FY 2001 Action Plan proposal 200106700

Section 1. Administrative

Proposal titleRestore Passage Lower Lemhi / Salmon Rivers
Proposal ID200106700
OrganizationState of Idaho Office of Species Conservation (IOSC)
Proposal contact person or principal investigator
NameMike Larkin
Mailing addressP.O. Box 1336 Salmon, ID 83467
Phone / email2087562271 / mlarkin@idfg.state.id.us
Manager authorizing this projectGreg Schildwachter, IOSC
Review cycleFY 2001 Action Plan
Province / SubbasinMountain Snake / Salmon
Short descriptionThis proposal has three components: 1). Establish fish passage and reconfigure the L3 and L3A Diversions on the Lower Lemhi River 2). Reconfigure culvert fish passage barrier on Kinnikinic Creek 3). Reconfigure culvert fish passage barrier on Holman Creek
Target speciesChinook and steelhead salmon (anadromous and resident); resident and migratory bull trout; cutthroat trout
Project location
LatitudeLongitudeDescription
45.1515 -113.8033 L3 Diversion
45.1515 -113.8033 L3A Diversion
44.2788 -114.4023 Kinnikinic Creek
44.2526 -114.5863 Holman Creek
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1). Improve fish passage at L3 and L3A Diversions Construct and install fish ladders 12 months $140,000
2). Reconfigure culvert and fish passage barrier at Kinnikinic Creek Construct stair-step pools at outlet of the Highway 75 culvert 12 months $120,000
3). Reconfigure culvert and fish passage barrier at Holman Creek Construct stair-step pools at the outlet of the Highway 75 culvert 12 months $120,000
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: Non-applicable, see "Cost Sharing" $0
Fringe N/A $0
Supplies Materials for diversion structures, movement of gravel berms, fish ladder construction $330,000
Travel $3,000
Indirect $47,000
NEPA None $0
$380,000
Total estimated budget
Total FY 2001 cost$380,000
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$380,000
FY 2001 forecast from 2000$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
IDFG M&E - Surveys/Planning/Monitoring $25,000 in-kind
Model Watershed Project development, agency coordination $10,000 in-kind
ITD Hydraulic analysis $5,000 in-kind
DEQ Water quality monitoring $5,000 in-kind
Corps of Engineers Planning & Design $20,000 in-kind
NRCS Project Development $10,000 in-kind
BoR Planning & Design $20,000 in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Fundable. B-list
Date:
Jun 21, 2001

Comment:

Fundable, ranked at the top of the B list. This proposal satisfies the scope and criteria for project proposals. It is a good proposal to improve fish passage at three sites on the Lemhi and Salmon rivers. A fish ladder will be constructed and installed at the two (L3 and L3A) diversions on the Lemhi River. They will construct stair-step pools in Kinnikinic Creek, and in Holman Creek at Highway 75 culverts. The sites were identified as significant barriers to migrating fish by NMFS. The projects should in the long term provide benefits for the broods and population affected by the power system emergency. The budget is modest for construction projects and includes good cost share.

Details are lacking on the type of diversions involved on the Lemhi River. In general, the ISRP encourages the type of passage structure on the Holiday Ranch, John Day River, or infiltration galleries rather than fish ladders over diversion dams, if feasible. Assuming the sponsors have selected the best alternative, i.e., fish ladders, this project is fundable.


Recommendation:
Fund
Date:
Jun 29, 2001

Comment:


Recommendation:
Fund
Date:
Jul 12, 2001

Comment: