Proposal title | Spokane Tribal Hatchery (Galbraith Springs) Operation and Maintenance |
Proposal ID | 199104600 |
Organization | Spokane Tribe of Indians (STOI) |
Proposal contact person or principal investigator |
Name | Tim Peone, Manager |
Mailing address | POB 100 Wellpinit, WA. 99040 |
Phone / email | 5092587297 / tpeone@aol.com |
Manager authorizing this project | Tim Peone, Manager |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Inter-Mountain / Lake Roosevelt |
Short description | Operate and maintain the Spokane Tribal Hatchery to aid in the restoration and enhancement of the Lake Roosevelt and Banks Lake fisheries. |
Target species | |
Year | Accomplishment |
1990 |
Contractual Agreement with the BPA for funding design, construction and O&M (25 yrs) of the Spokane Tribal Hatchery Project (Galbraith Springs). |
1991 |
Construction of Spokane Tribal Hatchery and initial operation; 1,674,577 fingerling kokanee planted and 33,510 kokanee and 326,461 rainbow fingerlings transferred to Lake Roosevelt (FDR) net pens. |
1992 |
819,220 kokanee fingerlings & 71,256 kokanee yearlings planted; 1,099,000 fingerling & 68,552 yearling kokanee transferred to Sherman Creek Hatchery (SCH); 424,395 rainbow fingerlings transferred to FDR net pens. |
1993 |
1,024,293 kokanee fingerlings & 21,190 kokanee yearlings planted; 635,267 fingerling & 72,508 yearling kokanee transferred to SCH; 40,305 kokanee & 446,798 rainbow fingerlings transferred to FDR net pens. |
1994 |
540,220 kokanee fingerlings & 29,111 kokanee yearlings planted; 1,087,161 fingerling, 90,881 yearling kokanee & 60,534 fingerling rainbow transferred to SCH; 288,046 rainbow fingerlings transferred to FDR net pens. |
1995 |
515,425 kokanee fingerlings & 59,825 kokanee yearlings planted; 210,634 yearling kokanee & 120,325 fingerling rainbow transferred to SCH; 164,328 kokanee & 288,739 rainbow fingerlings transferred to FDR net pens. |
1996 |
54,194 kokanee yearlings planted; 224,562 yearling kokanee & 146,380 fingerling rainbow transferred to SCH; 50,899 kokanee & 430,473 rainbow fingerlings transferred to FDR net pens. |
1997 |
381,513 kokanee fingerlings & 40,808 kokanee yearlings planted; 220,191 yearling kokanee & 150,801 fingerling rainbow transferred to SCH; 261,092 kokanee & 403,382 rainbow fingerlings transferred to FDR net pens. |
1998 |
823,844 kokanee fingerlings & 84,066 kokanee yearlings planted; 349,832 kokanee & 255,712 rainbow fingerlings transferred to SCH; 294,186 kokanee & 311,594 rainbow fingerlings transferred to FDR net pens. |
1999 |
808,505 kokanee fingerlings & 84,066 kokanee yearlings planted; 349,832 kokanee & 255,712 rainbow fingerlings transferred to SCH; 294,186 kokanee & 311,594 rainbow fingerlings transferred to FDR net pens. |
2000 |
1.5 million kokanee fingerlings, 522,456 kokanee yearlings and 608,000 rainbow trout fingerlings under production for release in 2000 and 2001. |
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Production of 1 million yearling kokanee, 550,000 yearling rainbow trout and 300,000 fingerling kokanee for release into Lake Roosevelt in 2001. |
a. Brood stock capture, egg collection/allotment, viral sampling and culturing. |
ongoing |
$88,636 |
|
|
b. Fry, fingerling and yearling rearing. Includes 100% marking of kokanee salmon. |
ongoing |
$139,902 |
|
|
c. Fish releasing and transferring. |
ongoing |
$93,006 |
|
|
d. Water development, regulation and monitoring. |
ongoing |
$98,636 |
|
|
e. Hatchery and grounds maintenance, culture protection and enhancement. |
ongoing |
$123,636 |
|
2. Artificial Production Review compliance. |
a. Implement reform measures in the form of initial review process using Hatchery and Genetics Management Plan. |
ongoing |
$1,208 |
|
3. Coordinate project through regional and local planning, programmatic review and implementation processes. |
a. Participate in NPPC amendment process. |
ongoing |
$1,208 |
|
|
b. Participate in inter-mountain province sub-basin planning process. |
ongoing |
$1,208 |
|
|
c. Coordinate activities through Lake Roosevelt Hatcheries and Fisheries Management Team. |
ongoing |
$1,208 |
|
|
d. Public information exchange through Lake Roosevelt Forum. |
ongoing |
$1,208 |
|
The change from the FY'00 estimate reflects costs for purchase of a fork lift @ $15,000, engineering and design for scoping new well and water conveyance system for construction in 2002 @ $10,000, maintenance for degrading facility structure which includes painting and replacing water damaged floor @ $5,000 and the dredging of the settling pond and surface water collection site currently filled in with nutrient and natural sediment @ $15,000.
No major changes goals, objectives or tasks.
This information was not provided on the original proposals, but was generated during the review process.