe (NPT) |
Proposal contact person or principal investigator | |
Name | Becky Ashe |
Mailing address | P.O. Box 365 Lapwai, ID 83501 |
Phone / email | 2088437320 / beckya@nezperce.org |
Manager authorizing this project | Silas Whitman |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Blue Mountain / Imnaha |
Short description | Plan and develop conservation production facilities in the Imnaha and Grande Ronde rivers necessary to implement salmon recovery programs for native, ESA listed salmon. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1998 | Developed management plan for Imnaha and Lostine spring chinook salmon with co-managers. |
1998 | Completed well testing at proposed facility sites - Imnaha and Lostine rivers. |
1998 | Completed cultural resource surveys at proposed facility sites - Imnaha and Lostine rivers. |
1998 | Completed feasibility study on reintroduction of coho and sockeye salmon in the Grande Ronde River. |
1999 | Completed independent review of Lookingglass Hatchery. |
2000 | Completed Spring Chinook Master Plan and supporting documents - submitted to NPPC April 14. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Continue planning and development of spring chinook conservation facilities as proposed in the spring chinook master plan. | a. Preliminary and Final Design of proposed facilities on the Imnaha and Lostine rivers, including M&E facilities. | 1 | $1,305,000 | Yes |
b. Participate in Preliminary and Final Design of proposed facilities on the Imnaha and Lostine rivers. | 1 | $103,000 | ||
c. NEPA analysis of proposed alternative for facilities on the Imnaha and Lostine rivers. | 1 | $150,000 | Yes | |
d. Participate in NEPA analysis of proposed alternative for facilities on the Imnaha and Lostine rivers. | 1 | $85,000 | ||
e. Submit Preliminary Design and NEPA analysis to NPPC for Step 2 Review. Participate in NPPC Review Process. | 1 | $25,000 | ||
f. Continue to collect and analyze water temperature and flow information at proposed facility sites. | 2 | $25,000 | ||
g. Cost share funding of Imnaha River USGS gage. | 2 | $2,500 | Yes | |
h. Summarize existing biological information from monitoring and evaluation studies, including genetic stock structure; and develop M&E action plan (task) based on conceptual M&E framework. | 1 | $100,000 | ||
i. Perform conservation biology assessment of adult escapement goals. | 1 | $30,000 | Yes | |
h. Provide cultural resource consultation for NEPA and design work for proposed facilities. | 1 | $30,000 | Yes | |
i. Submit Final Design of proposed facilities to NPPC for Step 3 Review. Participate in NPPC Review Process. | 1 | $25,000 | ||
2. Develop a master plan for the transition of steelhead production in the Imnaha and Grande Ronde subbasins from mitigation to supplementation and restoration. | a. Determine critical uncertainties regarding the condition of steelhead populations in the Grande Ronde and Imnaha subbasins and develop a plan for collection of baseline data in appropriate subbasin tributaries, includes adult escapement feasibility. | 1 | $60,000 | Yes |
b. Collect and summarize existing information on population status, including base line genetic stock structure. | 1 | $180,000 | Yes | |
c. Conduct review of existing production facilities and the potential for modification to meet restoration program needs. | 1 | $30,000 | Yes | |
d. Identify potential options for new supplementation programs and/or modification of existing LSRCP production programs to implement restoration program. | 1 | $25,000 | ||
e. Identify potential site locations for adult trapping facilities, incubation and rearing facilities, stream-side incubators, acclimation and release facilities. | 1 | $10,000 | ||
3. Coordinate planning and development of NEOH facilities and programs with appropriate entities. | a. Provide facilitation of program development with NPPC, BPA, other tribal, state and federal agencies, Wallowa County. | 2 | $18,000 | Yes |
b. Facilitate and participate in the NEOH Planning and Coordination Team which will meet regularly to guide the project. | on-going | $30,000 | ||
b. Cooperatively develop appropriate Section 10 permit applications or 4(d) rule plans, Hatchery and Genetic Management Plans, and biological assessments for programs. | on-going | $25,000 | ||
c. Contact and coordinate with landowners of potential facility sites. | 3 | $10,000 | ||
e. Prepare and administer necessary subcontracts for work to be accomplished by subcontractors. | on-going | $18,560 | ||
f. Prepare project budgets, statement of work, project prioritization process, project review documents. | on-going | $9,000 | ||
4. Transfer of technology | a. Prepare and provide quarterly reports summarizing activities accomplished during the quarter. | on-going | $9,000 | |
b. Present reports on project activities and findings at Annual BPA/CBFWA Project Review and other appropriate forums. | on-going | $7,300 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
FY 2004 | FY 2002 | FY 2003 |
---|---|---|
$320,000 | $691,000 | $423,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
FY 2002 | FY 2003 |
---|---|
$5,320,000 | $8,540,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
FY 2004 | FY 2005 | FY 2003 |
---|---|---|
$983,680 | $1,042,700 | $928,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
FY 2004 | FY 2005 | FY 2002 | FY 2003 |
---|---|---|---|
$1,087,000 | $1,096,000 | $762,000 | $1,080,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Personnel | FTE: 3.7 | $162,835 |
Fringe | $47,093 | |
Supplies | $32,438 | |
Travel | $15,690 | |
Indirect | 26.6% | $58,804 |
NEPA | $150,000 | |
Subcontractor | $1,845,500 | |
$2,312,360 |
Total estimated budget
Total FY 2001 cost | $2,312,360 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $2,312,360 |
FY 2001 forecast from 2000 | $3,000,000 |
% change from forecast | -22.9% |
Reason for change in estimated budget
We initially anticipated preparation for construction of facilities (land purchase, site work, etc.) would begin in 2001. Updated projection of construction on this project will not begin until 2002 - see out year budget projections. Capital construction estimates are +/- 35% based on conceptual design in the master plan and will be refined during preliminary and final design steps.
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
CBFWA Funding Recommendation
Ongoing Funding: yes; New Funding: no
Jul 14, 2000
Comment:
The budget has been adjusted due to a change in the indirect cost rate.The project sponsors initially anticipated preparation for construction of facilities (land purchase, site work, etc.) would begin in 2001. Updated projection of construction on this project will not begin until 2002 - see out-year budget projections. Capital construction estimates are +/- 35% based on conceptual design in the master plan and will be refined during preliminary and final design steps.
Comment:
This project shows an ongoing total of $2,309,038 for FY2001. It was not clear that this is "new" money, that is, it was confusing as to whether this amount was to come from the capital construction placeholder. After clarification with Tom Geise of CBFWA, we determined the 2001 request was new money in addition to the placeholder. This needs to be clarified in the budget.Comment:
Depends on NPPC step 1 decisionNW Power and Conservation Council's FY 2006 Project Funding Review
capital
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$7,267,271 | $6,000,000 | $6,000,000 |
Sponsor comments: See comment at Council's website